This document contains details regarding utility relocation work required for the FKC Middle Reach Capacity Correction Project Phase 1. The project, solicited under solicitation number 140R2020R0009, is being conducted by the Department of the Interior Bureau of Reclamation and involves constructing capacity corrections to the Friant-Kern Canal between mile markers 53+10 and 58+40. The document lists over 60 locations where existing electrical, communication, and gas utilities will need to be relocated, including the specific utility owners, sizes of lines, whether they are overhead or buried, and the planned relocation schedule between August and December 2021 or October 2022. Relocations will involve removing and replacing poles and buried lines at road and canal crossings as well as locations running parallel to roads and the canal.

View the file

Other files for this federal contract opportunity

Other files attached to FKC Middle Reach Capacity Correction Project Phase, newest first.
File Type Posted
Attachment_8_Amendment_0008_0008.pdf PDF
Sol_140R2020R0009_Amd_0008.pdf PDF
Amendment_0007_for_Solicitation_140R2020R0009_0007.pdf PDF
Sol_140R2020R0009_Amd_0007.pdf PDF
Attachment_7_Amendment_0006_0006.pdf PDF
Sol_140R2020R0009_Amd_0006.pdf PDF
Attachment_B_1_Amendment_No_0005_0005.xlsx XLSX spreadsheet
Attachment_42_Amendment_0005_0005.pdf PDF
Attachment_37_Amendment_No__0005_0005.pdf PDF
Attachment_35_Amendment_No__0005_0005.pdf PDF
Attachment_33_Amendment_No__0005_0005.pdf PDF
Attachment_32_Amendment_No__0005_0005.pdf PDF
Attachment_26_Amendment_No__0005_0005.pdf PDF
Attachment_10_Amendment_No_0005_0005.pdf PDF
Attachment_4_Amendment_No_0005_0005.pdf PDF
Attachment_2_Amendment_No_0005_0005.pdf PDF
Attachment_25_Amendment_No__0004_0004.pdf PDF
Attachment_21_Amendment_No__0004_0004.pdf PDF
Attachment_19_Amendment_No__0004_0004.pdf PDF
Attachment_15_Amendment_No__0004_0004.pdf PDF
Attachment_7_Amendment_No_0004_0004.pdf PDF
Attachment_14_Amendment_No__0004_0004.pdf PDF
Attachment_27_Amendment_No__0004_0004.pdf PDF
Attachment_24_Amendment_No__0004_0004.pdf PDF
Attachment_10_Amendment_No_0004_0004.pdf PDF
Drawing_GC-17_Attachment_21_Amendment_No__0003_0003.pdf PDF
Drawing_G-03_Attachment_18_Amendment_No__0003_0003.pdf PDF
Drawing_C-703_Attachment_16_Amendment_No__0003_0003.pdf PDF
Drawing_C-304_Attachment_14_Amendment_No__0003_0003.pdf PDF
Drawing_C-203_Attachment_6_Amendment_No__0003_0003.pdf PDF
Amendment_No__0003_for_Solicitation_140R2020R0009_0003.pdf PDF
Attachment_1_Amendment_No_0003_0003.pdf PDF
Attachment_B_1_Amendment_No_0003_0003.xlsx XLSX spreadsheet
Drawing_C-100_Attachment_5_Amendment_No__0003_0003.pdf PDF
Drawing_C-23_Attachment_4_Amendment_No__0003_0003.pdf PDF
Drawing_C-22_Attachment_3_Amendment_No__0003_0003.pdf PDF
Attachment_2_Amendment_No_0003_0003.pdf PDF
Attachment_5_-_PPI_Data_Revised_0002.xlsx XLSX spreadsheet
Attachment_B_1_Amendment_No_0002_0002.xlsx XLSX spreadsheet
General_Decision_Number_CA20210020_0002.pdf PDF
Attachment_No__3_-_FKC_Site_Visit_Agenda_and_Sign_in_Sheet_0002.pdf PDF
Sol_140R2020R0009_Amd_0002.pdf PDF
Attachment 3 - Past Performance Questionnaire.pdf PDF
Solicitation 140R2020R0009.pdf PDF
Attachment 13 - Drawing Part 4 of 5.pdf PDF
Attachment 13 - Drawing Part 2 of 5.pdf PDF
Attachment 11 - Geotechnical Data Report Friant-Kern Canal Middle Reach Capacity Correction Project.pdf PDF
Attachment 8 - Key Personnel.pdf PDF
Attachment 7- Release of Claims.pdf PDF
Sol_140R2020R0009.pdf PDF
Show all 50

FKC Middle Reach Capacity Correction Project Phase has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 29 Amendment No 0004 Solicitation No: 140R2020R0009 Specifications No. 20-C0907

STANTEC/184031016 CONSTRUCTION CONSTRAINTS AND SEQUENCING

FKC MIDDLE REACH CAPACITY CORRECTION PROJECT PHASE 1 PAGE 01 14 00-7980

UTILITY RELOCATION WORK BY OTHERS

Approx.

Station Utility (Type)

Approx.

Number of Poles to Relocate

Utility Size (in.)

Utility Owner Marker Dwg. No.

Location with

Respect to New Canal - Crossing or

Parallel

Road Relocation Schedule (Month

Ending Date)

5310+00 Electrical (Buried) 0 0 So Cal

Edison Distribution Powerunma rked C-22, C-23 Parallel

Ave 136 to Ave

August December

5322+43 Electrical (Overhead) 4 SoCal

Edison 12KV C-22 Parallel Ave 136 August

December

5361+71 Electrical (Overhead) 1 SoCal

Edison Distribution

Power C-23, C-203 Crossing Ave 128

August December

5483+25 Electrical (Overhead) 1 SoCal

Edison 66KV C-28, C-204 Crossing Ave 112

August December

5483+65 Communication (Buried) 4" AT&T Comms. C-28, C-204 Crossing Ave 112 August

December

5536+06 Electrical (Overhead) 1 SoCal

Edison 12KV C-30, C-100 Crossing

Deer Creek Check

August December

5542+98 Communication Friant Comms. C-30, C-100 Parallel

Deer Creek Check

August December

5563+78 Electrical (Overhead) 8 SoCal

Edison 12KV C-31 to C-32 Parallel

Deer Creek to

Terra Bella

August December

5588+00 Communication (Buried) AT&T Comms C-205 Crossing Terra

Bella August

December

5588+20 Gas 5.6” SoCal Gas High Pressure

C-32, C-205 Crossing Terra

Bella December

5588+40 Electrical

(Overhead)JPA

(AT&T)

2 SoCal Edison

Distribution Power

C-32, C-205 Crossing Terra

Bella August

December

5600+60 Electrical

(Overhead)JPA

(AT&T)

1 SoCal Edison

Distribution Power

C-33, C-206 Crossing Road

August

December

5663+50 Electrical

(Overhead)JPA

(AT&T)

1 SoCal Edison

Distribution Power

C-36, C-207 Crossing Ave 88

August December

5671+51 Electrical (Overhead) 2 SoCal

Edison 220 kV-HV C-36 Crossing South of Ave 88 October 2022

5672+56 Electrical (Overhead) 2 SoCal

Edison 220 kV-HV C-36 Crossing South of Ave 88 October 2022

5687+80 Electrical (Overhead) 2 SoCal

Edison Distribution

Power C-37 Parallel Terra Bella

December

5728+09 Electrical (Overhead) 1 SoCal

Edison 12KV C-38, C-208 Crossing Ave 80 December

5757+09 Electrical (Overhead) 1 SoCal

Edison 12KV C-39 Crossing Ave 74 December

5781+00.00 Communication (Buried) 2" Ducor

Telephone Comms. C-40 Crossing Road

August December

5781+00 Electrical (Overhead) 1 SoCal

Edison Distribution

Power C-40 Crossing Road

December

5800+00 Electrical (Overhead) 2 SoCal

Edison Distribution

Power C-41 Crossing Road

December

5827+00 (A) Electrical (Overhead) 1 SoCal

Edison 66kv C-42, C-209 Crossing Road

December

Attachment 29 Amendment No 0004 Solicitation No: 140R2020R0009 Specifications No. 20-C0907

STANTEC/184031016 CONSTRUCTION CONSTRAINTS AND SEQUENCING

FKC MIDDLE REACH CAPACITY CORRECTION PROJECT PHASE 1 PAGE 01 14 00-7980

Approx.

Station Utility (Type)

Approx.

Number of Poles to Relocate

Utility Size (in.)

Utility Owner Marker Dwg. No.

Location with

Respect to New Canal - Crossing or

Parallel

Road Relocation Schedule (Month

Ending Date)

5840+00 Electrical (Overhead) 1 SoCal

Edison Unmarked

Transmissio n Power

C-43 Crossing Ave 64 December

5841+00 Electrical (Overhead) 64 SoCal

Edison Distribution

Power C-43 to

C-44 Parallel South of Ave 64

December

A . Includes buried line and vault removal/replacement parallel to Road 192

UTILITY RELOCATION WORK BY OTHERS
A . Includes buried line and vault removal/replacement parallel to Road 192