Attachment_8_Clarifications_14-18_140P8322R0008_0002.pdf

PDF 136 KB Posted

Attached to
Rehab campground water system, Olympic NP, WA
Solicitation number
140P8322R0008
Issued by

About this file

This request for proposals solicits offers for a firm-fixed-price construction contract to rehabilitate the public water system at Heart o' the Hills campground in Olympic National Park, Washington. The scope of work includes replacing the well pump and controls, installing new electrical conduit and wiring, demolishing and replacing the water treatment building, upgrading the chlorine feed system, replacing water storage and distribution piping, installing backflow prevention, and directional drilling under Ennis Creek. Optional work involves inspecting and upgrading the wastewater system, replacing septic and pump tanks, upgrading electrical panels, and reinstalling lift station pumps. Offers are due approximately 30 days after posting. The contract will be set aside for small businesses with a NAICS code of 237110 and size standard of $39.5 million. The substantial completion date is June 24, 2023. The solicitation was issued by the National Park Service Pacific West Region.

View the file

Other files

File Type Posted
Attachment_4b_Revised_Wage_Determination_WA20220022_Building_6-24-22_0002.pdf PDF
Attachment_5a_Revised_Wage_Determination_WA20220044_Heavy_6-24-22_0002.pdf PDF
Attachment_9_Revised_Electrical_Specification_Sections_0002.pdf PDF
Sol_140P8322R0008_Amd_0002.pdf PDF
Attachment_7_Site_Visit_Notes_and_Clarifications_1-13__0001.pdf PDF
Attachment_4a_Revised_Wage_Determination_WA20220022_Building_6-17-22_0001.pdf PDF
Sol_140P8322R0008_Amd_0001.pdf PDF
Attachment_5_Wage_Determination_WA20220044_Heavy_2-25-22.pdf PDF
Form_2_-_Price_Schedule.docx DOCX document
Form_5_-_Relevant_Experience.docx DOCX document
Attachment_1_Specifications__Rehabilitate_Heart_o__the_Hills_Water_and_Wastewater_Systems_(May_2022).pdf PDF
Form_4_-_Limitations_on_Subcontracting_compliance_worksheet.xlsx XLSX spreadsheet
Form_3_-_FAR_representations.docx DOCX document
Attachment_2_Drawings__Rehabilitate_Heart_o__the_Hills_Water_and_Wastewater_System.pdf PDF
Sol_140P8322R0008.pdf PDF
FAQs_for_RFP_140P8322R0008.pdf PDF
Form_1_-_SF1442_140P8322R0008.pdf PDF
Attachment_3_Heart_O__the_Hills_Well_Log_-_Abandoned_(for_decommissioning).pdf PDF
Attachment_4_Wage_Determination_WA20220022_Building_2-25-22.pdf PDF
Form_6_-_General_References.docx DOCX document
Attachment_6_Notice_and_Certification_of_Vaccination_Form_(exp_2-28-25).pdf PDF
Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP #140P8322R0008, Rehabilitate Heart O’ the Hills water wastewater systems Olympic NP Attachment 8: Clarifications #14 - #18

Clarifications 14 – 18 for Solicitation #140P8322R0008

Amendment 2 posted on 6/30/22

This document provides clarifications based on submitted queries.

Clarifications 1 – 13 are in Attachment 7.

14. Spec 26 05 33, 3.1.A.2 does not list HDPE as an acceptable underground electrical conduit. Since the plans mention HDPE, should it be assumed that it is acceptable as an option?

Electrical conduit may be HDPE or PVC; either material is acceptable.

15. Spec 26 05 33, Section 2.4.B mentions underground polymer-concrete pull boxes. No pull boxes are shown on the plans, but they are needed due to the length of the conduit/wiring runs. Since these pull boxes will be installed in the roadway, these will need to be H20 rated. Please confirm that the contractor should add H20 rated pull boxes as needed, which will be installed in the roadway.

As noted in Attachment 7, Site Visit Notes and Clarifications 1-13, Q&A #3, the contractor and/or electrician is responsible for determining electrical requirements that will meet the intent of the water and wastewater functions as described, in accordance with the National Electrical Code (NEC) and other applicable requirements. This includes planning for an appropriate number of H20 traffic rated pull boxes, as need and where installed within the road corridor.

16. Spec 26 05 33, Section 3.3.A.1 mentions “CEC Article 300.5(A). Please confirm that this is a typo and should be referring to the “NEC – National Electrical Code”. There are multiple other references in the specifications to “CEC” as a standard. Please confirm these should all be changed to “NEC” instead.

CEC refers to “California Electrical Code” and is indeed a typo and oversight that impacts seven different spec sections. These sections have been revised and updated to reference the proper National Electrical Code section and are consolidated into Attachment 9, Revised Electrical Specification Section. Upon contract award, Attachment 1, Specifications, will be revised and updated to incorporate all changes made throughout the solicitation period.

17. Multiple plan sheets mention a 4-20mA signal for the pressure transmitter and other controls. If the contractor determines that a better signal can be achieved with a different type of signal, can an alternative signal be provided as long as it meets the performance requirements of the plans and specs?

Yes, the intent of the electrical portion of this project is for the contractor to determine how to best meet the performance requirements of the plans and specs. If a better signal can be achieved with a different type of signal alternative methods, approaches, and “or equal” materials/products will be considered through the submittal review process.

RFP #140P8322R0008, Rehabilitate Heart O’ the Hills water wastewater systems Olympic NP Attachment 8: Clarifications #14 - #18

18. Drawing C22 shows the new well pump controls fed from the existing power source, which appears to be the existing electrical panel adjacent to the well pump control panel.

Please confirm that the intent is to re-use the existing electrical panel and feeder at this location and not replace them. There was discussion on-site that the feeder between the transformer at the panel is direct buried and may be desired to be replaced in conduit.

The intent at this point is to re-use the existing electrical panel and feeder that powers the existing well pump and control panel. Any significant deficiencies in this existing power source and feeder that are discovered during construction may be addressed at that time through the contract modification process.