This is a Questions and Answers document for federal solicitation 140P2026R0098 (GRTE 237343) issued by the National Park Service for the comprehensive rehabilitation of the 4 Lazy 4 Ranch historic property. The solicitation calls for contractor design, permitting coordination, and construction of new foundations, utilities (water, sewer, fiber optics, fire alarm, and electrical systems), structural upgrades, and restoration work for the main lodge and multiple cabins. The project involves significant infrastructure installation including force main sewer and water systems requiring plowing methods in roadways, gravity sewer services (4" PVC SDR-35), new 2" HDPE water services to buildings, fire suppression systems, and electrical service upgrades. Key environmental and regulatory constraints include wildlife protection measures during elk calving season, asbestos and lead-based paint abatement coordination, Hantavirus and bird/bat guano remediation, and compliance with Wyoming Department of Environmental Quality (WYDEQ) permits already acquired by the government. The project includes base work and multiple optional bid items covering individual building renovations, with pricing structured by Contract Line Items (CLINs) for utilities, sitework, parking lot, individual cabins, and roadway/staging area restoration.
The 116 questions and responses address critical clarifications on construction methods, material specifications, design parameters, personnel requirements, hazardous materials scope, and work demarcation between base and optional CLINs. Notable resolutions include confirmation that plowing is the required force main installation method, all gravity sewer services must be 4" PVC (not 3" HDPE), the lift station wet well requires 72" diameter capacity, fire alarm cable may be installed unconcealed in walls and ceilings with conduit only where exposed, and the contractor is not responsible for water and sewer system design or permitting as WYDEQ permits are government-acquired. The contractor must perform groundwater monitoring, arrange third-party asbestos clearance testing through the government, remove bird and rodent droppings from all structures, and coordinate historic preservation work including log replacement and chimney lifting. Personnel requirements mandate separate Safety Officer and Quality Control representatives on-site at all times, though these roles may be filled by a single individual. The due date for proposal submission was November 20, 2026.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation 140P2026R0098 GRTE 237343 - Rehabilitate 4 Lazy 4 Ranch
Question No. Sheet or Reference Question Response
Force Main Installation Method: Section 33 14 15 subsection 1.1.A.2.C and Note 6 on Sheet C300 indicates the sewer force main to be plowed. Section 33 14 15 subsection 3.2.F.3 indicates “To keep within the proposed limits of disturbance, contractors may utilize alternative construction techniques such as plowing the force main”. Please confirm if open-cut trenching per Detail 1/C205 is acceptable provided work remains within the 15-ft limit of disturbance (Detail 3/C305) and one 10-ft travel lane is maintained (33 14 15 subsection 3.2.F.2).
Plowing is required for force main installation to expedite installation and minimize impact to Park operations and wildlife.
Plowing is the required method for force main installation in roadways; performance-based standards must be met.
Plowed Sections: If plowing is required, please confirm the bedding, compaction testing (33 14 15 subsection 3.2.G), and blue board insulation (33 14 15 subsection 3.2.F.7; Detail 2/C205) requirements for plowed sections.
Plowing is required for force main installation to expedite installation and minimize impact to Park operations and wildlife.
Pipe installation requirements per Details 1&2/C205 are applicable to open trench installation as required for gravity mains. Avoid force main insulation by ensuring minimum 6' cover over all force main pipe. If minimum cover is not possible, insulate above plowed pipe with minimum 2" thickness of overlapping blue board per foot of difference in cover between 6' and installed depth.
Cobbles and Boulders: The Geotechnical-Engineering Report (Section J, Attachment 6) identifies 5–45% cobbles and boulders. Please confirm whether open cut is permitted where cobbles or boulders prevent plowing.
Plowing will occur in roadway. This method has been previously employed successfully in the park. Pipe installation must comply with performance-based standards per Wyoming DEQ. Plowing; deflection and leakage requirements must be met.
Fiber in Common Trench: The area will be disturbed twice if the force main is plowed and the fiber is trenched in the same 15-ft strip (C300). Please confirm if the fiber can go in the same trench and the required separation if NPS approves open cut for the force main.
Yes, fiber to be installed in separate open cut trench.
5 Will contractors be able to camp or will NPS provide an RV/camper spots for contractors? Contractors cannot camp on site and NPS does not have any RV/camper spots available for contractor use.
On the main lodge, is there a species of wood spec'd for the wall base and/or the interior wood paneling?
I assume this specification would be applicable to all cabin renovations.
WOOD BASE:
See section 062000 "Finish Carpentry" 2.1.C.1. and 2.2.B. for wood base description and material type. See Room Finish Schedule on A905 sheets for wood base (WB-1) locations.
See 000 A901 for profile. Contractor to test and match existing trim materials but for bidding purposes, assume a Douglas fir.
WOOD PANELING:
There are two wood paneling materials used in the project (WP-1 & WP-2). See section 064200 "Wood Paneling" 2.1.B. & C. for description of both paneling types. See Room Finish Schedule on A905 sheets for wood paneling locations. See 000 A901 for profile.
Contractor to test and match existing materials but for bidding purposes, assume a knotty pine for WP-1 and a Douglas fir for WP-2.
Government provided materials- ( see spec section 01 11 00-3 B 3) Can we get clarification on if they plan to provide all site conduits including conduit for fiber optic, fire alarm system, power conduits and all associated handholes for each system? Or is it just for the Fiber Optics?
Materials will only be provided for the Fiber Optics system. See notes 7 & 8 on sheet C202.
Is there any order of importance regarding which cabins need to be renovated? Are there certain cabins you would like us to start rehabbing first?
The Bid Options are generally listed in order of priority, as reflected on the bid sheet, with the lodge as the first choice. This order may shift based on proposal pricing, but that is the intended priority.
Question No. Sheet or Reference Question Response
Is there a bath accessories/fixtures schedule? Bathroom accessories are shown on interior bathroom elevations and interior elevations.
They are identified with abbreviated callouts that correspond to products in specification section 10 28 00. Minor clarifications at bathroom elevations and in the specification will be included in a forthcoming addendum. Bathroom fixtures are scheduled on plumbing drawings.
Reference: Div 28 (fire alarm) The specifications require a minimum ¾" conduit to fire alarm devices. Is cable-only wiring to devices acceptable? If so, please revise the device wiring requirement.
All fire alarm system conductors shall be run in conduit.
11 Reference: E100 Keynotes 8-9 Please provide additional information for the grinder pump motor electrical connection.
See updated plans issued based on DEQ comments clouded as Revision 1. Specifically, see detail 4 on sheet 000 E004, and detail 4 on sheet 000 C204.
12 Who will accept the existing light fixtures retained for rehabilitation? Suggest coordinating with local lighting reps for this scope of work, including but not limited to: TLA North, Quantum Lighting, MH Lighting, and Northern Rockies Agency.
Reference: Div 26
a. Is NM (nonmetallic) cable approved for crawl spaces and protected areas?
b. Is wiring to devices (outlets, switches, lighting) required in painted EMT conduit for vertical runs?
a. Yes
b. Where exposed, yes painted EMT conduit shall be used.
Reference: E100 Keynote 4 Please confirm the existing feeder conductors and conduit from the LVE CT can to the existing disconnects are code compliant and reusable. Unless directed otherwise, no replacement of these conductors will be included without additional information.
Confirmed. Intent is to reuse these existing direct-bury feeders as shown in documents.
What is the intent for outlets on log walls?
a. Recessed in the logs, with holes bored to the crawl space? This requires NM or MC cable with access holes; conduit is very difficult to conceal in log walls.
b. Surface boxes mounted on the log face? Surface boxes (1-5/8" deep four-square or single-gang handy boxes) have visible knockouts and an industrial look, with conduit surface-mounted to the crawl space.
Varying log diameters will make the installation look uneven.
See detail 3 on sheet 000 E003.
As noted, preference is concealed. New wiring shall be concealed within walls, crawl space, and ceiling cavity to greatest extent possible. Where removal and replacement of log wall chinking is feasible, cabling shall be concealed behind interior wall chinking. NM or MC cable is allowed where concealed. Reuse existing path where possible. All routing shall be planned and approved by the Contracting Officer prior to implementation.
Existing historic building components, including logs, may not be drilled or otherwise damaged to create pathway for electrical cabling.
Where exposed surface mount routing is necessary, wiring shall be provided in painted EMT conduit, run vertically from crawl space or ceiling. Surface mount boxes shall be painted too.
Reference: Div 26 (grounding and bonding); Div 22
a. Is the existing water service to the cabins and lodge metal or PVC?
b. If metal, are service bonding jumpers required across dielectric connections?
c. Interior domestic water is copper per the specifications. Please confirm bonding requirements.
a. All existing water services to the cabins are being removed and replaced per contract documents. See civil and plumbing documents.
b. Yes, as per NEC 250.68(B) and specification 260526 part 3.4.D.
c. Bonding is required per NEC 250.104(A).
a. Section 26 05 44 lists several acceptable products. Which is preferred for this project?
b. What is required at conduit penetrations through cabin floors to surface-mounted outlets on log walls?
Is silicone around the conduit acceptable?
c. Is silicone acceptable at NM cable penetrations through 2x4 plates to the crawl space?
a. Varies by application. See "Part 3 - Execution" portion of specification section 260544 for application of products depending on wall type, penetration location, etc.
b. Yes, unless any fire ratings require fire caulking. Coordinate with GC for flooring finish around exposed conduit penetrations and also provide escutcheon plates around exposed conduit penetrations.
c. Yes, unless any fire ratings require fire caulking.
Are the exposed ceilings that remain to be stripped and/or refinished? I assume this would be the same requirement for all cabins?
Reference: Main Lodge - 399/A601
Reflected ceiling plan notes require all interior ceiling components to be cleaned; finish shedule notes describe the cleaning method. Finish schedule notes specify that all interior beams and purlins are to be finished. The exposed underside of interior wood plank roof decking is to remain unfinished. All exterior exposed decking shall be finished. Please see drawings references below.
Per A601, Reflected Ceiling Plan Note #7:
CLEAN AND FINISH ALL EXPOSED STRUCTURE INCLUDING BEAMS, JOIST, AND
DECKING AT BUILDING INTERIOR & EXTERIOR.
Per A905, Finish Schedule General Note #1:
ICL-1 (GENERAL INTERIOR CLEANING TREATMENT) AT ALL (E) INTERIOR
SURFACES.
Per A905, Finish Schedule General Note #2:
ST-1 AT ALL INTERIOR LOG AND LB-1 SURFACES INCLUDING WALLS, COLUMNS,
BEAMS, AND PERLINS. APPLY FINISH PRIOR TO ANY CONSTRUCTION THAT
WOULD BLOCK ACCESS TO SUCH SURFACES.
RFI: I don't believe the crawls depths are called out. We understand that the bottom of footer needs to be 34" below grade per 399/S201. Is there a minimum stem wall height for the Main Lodge? I assume this height will be applicable to all cabins.
The height of the stem wall shall be as required to meet minimum depth requirements and top of stem wall to grade requirements as shown on the architectural drawings including sheet 000 A803.
the specs 33 14 15 and plans for the Sewer and Water force main's don't specify the SDR or if the hdpe needs to be CTS or IPS sized. There is one mention that the grinder/lift station piping is to be "HDPE PE 4710 CTS". CTS sizing stops at 2" max. IPS is more common and available, would IPS SDR 11 PE 4710 HDPE be acceptable for all hdpe sewer service?
Yes, IPS SDR 11 HDPE is acceptable for force main piping and the pressure sewer service from the Caretaker's Cabin.
21 Pipe size and material on C300 to the caretakers cabin is not specified. Should we assume 3" hdpe to the grinder and 2" hdpe to the 4" force main?
Specify 4" PVC to the grinder as per gravity sewer piping. Pressure service to be 2" SDR11
HDPE.
Spec 33 14 15 indicates water service to be "HDPE PE 4710 CTS", however CTS sizing stops at 2" max. IPS is more common and available, would IPS SDR 11 PE 4710 HDPE be acceptable for the wall water pipe?
IPS SDR 11 HDPE is acceptable for water services.
23 Can you confirm the size of pipe for water service to buildings is 2" HDPE? Water services are to be 2" HDPE
Are there limitations/closures due to Elk calving season? Yes. Refer to Summary of Work (01 11 00 -6) Wildlife- Related Work Schedule chart and
Environmental Protection (01 35 13.05-3) Wildlife Protection section, for additonal information.
25 Water main
Water main symbols (C400, sheet 35). Two symbols resembling a “Z” or “N” appear near the valves at Sta. 3+42.29 and 4+69.90. Are these part of the valve notation or separate items we should include in the bid? If separate, please identify the required items and applicable detail.
Symbol (shown below) is the tracer wire termination block on 3/C203.
What is the power situation going to look like? I noticed at the site walk that there were outlets in the buildings, but I understand that there is currently not power. Will that be turned on at any point? Will a generator be necessary for the entire duration? I also understand if that is yet to be determined, but whatever information you have would be greatly appreciated.
Please see specification section 01 50 00 - TEMPORARY FACILITIES AND CONTROLS for information regarding construction power sources and associated general contractor requirements.
27 Water and sewer design scope
Water and sewer design scope. The solicitation calls for contractor design, but the issued drawings already show pipe sizes, alignments, profiles, and details. Can we bid the systems as drawn, with field verification and standard submittals? If additional engineering is required, please clarify what remains to be designed and whether we should include sealed drawings, calculations, or permit revisions
Yes, bid water and sewer systems as designed. Additional engineering is not required.
28 Site utility permit question
Section C (page 10 of 67); specification 01 11 00 section 1.2.B.2, and C201 notes require the Contractor to design and permit the site utilities. Specification 01 31 00 section 1.9 states the Government acquired the WYDEQ Permit to Construct.
Please confirm Contractor is not required to design and permit site utilities and that contractor design is limited to field investigations, submittals, CO-approved adjustments, as-built drawings, and closeout documents
Confirmed. Contractor is not required to design and permit site water and waste utilities.
WYDEQ permit is acquired.
29 Specialize consultants
Are bidders required to include all specialized consultants. Could you clarify whether one person must be dedicated to each of these roles for the full lifecycle of the project.
Historic Preservation Specialist Environmental Manager Wildlife compliance specialist Safety officer Testing agencies
a. The Superintendent cannot serve as the Safety Officer or Quality Control Representative.
One individual may serve as both Safety Officer and Quality Control Representative. Both positions must be staffed on site at all times during construction.
b. Historic Preservation, Environmental Manager, Wildlife Compliance Specialist are consultants to contractor. These posittions may serve in collateral roles, provided the individual is qualified. These responsibilities may be shared among personnel or assigned as additional duties to an individual’s primary position. c. Third party testing agencies are to sub-contracted by contractor as per plans and specifications
30 Roles Can project Superintendent play the role of Safety Manager? No. The Superintendent cannot serve as the Safety Officer or Quality Control
Representative. One individual may serve as both Safety Officer and Quality Control Representative. Both positions must be staffed on site at all times during construction.
31 Snow removal Can you clarify the limits of where NPS will complete snow removal and access road maintenance throughout the project and where Contractor will be responsible?
Snow is typically plowed by the park to the area around the Menors Crossing vault toilet.
Contractor is responsible for all snow plowing required for site access.
32 Schedule Regarding the Proposal Schedule, with the base bid and optional bid items, does NPS want three separate schedules or one holistic schedule assuming all options are awarded?
Contractors shall provide one comprehensive schedule that includes the base bid and all options, assuming all options are awarded. The schedule must fall into the period of performance specified in the specifications.
33 Storage Will Government-owned buildings be available for storage? No
34 Site
How will the property development (parking lot and other dirt work) be covered with the bid schedule?
There isn’t any separate call out for that.
Reference 01 27 00 Definition of Contract Line Items. CLIN 11 Sitework - Parking Lot.
CLIN 12 Sitework - Roadway and Staging Area Restoration. Note: Each facility has site work included within their associated CLINs. Staging Area restoration in CLIN 12 would only be for staging established on roads and remaining site work not captured in other CLINs. Staging areas, established in areas other than existing parking areas or roads, would be expected to be restored if CLIN 12 was not awarded.
35 CO answer In the event of conflicts between drawings and specifications, which governs? See clause FAR 52.236-21. Specs govern over drawings, but the order or precedence is described in this FAR cluase.
36 Change orders How will unforeseen structural deterioration be handled (Change order or is it Contractor Full Responsibility)? Examples include (Hidden rot, Insect damage, Concealed water damage, Deteriorated logs, Damaged framing and Unknown utility conditions)
Some structural deterioration is called out in the contract documents, so please pay close attention to these details. Anything not described in the contract documents would be handled pursuant to FAR 52.236-2 Differing Site Conditions.
37 CMR Will NPS provide direct oversight during historic restoration activities? No. Direct oversight during historic restoration activities is contractor’s responsibility.
38 Foundations During the walkthrough it was mentioned that the River Cabin and the New Cabin are the only structures that are not getting a new foundation, can you clarify that the Ice House and Mouse House are also not getting a new foundations?
The River Cabin and the New Cabin are the only housing structures that are not getting a new foundation. The Ice House and Mouse House (storage buildings) are also not getting new foundations. All other buildings are getting new foundations.
39 Cabin leech fields
Where are the existing leech fields and what happens to them once the cabins are connected to the sewer line?
The cabins and lodge abandoned leech fields are not surveyed. NPS assumes they exit the back of the cabins. These are abandoned in place. Given the site’s historic significance, the contractor will encounter undocumented abandoned utilities during construction and is expected to identify to CMR/Park staff and resolve/work though conflicts.
40 sewer Do the Force Main services need to be plowed as well? Force main service laterals for caretaker and new cabin do not need to be plowed.
41 CO
Reference: Att. 01 Dwgs 000 S001 General Requirements – Discrepancies (Dwg p.65); FAR 52.236-21 Sheet S001 states that where documents conflict the Contractor is "deemed to have included in the price the most expensive way of completing the work" and that conflicts are not a basis for adjustment. Please confirm that FAR 52.236-21 governs the resolution of discrepancies, that the Contracting Officer determines which document governs, and that the S001 paragraph is deleted.
Please ignore that statement at the top of pg 65 (sheet 000 S001) of the drawings. FAR 52.236-21 will govern here.
42 Personnel roles
Reference: Section H SR 6 Key Personnel (Sol. p.19); FAR 52.236-6; Att. 02 Specs 01 40 00 ¶1.5.B.1–3 (p.102); 01 35 23 ¶1.4.B (p.88); 01 74 19 ¶3.1.B (p.178) SR 6 lists four key personnel (Project Manager, Superintendent, QC Manager, Safety Manager); 01 40 00 states the QC Supervisor "shall be assigned no other duties"; and 01 74 19 requires a full-time Waste Management Coordinator. Given the remote site and residential-scale buildings, please confirm whether (a) the Project Manager may be off-site with periodic visits; (b) the Superintendent may also serve as Safety Manager/SSHO; (c) one qualified individual may serve as Superintendent, QC Manager and SSHO, with a named alternate; and (d) the Waste Management Coordinator may be a collateral duty. Additional Questions – Listed in Descending Order of Priority
The Project Manager may be off-site but must make periodic site visits. The Superintendent cannot serve as the Safety Officer or Quality Control Officer. However, one individual may fulfill both the Safety Officer and Quality Control Officer roles. The Waste Management Coordinator may be assigned as a collateral duty in addition to an individual's primary responsibilities.
43 Spec 28 46 21-fire alarm
Specification section 28 46 21 paragraph 1.13 mentions an annual service contract to the Owner. What should be included in the service contract? Is this to cover system monitoring and/ or annual testing services?
Annual service contract to the Owner will not required.
44 Spec 28 46 21-fire alarm
Specification section 28 46 21 paragraph 3.7G requires the contractor to provide the first annual test one year after substantial completion. However, Grand Teton park has a maintenance contract for all fire alarm and fire suppression maintenance. Will this contract cover the first annual inspection or will the maintenance of these fire systems be added to the existing maintenance contract?
First annual test after substantial completion will not required. A final integrated fire alarm and sprinkler test, to include all facilities reabilitated by contract, will be required by AHJ for acceptance and occupancy.
When removing asbestos vinyl flooring and mastic, it is often necessary to remove floor sub straight.
Does this have a historical impact or is sub straight removal an approved method for eliminating hazardous materials?
Generally, removal of historic building substrates, currently scheduled to remain, should be avoided. However, substrate removal is an acceptable means of abatement should other methods not be feasible. Prior to removal of asbestos containing flooring material, determine the extent of substrate removal required. As new flooring will be installed at all locations where asbestos containing flooring material exists, substrate removal will be allowed with Contracting Officer approval.
If substrates are removed, contractor will be required to replace them with new plywood floor decking.
46 Roof shingles The current specification for shingles is for GAF HDZ RS. I believe the RS version of those shingles is unavailable in our market. I wanted to confirm that standard GAF HDZ shingles can be used here.
Standard GAF HDZ shingles appear to meet the requirements of specification section 07 3113. Follow procedures for substitutions; see Section 01 67 00 – Product Requirements.
47 Roof detail The plans show a Reglet counterflashing detail for roof to wall flashing at the logs. I wanted to confirm that this is also the intended detail for roof to wall flashing at the chimneys? This would require us to cut a kerf into the existing chimney masonry to install counterflashing.
Please see detail 3/399 A801 illustrating roof to wall flashing at chimneys.
Removal of lead-based paint (LBP) components May all components identified as having LBP be removed and disposed of in their entirety rather than stripped of paint? Please identify any components that must be retained, stripped, or otherwise treated in place, including any salvage or historic preservation requirements.
Lead paint shall be removed without removal or damage to existing historic building components that are scheduled to remain, to be salvaged, or to be refinished or restored, per plans and documents. Only building components that are scheduled for removal may be removed and disposed of.
Removal of subfloor beneath asbestos-containing sheet vinyl May the abatement contractor remove and dispose of the sheet vinyl, inseparable mastic, and underlying subfloor together as asbestos-containing waste, rather than removing the flooring and mastic from the subfloor? Please identify any areas where the subfloor must remain and confirm who is responsible for replacement if removal is permitted.
Generally, removal of historic building substrates, currently scheduled to remain, should be avoided. However, substrate removal is an acceptable means of abatement should other methods not be feasible. Prior to removal of asbestos containing flooring material, determine the extent of substrate removal required. As new flooring will be installed at all locations where asbestos containing flooring material exists, substrate removal will be allowed with Contracting Officer approval.
If substrates are removed, contractor will be required to replace them with new plywood floor decking.
50 Temp power Temporary power. Will electrical power be available for contractor use at each building, or must contractors provide their own generators and temporary power distribution? If power is available, please confirm the connection locations, voltage, and available amperage.
Power is available on site for the Contractor to use. Contractor may establish temporay power distribution as needed to execute work.
51 Structural - 411
The schedule on 000 - G008 states that cabin 411 requires structural upgrades to the foundation. Sheet 411 - S201 does not call out any structural upgrades. 1) Can you please clarify whether there are structural upgrades to the foundation on cabin 411. 2) If there are upgrades, please clarify what they entail.
1&2) Structural upgrades are limited to connections between the existing floor system and the existing foundation as illustrated on 8/000 S402.
52 Building foundation
Regarding cabin 404, the south side of the building sits on an existing foundation. Is the existing foundation to be demolished and receive a new foundation along with the rest of the building?
At Cabin 404, the entire existing foundation is to be removed and replaced per the architectural and structural drawings.
53 Base/Bid options pricing
Reference: Att. 02 Specs 01 27 00 ¶3.1.A–D (utilities "to within 5 feet of each structure"); Att. 01 Dwgs 000 F004 Riser Legend 1–2 ("site contractor" to tee inside building, Dwg p.91); 000 E100 KN 5 Base utility CLINs terminate 5 ft outside each building, while F004 has the "site contractor" carrying the service to a tee inside the building. Please confirm the work from 5 ft outside through the new foundation to the interior connection (sleeves, insulation, penetrations) for water, sewer, power, fiber and FA conduit is included in each building's option CLIN, and that the Base CLINs terminate with capped, marked stubs 5 ft outside.
The division of work between CLINs, as described in the question, is correct.
54 Lead paint
There are several places in which lead paint was identified. There are a few ways to remove said paint, but I wanted to know if you have any preferences to methods used. For example, the cleanest and most permanent option is to just remove the wood/trim that is painted, but if that wood has to be preserved, an option like using a solvent works well but has the potential to stain the wood.
Lead paint shall be removed without removal or damage to existing historic building components, including trims and doors, that are scheduled to remain, to be salvaged, or to be refinished or restored. Only building components that are scheduled for removal may be removed and disposed of.
RFI: Is trenching an acceptable excavation alternative to "plowing method?"
Per 33 14 15 - 1 "Construction technique for the sewer force main along the gravel road alignment from Moose to 4 Lazy F as noted on the drawings shall be constructed via plowing methods"
Plowing is required for force main installation to expedite installation and minimize impact to Park operations and wildlife.
Plowing is the required method for force main installation in roadways; performance-based standards must be met.
C306 indicates a 3" pvc lateral off of the 6" pvc, however C310 indates the 3" service as HDPE. Which material is correct?
Sewer service requirements have been updated following DEQ review. All gravity sewer services are to be 4" PVC. Reference updated drawings issued with ammendment.
Gravity sewer services and cleanouts (C204, C307–C311). The profiles show 3-inch HDPE, while C204 shows a PVC cleanout adapter and 4-inch minimum pipe at the dual cleanout. Please confirm the required cleanout size and material and the acceptable HDPE-to-PVC transition. At the bends and wyes, is butt fusion acceptable with the internal beads left in place, or is another joining method required?
May we propose 3-inch Schedule 40 PVC as an alternate for the gravity services?
Gravity sewer services are to be 4" PVC, see most recent planset following DEQ permitting (marked as Revision 01).
The gravity sewer service size and material differ between the drawings and the specifications:
Drawings: Profiles C307 through C311 label the building services as 3" HDPE, with no DR or joining method.
Specifications:
Section 33 14 15, §2.2.A.3, requires sewer services of PVC SDR-35, with fittings of the same material.
Detail 1/C204 calls for a 4" minimum sewer pipe.
The Water/Sewer Design Report, §9.c.iii, states that gravity services will be 4" in diameter.
PVC SDR-35 (ASTM D3034) is standard size starting at 4" and greater. Under FAR 52.236-21(b)(1), the specifications govern, however the size shown on the profiles is a discrepancy in the figures, so we request a written determination under FAR 52.236-21(b)(2).
Please confirm:
Gravity sewer services will be 4" PVC SDR-35 (ASTM D3034) with elastomeric-gasket bell-and-spigot joints, per Section 33 14 15 §2.2.A.3.
If 3" HDPE is required instead, please provide:
the DR or pressure class;
the joining method (butt fusion, electrofusion or other);
the required transition fittings at the PVC SDR-35 wyes on the main and at the PVC DWV cleanout adapter in Detail 2/C204.
Gravity sewer services are to be 4" PVC, see most recent planset following DEQ permitting (marked as Revision 01). Reference updated civil sheets issued with this ammendment (marked as Revision 1).
Reference: Div 26
How are exterior sconces to be fed?
a. Drill down through the logs from the roof to a routed box opening?
b. Surface conduit to the box and light?
Exact means and methods are not dictated, however same guideline applies to lights as is noted in answer above for outlets on log walls (please see Q/A 16). New wiring shall be concealed within walls, crawl space, and ceiling cavity to greatest extent possible. Where exposed surface mount routing is necessary, wiring shall be provided in painted EMT conduit/boxes and shall be surface mounted on the interior side of the wall. At log wall locations, exterior junction boxes shall be set in trim mounted to the exterior face of the log wall. Please see the revised Sheet 000-A804.
All the 6" sewer on the plans is 3034 pvc except on C308, is that a mistake? All 6" sewer pipe is to be SDR35 (ASTM D3034D) PVC. Updated civil sheets issued with this ammendment (marked as Revision 1) specify this.
Survey Data – Remaining Structures:
Section 01 35 23, 1.2.A.4 lists Hantavirus as a site-specific hazard. Section 02 85 00, 1.1.B.3.d lists Cryptococcus, Histoplasmosis, and Psittacosis. Attachment 4 (Indoor Air Sampling for Histoplasma capsulatum, Northern Industrial Hygiene, July 8, 2025) covers the Main Lodge only and includes no rodent or Hantavirus sampling. Please provide any survey or sampling data for the remaining structures rated on Sheet G007.
Removal of bird, bat, and rodent dropping shall be performed as described in Section 02 8500. Bird, bat and rodent droppings shall be removed from all structures. No additional sampling data is available.
Will all electrical material need to meet BABA requirements? Will this include the fire alarm system as well?
52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022) and 52.225- 10 have been included in the solicitation. These two clauses will govern what materials fall under the Buy American Act. Generally speaking, COTS items are exempt from Buy American requirements.
Cleaning and preparation before abatement Will each building be cleaned and cleared of contents, debris, and animal waste before the abatement contractor mobilizes? If preparation is included in our scope, please define the required work by building, including how it relates to the guano cleanup scope.
No additional cleaning by NPS will occur prior to contractor mobilization. Contractor shall coordinate clearing of contents with new construction and restoration work described in the construction documents and with the Contracting Officer.
Removal of bird, bat, and rodent dropping shall be performed as described in Section 02 8500. Bird, bat and rodent droppings shall be removed from all structures.
Section 32 10 00 section 1.4.B.1.a requires a geotechnical investigation to determine groundwater depth through the project, more specifically at the lift station.
Attachment 6 (Jorgensen Geotechnical report, 8/19/2025, (section 4.3) states that groundwater was not encountered in the July 2025 test pits, that standpipe piezometers were installed in three of the five test pits, and recommends groundwater monitoring during the spring 2026 runoff.
1. Was the spring 2026 groundwater monitoring performed? If so, please provide the monitoring data and final report.
2. Will NPS accept the existing Attachment 6 investigation, plus any monitoring data, as satisfying section 1.4.B.1.a? Or is the Contractor required to perform a new investigation and monitoring at the lift station?
1. Spring 2026 groundwater monitoring was not performed.
2. The contractor shall perform required groundwater monitoring.
Lead-containing paint (LCP) Please confirm whether materials identified as LCP will remain in place, be included in the lead abatement contractor’s scope, or be handled by the general contractor. If responsibilities vary, please provide an itemized list.
Lead based paint, present on window sashes scheduled to be restored by the Government, will be addressed by the Government. All other lead based paint shall be addressed by the general contractor per the requirements of section 02 03 00.
66 Reference spec section 26 24 16 - 2 ( 2.2) Will Siemens be acceptable as a Panelboard manufacturer?
Siemens is not a listed manufacture and such, is not acceptable.
67 What are the heights/elevations of the 2 small packaged sewer grinder pump stations? There is only one grinder pump station, serving the Caretaker's cabin. That station is to utilize a 24"x48" basin (Zoeller 31-0866 or equivalent) per revised Sheet C-204.
68 Are there plan and profile sheets for the FM services and sewer services from the Caretakers Cabin?
Please clarify pipe sizes for these services.
There is only one grinder pump station, serving the Caretaker's cabin. That station is to utilize a 24"x48" basin (Zoeller 31-0866 or equivalent) per revised Sheet C-204.
69 C307 shows the FM service from the New Cabin coming into a gravity manhole (MH-1) at an acute angle. Will this be allowed?
Refer to the Permit set of drawings issued following WYDEQ review. The new cabin will be connected to sewer via gravity service with a wye connection to the main.
Why is the service for the New Cabin a Force Main with a lift station? The profile shows it is sloped for gravity. That service has been changed to a gravity main following DEQ review. All gravity services have been upsized to 4" diameter so the proposed slope from the New Cabin is sufficient.
FM service from Caretakers, what does the connection from the service to the main look like? Does the detail 3/C204 apply to the force main service connection for the service. Would a check valve be required?
An in-line tee is appropriate for that connection. A check valve is recommended at the service connection in addition to the required check valve on the grinder pump discharge.
Is directional drilling an accepted method of installing the Force Main? Plowing is required for force main installation to expedite installation and minimize impact to Park operations and wildlife.
Plowing is the required method for force main installation in roadways; performance-based standards must be met.
Log species: Section 06 13 13 section 2.6.A.1 requires replacement logs to "Match existing," and Section 01 32 16 lists lodgepole pine logs as a long-lead item. Allowance No. 3 (01 21 00 section 3.3.C) includes wood species testing. Should offerors price lodgepole pine? If testing identifies a different species, will the difference be adjusted by modification?
Yes, price as lodgepole pine. If testing identifies a different species a change order may be pursued at that time.
Specification section 28 46 21 paragraph 2.1 lists many different fire alarm manufacturers. Some of the listed manufacturers offer proprietary and non proprietary lines of panels. Is there a preference toward non-proprietary systems due to the park's maintenance practices? Is there a preference to match system manufacturer to any existing systems or equipment within the park to reduce spare parts maintenance and storage?
Follow Specification section 28 46 21 list of different fire alarm manufacture. No specific prefereance by park.
Specification section 28 46 21 paragraph 2.8D specifies to use a cellular radio for system reporting. It specifies a Telguard No. TG-7F or approved equivalent. Please confirm a Napco StarLink Fire dialer is an acceptable equivalent.
Yes this is acceptable.
All smoke detection shown on the drawings are shown to be Smoke and CO combo units, with most also requiring a sounder base. Specification section 28 46 21 paragraph 2.11 lists the requirements for smoke detectors; Subsection B7 a-c lists requirements for heat detection. Please clarify if the smoke detectors shown on the drawings must also have heat detection capability.
The smoke detectors shown on the drawings do not need heat detection capability.
Specification section 28 46 21 paragraph 2.15B states that notification appliances must be addressed and connected to the signaling line circuit (SLC). This is atypical from industry standards. Please confirm that conventional notification appliances are acceptable.
Yes conventional notification appliances are acceptable and to be on NAC circuit.
Drawing page 000 E003 notes that "Fire Alarm System installer shall submit NICET Level 3 certification PRIOR to undertaking project." Does this mean this certification must be included in the proposal submittal?
Fire alarm system installer shall be NICET 3 certified as noted. Certifications will be reviewed as part of project submittal process.
Drawing page 407 E101 shows the WP Horn Strobe for the fire alarm to be on the exterior wall of the bathroom. This location will not be visible from the walkways or road of the complex, and may delay the response time of emergency vehicles when responding. Please confirm the WP Horn Strobe location on these building is correct.
This WP horn strobe location to be relocated to the north side of the cabin for better visibility.
Materials containing less than 1% asbestos Please identify which materials reported as containing less than 1% asbestos must be included in the asbestos abatement contractor’s scope. Specifically, please confirm whether the log mortar in George’s Cabin is included.
ALL ASBESTOS MUST BE REMOVED BY A CERTIFIED ASBESTOS PERSONEL
(Asbestos Abatement Contractors).
Based on the various building materials identified with asbestos concentrations equal to or less than 1%, the Environmental Protection Agency (EPA) and Wyoming Department of Environmental Quality (WDEQ) do not regulate them. However, Occupational Safety and Health Administration (OSHA) regulation 29 CFR 1926.1101, Asbestos Standard for the Construction Industry, states that if asbestos-containing material containing 1% or less asbestos is to be removed by construction personnel, the employer shall provide awareness training, a written respirator protection program, respirators, and a negative exposure assessment would apply for any disturbance activities associated with these materials.
Accordingly, individuals engaging in the disturbance or removal of these materials utilize asbestos-safe work practices as specified within 29 CFR 1926.1101. As stipulated under 29 CFR 1926.1101, work practice requirements and prohibitions that must be observed regardless of the exposure levels and the percentage of asbestos in the installed construction materials include, but are not necessarily limited to:
29 CFR 1926.1101(g)(1)(ii), which requires: wet methods, or wetting agents, to control employee exposures during asbestos handling, mixing, removal, cutting, application, and cleanup, except where employers demonstrate that the use of wet methods is infeasible due to, for example, the creation of electrical hazards, equipment malfunction, and, in roofing, except as provided in paragraph (g)(8)(ii) of this section.
29 CFR 1926.1101(g)(1)(iii), which requires: prompt clean-up and disposal of wastes and debris contaminated with asbestos in leak-tight containers except in roofing operations, Materials containing greater than 1% asbestos Please confirm whether all identified materials containing greater than 1% asbestos must be removed by the asbestos abatement contractor. If any will remain in place, please provide an itemized list, including clarification regarding the beam caulk in River Cabin and the foundation sealant at Main Lodge.
ALL ASBESTOS MUST BE REMOVED BY A CERTIFIED ASBESTOS PERSONEL
(Asbestos Abatement Contractors). Please see response to item 80 above.
Windows with asbestos-containing glazing or caulking Should the asbestos abatement contractor remove only the identified glazing and caulking while retaining the windows, or remove and dispose of the complete affected window assemblies as asbestos-containing waste? Please identify any requirements that vary by window or building.
ACM, present on window sashes scheduled to be restored by the Government, will be addressed by the Government.
Third-party final clearance testing. Will the general contractor arrange and pay for independent third-party final visual inspections and air clearance testing following asbestos abatement, or should the asbestos abatement contractor include these services in its bid? Please specify the required clearance criteria and whether testing is required separately for each building or containment area.
Per specification 02 8200, 3rd party testing will be provided by the Government, not the General Contractor.
84 Guano removal
Guano. Will we only be removing the guano that is present in the main lodge? Or will there be some cleanup where droppings were present in other cabins?
Contractor is responsible for removing guano and animal waste in the Main Lodge and all structures prior to comencing other work. Removal of bird, bat, and rodent dropping shall be performed as described in Section 02 8500. Bird, bat and rodent droppings shall be removed from all structures.
85 Bid Extension
Would NPS please consider a solicitation response date extension?
The 4 Lazy F project has some very unique complexities. Bidding this project requires input from many different trades. We will also likely need several follow-up site visits.
The upcoming holidays and the end of the year also add to the chaos. We want to ensure competitive subcontractor participation.
Due date remains 11/20
Reference: Att. 01 Dwgs 000 E002 KN 9, 000 E004 Panel PLS "Supply From: P399", 000 E003 FA Riser notes, 000 E100 KN 5 and KN 9 (Dwg p.82–85); Att. 02 Specs 01 27 00 ¶3.1.C (p.32) The Base lift station panel PLS is fed from new panel P399 in the Main Lodge (Option 1, CLIN 002), while 01 27 00 ¶3.1.C describes a separate supply coordinated with Lower Valley Energy. Likewise, the central fire alarm panel that every cabin reports to is located in the Main Lodge, and the 411 grinder pump (Base) is powered from the Option 9 panel. Please confirm how the lift station is to be powered, and how cabin fire alarm signals are to be monitored, if Option 1 is not exercised or is exercised after the Base work, and identify the CLIN in which P399/PLS feeders, the FACP and the site fire alarm conduits are to be priced.
Lift Station Panel PLS to be powered from Main Lodge Panel P399 per plans. CLIN 01C incorrectly notes to supply from LVE. FACP is part of Main Lodge and thus part of CLIN
02. Site fire alarm conduits to be priced as part of each associated Cabin (i.e. fire alarm conduit from Main Lodge to George's Cabin 404 to be priced under CLIN 03). The 411 Grinder Pump has been removed; see updated sheets issued as part of DEQ revisions.
Reference: Section C (Sol. p.10, "design, permitting, and construction"); Att. 01 Dwgs C001 Note 3, C200/C201 Notes, C300 (Dwg p.10, 17–18, 23); Att. 02 Specs 33 14 15 Part 3 "Design Criteria"; 32 10 00 ¶1.4.B.1.a–c, ¶1.4.C (p.1025); Att. 08 The civil drawings are sealed and a WYDEQ permit application has been signed, yet Section C, the C- sheet notes, 33 14 15 Part 3 and 32 10 00 ¶1.4.B require the Contractor to perform a lift-station groundwater study, topographic survey and septic-system investigation "for the design of the project." Please confirm the C-series drawings are the complete Government design, identify the Engineer of Record, confirm the Government holds the WYDEQ permit, and confirm the Contractor is not responsible for engineering design or supplemental investigations beyond construction layout. If septic tank removal remains in the Contractor's scope, please provide the number and locations of tanks.
C-series drawings have been permitted for construction by WYDEQ. Groundwater and flood stage conditions at the lift station site have been evaluated in the design, and topographic survey has been completed as shown on the most recent plan set. Septic tanks have not been surveyed for demolition by the engineer.
Reference: Section B CLIN 012; Att. 02 Specs 01 27 00 ¶3.1.O; 01 35 13.05 ¶3.x.E ("at no cost to the Government", p.84); 01 11 00 ¶1.9.D.1; Att. 01 Dwgs L001 Staging Note 15 ("assume minor repairs", Dwg p.40); L002 (Dwg p.41); C101 (Dwg p.15) Option 11 has no defined limits, section or quantity ("assume minor repairs"), while Division 01 and L002 also require staging-area restoration at no cost.
Please define the road limits, the regrading/resurfacing section and the staging areas included in CLIN 012, confirm whether the no-cost restoration in 01 35 13.05 is superseded by CLIN 012, and state the Contractor's restoration obligation if CLIN 012 is not exercised.
NPS is still in the process of getting an answer to this RFI.
Reference: Att. 02 Specs 26 00 10 ¶1.4.A vs. ¶1.4.C (p.865); Att. 01 Dwgs 000 E001 General Note B (Dwg p.81) 26 00 10 ¶1.4.A makes the Contractor pay connection and system development fees, while ¶1.4.C and E001 Note B make the Owner responsible for all utility costs and fees. Please confirm that all Lower Valley Energy charges (engineering, line extension, transformer, metering, connection, breaker change- outs) are paid by the Government, or provide LVE's estimate or an allowance if the Contractor is to carry them. B. Site Utilities (Base CLINs 001A–001D)
Per section 01 50 00 - TEMPORARY FACILITIES AND CONTROLS the Construction Contractor will be responsible for the cost of power during construction including usage costs, distribution costs and coordination of temporary power service with the supplier.
Power does exist on the site per the Construction Documents.
Looking at the specs that were provided, an asbestos-containing grey sealant was identified on a few cabins. I would like to know exactly which sealant is in question here and where it is located to make sure we are looking at the same material to be removed. The roofs on a few cabins with said sealant (such as the Middle Cabin) also appeared to have newer roofing installed, so knowing when those roofs were installed and which layer of roofing has the asbestos-containing sealant would be phenomenal.
No additional descriptions of asbestoes containing materials or quantities is available. Per section 02 82 00 -Part 1.B.2: "The Asbestos Abatement Contractor shall satisfy himself as to the actual quantities to be abated and disposed of." The hazardous materials reports are provided as supplementary information to inform the Abatement Contractor's quantity assessments. Bids should be based on these conditions.
The River Cabin showed an asbestos-containing beam caulk, but in the schematic provided it appeared to be more beam caulk than was easily identifiable in person. Additional information about where exactly the beam caulk is located to make sure none is missed would be helpful.
No additional descriptions of asbestoes containing materials or quantities is available. Per section 02 82 00 -Part 1.B.2: "The Asbestos Abatement Contractor shall satisfy himself as to the actual quantities to be abated and disposed of." The hazardous materials reports are provided as supplementary information to inform the Abatement Contractor's quantity assessments. Bids should be based on these conditions.
The lead report shows some lead based paint on the main lodge as "exterior door components". The paint appeared identical on the doors as well as the door trim. I just want to check and see if the paint in question is on the doors themselves, the door trim, or both.
No additional descriptions of lead based paint locations or quantities is available. Per section 02 83 00 -Part 1.B.2: "The Contractor shall satisfy themselves as to the actual number of building components and quantities to be stabilized, components removed, soil removed, cleaned, disposed of, and soil backfilled by the Contractor in preparation for re-painting and component replacement." The hazardous materials reports are provided as supplementary information to inform the Contractor's quantity assessments. Bids should be based on these conditions.
Sheet 000 A801 roof assembly R1 shows 5/8" sheathing over 3" mineral wool insulation (4" at River Cabin) per 07 21 00 section 2.2.A. No sleepers, blocking or fastening schedule is shown for the upper sheathing through the insulation to the structure. 07 21 00 section 3.3 refers installation to 06 10 00, which provides only general fastening per IBC table 2304.9.1.
1. Please identify the support and compression control required (sleepers, blocking, spacers, or other) to prevent mineral wool compression and resist roof loads and downslope movement.
2. Please provide a fastening schedule for each type of insulated roof assembly, including upper sheathing, any sleepers/blocking, and attachment to the existing structure.
1. The specified roof insulation is sufficiently rigid to be installed…