This is Amendment 0002 to Solicitation 140P2026R0038, issued by the National Park Service (NPS), Division of the Directorate of Science Compliance (DSC) Contracting Services on April 16, 2026. The amendment responds to 15 bidder questions regarding a construction project and clarifies scope requirements. The solicitation deadline remains June 3, 2026, at 9:00 a.m. Mountain Time, and all amendments must be signed and submitted with proposals.
Key clarifications provided include: vegetation removal and joint repair are included in the scope per specification section 31 10 00; subgrade replacement details are referenced in site plans; the Government will provide a qualified professional for the Red Knot Survey with contractor coordination required; construction shall commence after Labor Day with a portion of the parking lot remaining open to the public as approved by the Contracting Officer; hazardous materials abatement for Building 609 demolition is included in the lump-sum price with assumptions for typical asbestos-containing materials, lead-based paint, and other standard hazardous materials, subject to post-award verification and equitable adjustment for documented overages; a bid bond is required; the project schedule runs between Labor Day and Memorial Day; laydown and material storage will be accommodated in the parking lot area as proposed by the contractor and approved by the Contracting Officer; quantity calculations for existing striping removal are the bidder's responsibility; pavement markings shall use extruded thermoplastic meeting NYCDOT Standard Specifications Section 685 and AASHTO M 249 standards; and collision-rated protective bollards shall conform to MASH TL-1 performance standards.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P2026R0038_Amd_0004.pdf | ||
| Sol_140P2026R0038_Amd_0003.pdf | ||
| Extracted_Pages_from_JABA_Asbestos_Survey_Report_0003.pdf | ||
| Sol_140P2026R0038_Amd_0001.pdf | ||
| B08_Attachment_5_Wage_Determination_NY20260003.pdf | ||
| Sol_140P2026R0038.pdf | ||
| B08_Attachment_1_GATE213019_JacobRiisParkingLot_Specifications_2025_7_15.pdf | ||
| B08_Attachment_2_GATE_213019_100__PS_E_Drawings_NPS.pdf | ||
| B08_140P2026R0038_Conformed_Solicitation_GATE_213019.pdf | ||
| B08_Attachment_3_ContractPriceSchedule_GATE_213019_blank_2025_8_11.xlsx | XLSX spreadsheet | |
| B08_Attachment_4_GATE_213019_SubmittalList100_FinalCD_250612.pdf | ||
| B08_Attachment_6_General_Refrences.pdf | ||
| B08_Attachment_7_Subcontract_Percentage_Worksheet.xlsx | XLSX spreadsheet |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: is not is required copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7.ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
PAGESOF
Contractor
The hour and date specified for receipt of Offers to sign this document and return
Rachel Dyer
See continuation page
NPS, DSC Contracting Services Div 1 Denver Federal Center, Building 50 P.O. Box 25287 Denver CO 80225-0287
DOI, NPS, DSC Contracting Services 1 Denver Federal Center, Building 50 P.O. Box 25287 Denver CO 80225-0287
PDS
PDS
140P2026R0038
04/16/2026
04/16/2026
1 6
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
140P2026R0038/0002
The purpose of amendment 0002 is to answer questions.
Question 1: Reference is made to the existing site conditions, which indicate extensive vegetation growth within the pavement joints.
Please confirm whether removal of the vegetation is included within the project scope, as this work would be required prior to striping operations. Additionally, please confirm whether repair of the existing joints will be required as part of the contract scope.
Answer 1: Per specification section 31 10 00
Para 3.2 A.: Remove obstructions, trees, shrubs, and other vegetation to permit installation of new construction. Remove vegetation and install new joints as needed for new concrete work activities, or as otherwise specifically noted in the CDs. In other areas, vegetation shall be made flush with the pavement so as not to impede painting operations.
Question 2: Please provide details regarding any required subgrade replacement, including the extent of replacement and the quantities to be carried in the bid, if applicable.
Answer 2: Refer to site plans and details.
Question 3: Reference is made to mitigation notes on sheet G1.3, please clarify if contractor is responsible for the Red Knot
Survey.
Answer 3: The Government shall provide a qualified professional. The Contractor shall coordinate schedules to ensure that the survey can be completed before work starts.
Question 4: Reference is made to the stated work restrictions. Please confirm whether the
Contractor will be permitted to occupy and perform work in all parking lot work areas simultaneously during the allowable work period.
Continued...
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
Answer 4: Construction shall commence after
Labor Day. A small portion of the parking lot shall remain open to the public for parking during construction. The area or areas shall be approved by the CO and can be moved as needed to accommodate construction.
Question 5: Reference is made to the demolition of Building 609. Please confirm whether there are any known asbestos-containing materials
(ACM) and/or lead-based paint or other hazardous materials present within the structure.
Answer 5: Hazardous materials abatement shall be included as part of the lump¿sum demolition scope. The Government¿s current information indicates that Building 609 contains limited known hazardous materials; however, this information is not considered exhaustive. For the purpose of establishing a basis of design and ensuring consistent pricing, the Contractor shall include in the lump¿sum price a complete hazardous materials abatement effort based on the following assumptions:
The Contractor shall assume discovery of typical quantities of asbestos¿containing materials (ACM), lead¿based paint (LBP), and other standard building hazardous materials consistent with structures of similar age and construction. Upon award, the Contractor shall perform a full hazardous materials survey by a licensed environmental professional to verify actual field conditions. If the verified conditions show less quantity than assumed, the
Contractor shall credit the Government the difference through a deductive modification. If the verified conditions show more quantity than assumed, the Contractor may request an equitable adjustment only for the documented, measurable overage. All abatement pricing shall be itemized with quantities, unit rates, and supporting documentation to allow Government validation.
Question 6: Reference is made to SF 1442
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C) section 13b. and Section M.C.3.d of the solicitation, is a bid bond required?
Answer 6: Yes, a bid bond is required.
Question 7: Reference is made to the work restrictions. Please confirm whether there are any additional restrictions or limitations on construction activities during the summer period.
Answer 7: The projected project schedule will run between Labor Day and Memorial Day to avoid summer limitations.
Question 8: Reference is made to the period of performance, does this period include all options as well?
Answer 8: The period of performance is an estimate of the days required to perform the work. Once an award is made the notice to proceed will start the period of performance.
Question 9: Please confirm whether the
Government will provide a designated laydown and material storage area for the Contractor¿s use during construction activities. If so, please provide the location and approximate dimensions of the available area.
Answer 9: Laydown and materials storage space will be accommodated in the parking lot area.
Size and location of this staging area to be proposed by the contractor in coordination with the Park and approved by the CO prior to the start of construction activities.
Question 10: Reference is made to Sheet C4.0, Note No. 2, regarding removal of existing striping. Please provide the quantity of existing striping to be removed for bidding purposes.
Answer 10: Quantity calculations are the responsibility of the bidder. Refer to the
Existing Conditions sheets in the drawing set for the existing paint marking locations.
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
Question 11: Reference is made to Sheet C4.0, Note No. 7, regarding conformance of striping to NYC DOT standards. Please clarify whether the required pavement marking material is
Latex, Epoxy, or Thermoplastic.
Answer 11: Use Extruded Thermoplastic Pavement
Marking: Provide hot¿applied, reflectorized thermoplastic pavement markings meeting NYCDOT
Standard Specifications, Section 685, and conforming to AASHTO M 249 for thermoplastic materials. Material shall comply with applicable ASTM performance standards for durability, retro reflectivity, and glass bead embedment. Use formulations free of lead and chromate. Apply at the manufacturer¿recommended temperature to ensure proper mechanical bonding to concrete substrates prepared in accordance with NYCDOT requirements. Colors shall conform to Federal Standard color specifications as required for pavement markings.
Question 12: Please provide additional details regarding the scope of work associated with the
Technology Garage Building. As no organized site visit was scheduled, bidders were not able to access or adequately assess the existing conditions within the building.
Answer 12: Refer to Detail and Notes on sheet
T1.1.
Question 13: For the Technology package please provide device schedules, clarify what is government-furnished vs contractor furnished, details on telecommunication room layout/rack elevations and associated equipment.
Answer 13: Refer to Technology Schedules sheets in the drawing set (T0.0 - T2.1).
Question 14: For bidding purposes, please provide quantities for pavement marking removal.
Answer 14: Quantity calculations are the responsibility of the bidder. Refer to the
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
Existing Conditions sheets in the drawing set for the existing paint marking locations.
Question 15: What load does the collision rated bollard have to resist?
Answer 15: The collision¿rated protective bollard on sheet C6.9 Detail C shall conform with MASH TL¿1 performance. This rating ensures that each bollard can resist the impact of a
2,270 kg (5,000 lb) pickup truck traveling at
50 km/h (31 mph). The bollard must be of the size and dimension as shown on the drawings.
All other terms and conditions hereby remain unchanged. The due date is still June 3, 2026, at 9:00am MT.
All amendments to this solicitation need to be signed and submitted with proposals.
| Amendment of solicitation/modification of contract |
| Contract ID code |
| Amendment/modification number |
| Effective date |
| Requisition/purchase requisition number |
| Project number |
| Issued by |
| Code |
| Administered by |
| Code |
| Name and address of contractor |
| Code |
| Facility code |
| Amendment of solicitation number |
| Dated |
| Modification of contract/order number |
| Dated |
| This item only applies to amendments of solicitations |
| Accounting and appropriation data |
| This item applies only to modifications of contracts/orders. |
| This change order is issued pursuant to: |
| The above numbered contract/order is modified to reflect the administrative changes |
| This supplemental agreement is entered into pursuant to authority of: |
| Other |
| Important: |
| Description of amendment/modification |
| Name and title of signer |
| Contractor/offeror |
| Date signed |
| Name and title of contracting officer |
| Signature of Contracting Officer |
| Date signed |
| Previous edition unusable |
| Standard form 30 (rev. 11/2016) |
| Continuation sheet |
| Reference Number |
| Name of Offeror or Contractor |
| OPTIONAL FORM 336 (4-86)) |
Sponsored by GSA FAR (48 CFR) 53.110
File details come from the government source that posted it. Updated .