Amendment_03_Past_Performance_Questionaire_03.docx

DOCX document 45 KB Posted

Attached to
Old Courthouse Phase 2 Renovations, Gateway Arch N Federal contract opportunity
Solicitation number
140P2022R0159
Issued by
Department of the Interior National Park Service National Office

About this file

This document is a past performance questionnaire for a construction contractor seeking to renovate the Old Courthouse in Gateway Arch National Park in St. Louis, Missouri. The questionnaire requests information about a previous $X.X million contract awarded on XX/XX/XXXX to renovate the facility, including the scope of work, quality of workmanship, adherence to schedules and cost controls, management and oversight of subcontractors, safety record, and regulatory compliance. References are asked to rate performance in these areas as exceptional, very good, satisfactory, marginal, or unsatisfactory. The completed questionnaire must be returned by a specified time and date to the contracting officer from the National Park Service's Denver Service Center.

View the file

Other files for this federal contract opportunity

Other files attached to Old Courthouse Phase 2 Renovations, Gateway Arch N, newest first.
File Type Posted
Amendment_09_SF_30_9-9-22_09.pdf PDF
Amendment_09_Questions_and_Answers_9-9-22_09.docx DOCX document
Sol_140P2022R0159_Amd_09.pdf PDF
Sol_140P2022R0159_Amd_08.pdf PDF
Amendment_08_SF_30_9-8-22_08.pdf PDF
Amendment_08_Questions_and_Answers_9-8-22_08.docx DOCX document
Amendment_08_Ground_Penetrating_Radar_08.docx DOCX document
Amendment_08_STL_OCH_Ramp_Project_Irrigation_As_Built__08.pdf PDF
Amendment_07_SF_30_9-2-22_07.pdf PDF
Amendment_07_Questions_and_Answers_9-2-22_07.docx DOCX document
Sol_140P2022R0159_Amd_07.pdf PDF
Amendment_06_SF_30_8-26-22_06.pdf PDF
Amendment_06_Questions_and_Answers_8-26-22_06.docx DOCX document
Sol_140P2022R0159_Amd_06.pdf PDF
Amendment_06_AS_BUILTS__JEFF_007895__Unistrut_Catwalk_06.pdf PDF
Amendment_06_Wage_Determination_MO20220051_7-29-22_06.pdf PDF
Amendment_05_Questions_and_Answers_8-25-22_05.docx DOCX document
Amendment_05_08_18_22_OCH_CONTRACTOR_SIGN_IN_05.pdf PDF
Amendment_05_08_16_22_OCH_CONTRACTOR_SIGN_IN_05.pdf PDF
Amendment_05_SF_30_8-25-22_05.pdf PDF
Amendment_05_08_24_22_Contractor_Walk_Thru_at_the_OCH_05.pdf PDF
Sol_140P2022R0159_Amd_05.pdf PDF
Sol_140P2022R0159_Amd_04.pdf PDF
Amendment_04_SF_30_8-19-22_04.pdf PDF
Amendment_04_Questions_and_Answers_8-19-22_04.docx DOCX document
Amendment_03_Project_Experience_Form_03.docx DOCX document
Amendment_03_Old_Courthouse_Preservation_Plan_Matrix_2022_08_03_03.pdf PDF
Amendment_03_SF_30_8-12-22_03.pdf PDF
Amendment_03_Questions_and_Answers_8-12-22_03.docx DOCX document
Sol_140P2022R0159_Amd_03.pdf PDF
Sol_140P2022R0159_Amd_02.pdf PDF
Amendment_02_TripReport_Schilling_and_Devore_11_20_final_02.pdf PDF
Amendment_02_PreBid_Conference_Presentation_7-29-22_02.pptx PPTX presentation
Amendment_02_Questions_and_Answers_8-9-22_02.docx DOCX document
Amendment_02_SF_30_8-9-22_02.pdf PDF
Amendment_02__Sign_In_Sheet_140P2022R0159_GANP_242900___2537127_02.pdf PDF
Amendment_01_Questions_and_Answers_7-29-22_01.docx DOCX document
Sol_140P2022R0159_Amd_01.pdf PDF
Amendment_01_SF_30_7-29-22_01.pdf PDF
B08_Attachment_1c_Project_Manual_VOL_3.pdf PDF
B08_Attachment_1d_Project_Manual_VOL_4.pdf PDF
B08_Attachment_3a_DOI_Memo_Implementation_of_Cert.pdf PDF
B08_Attachment_1b_Project_Manual_VOL_2.pdf PDF
B08_Attachment_2_Drawings.pdf PDF
B08_Attachment_3b_DOI_Memo_Certification_of_Vaccination_Form.pdf PDF
B08_Attachment_5_Proposal_Submission_Package_Portfolio_7-25-22.pdf PDF
B08_Attachment_1a_Project_Manual_VOL_1.pdf PDF
B08_Attachment_4_Wage_Determination_5-27-2022.pdf PDF
B08_GANP_242900_Sol_140P2022R0159_SF1442_and_Clauses_7-25-22.pdf PDF
Sol_140P2022R0159.pdf PDF
Show all 50

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PAST PERFORMANCE QUESTIONNAIRE

SOLICITATION NO. 140P2022R0159

INSTRUCTIONS: Offeror to complete Sections A and B and transmit questionnaire to reference.

Reference to complete Sections C and D and transmit back to Contracting Officer listed in section E.

Notice to Contractor Information provided in this questionnaire is intended for use as source selection information and as such is deemed Source Selection Sensitive. Statements or comments provided in the questionnaire do not signify an express or implied endorsement of any product, supply, service, or enterprise.

This information shall not be construed as an endorsement by the Government or its employee(s) of the contractor for advertising purposes or in a manner that implies the contractor, its products, or services, are approved, endorsed, or considered by the Government to be superior to other products or services.

The contractor shall not be permitted to use any information provided in this questionnaire to publicize, or otherwise circulate, promotional materials that state or imply Governmental, organizational, group, expert, or individual endorsement or consumer testimonial of a product, service, or position which the contractor represents.

A. OFFEROR INFORMATION

Company Name
Company
Street Address
Address
City
City
State
State
Zip Code
XXXXX
Unique Entity Identifier (UEI) Number / SAM
XXXXXXX
Point of Contact
Name, Email, Phone

B. CONTRACT INFORMATION FOR PAST PROJECT (PROJECT SUBMITTED UNDER PROJECT EXPERIENCE)

Project Title
Title
Contract Number
XXXXXXXXXX
Contract Type
Firm Fixed Price / Time & Materials / Cost Reimbursable / Other
Awarded Contract Price
$X,XXX,XXX
Current / Final Price
$X,XXX,XXX
Contract Award Date
XX/XX/XXXX
Contract Completion Date
XX/XX/XXXX
Period of Performance
XX/XX/XXX – XX/XX/XXX
Project Location
Park or Street address, City, State
Client / Owner
Company
Brief description of the contract & work effort:
Scope of work description

C. REFERENCE:

Name
First, Last
Position / Title
Title
Organization
Agency or Company
Phone Number
XXX-XXX-XXXX
Email Address
Email
Signature
Signature
Date
XX/XX/XXXX

D. EVALUATION

Rating
Definition
Exceptional
Performance met contractual requirements and exceeded many to the owner’s benefit. The element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective.
Very Good
Performance met contractual requirements and exceeded some to the owner’s benefit. The element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.
Satisfactory
Performance met contractual requirements. The element being assessed contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.
Marginal
Performance did not meet some contractual requirements. The element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions.
Unsatisfactory
Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The element being assessed contains a serious problem(s) for which the contractor’s corrective actions appear or were ineffective.
Evaluation Area
Rating

Quality

Quality of workmanship (including subcontractors)?
Choose an item.
Quality of and adherence to quality control plan?
Choose an item.
Quality of informational and technical submittals?
Choose an item.
Overall Quality Rating
Choose an item.
Comments (Please provide comments supporting the above ratings. Comments supporting ratings of excellent, marginal, & unsatisfactory are especially helpful.):

Schedule (& Time Management)

Met project schedule milestones?
Choose an item.
Responded to owner requests in a timely manner?
Choose an item.
Informational and technical submittals submitted timely?
Choose an item.
Promptly addressed scheduling issues?
Choose an item.
Overall Schedule (& Time Management) Rating
Choose an item.
Comments (Please provide comments supporting the above ratings. Comments supporting ratings of excellent, marginal, & unsatisfactory are especially helpful.):

Cost Control

Addressed differing & unforeseen site conditions so as to minimize additional costs?
Choose an item.
Provided fair and reasonable pricing for contract modifications?
Choose an item.
Submitted accurate and complete invoices?
Choose an item.
Promptly paid subcontractors and suppliers?
Choose an item.
Overall Cost Control Rating
Choose an item.
Comments (Please provide comments supporting the above ratings. Comments supporting ratings of excellent, marginal, & unsatisfactory are especially helpful.):

Management

General oversight by project manager and superintendent?
Choose an item.
Coordination with and control of subcontractors?
Choose an item.
Avoidance of accidents & safety violations?
Choose an item.
Addressed location factors (especially remote locations)?
Choose an item.
Maintained good working relationship with owner representatives?
Choose an item.
Demonstrated flexibility, innovativeness and cooperation in resolving potential problems?
Choose an item.
Overall Management Rating
Choose an item.
Comments (Please provide comments supporting the above ratings. Comments supporting ratings of excellent, marginal, & unsatisfactory are especially helpful.):

Small Business Subcontracting (& Labor Standards)

Met regulatory and contractual labor standards?
Choose an item.
Successfully contracted with small and socio-economically disadvantaged businesses?
Choose an item.
Quality and adherence to applicable subcontracting plans?
Choose an item.
Overall Small Business Subcontracting (& Labor Standards) Rating
Choose an item.
Comments (Please provide comments supporting the above ratings. Comments supporting ratings of excellent, marginal, & unsatisfactory are especially helpful.):

Regulatory Compliance

Met building and life safety codes?
Choose an item.
Overall Regulatory Compliance Rating
Choose an item.
Overall Recommendation:
Given what I know today about the contractor's ability to perform in accordance with the contract’s most significant requirements, I would recommend them for similar contracts:
Choose an item.
Overall Comments:

E. RETURN:

Return by
Time / Date
Name
CO or CS name
Title
Contracting Officer / Contract Specialist
Organization
National Park Service – Denver Service Center
Email
First_Last@nps.gov

File details come from the government source that posted it. Updated .