B08_Attachment_1b_Project_Manual_VOL_2.pdf
PDF 10 MB Posted
- Attached to
- Old Courthouse Phase 2 Renovations, Gateway Arch N Federal contract opportunity
- Solicitation number
- 140P2022R0159
About this file
This document summarizes a federal solicitation for renovations to the Old Courthouse in St. Louis, Missouri. The solicitation number is 140P2022R0159 and was issued by the Department of the Interior National Park Service National Office to renovate Phase 2 of the Old Courthouse, which is part of the Gateway Arch National Park. Renovations are needed for the former Jefferson National Expansion Memorial building and will include work on mechanical, electrical and plumbing systems as well as repairs to the exterior stonework and roof. The response due date is not provided in this attachment, but responses should be tailored for the continued preservation and restoration of the historic Old Courthouse facility.
View the file
Other files for this federal contract opportunity
Show all 50
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GATEWAY ARCH NATIONAL PARK
ST. LOUIS, MO
OLD COURTHOUSE ACCESSIBILITY IMPROVEMENTS PHASE 2
PMIS/PKG NO. 242900/253127
Final Construction Documents
NATIONAL PARK SERVICE
DENVER SERVICE CENTER
July 1, 2022
VOLUME 2 OF 4
jwilhelm Image jwilhelm Image
PMIS/PKG NO. 242900/253127 21 05 00 - 1
BASIC FIRE SUPPRESSION REQUIREMENTS
SECTION 21 05 00 - BASIC FIRE SUPPRESSION REQUIREMENTS
PART 1 - GENERAL
1.1 SECTION INCLUDES
Requirements applicable to all Division 21 Sections. Also refer to Division 1 - General
Requirements.
All materials and installation methods shall conform to the applicable standards, guidelines and codes referenced herein and within each specification section.
1.2 SCOPE OF WORK
This Specification and the associated drawings govern the furnishing, installing, testing and placing into satisfactory operation the Fire Protection Systems.
The Contractor shall provide all new materials indicated on the drawings and/or in these specifications, and all items required to make the Mechanical Work a finished and working system.
Scope of Work:
1. Fire Protection Work shall include, but is not necessarily limited to:
a. Extend existing wet pipe sprinkler system for areas noted on the drawings.
b. Furnish and install complete dry pipe sprinkler systems for areas noted on the drawings.
c. Revise existing fire valve/fire hose standpipe system as noted on the drawings.
d. Furnish and install all items listed on the Fire Protection Material List.
e. Furnish all hydraulic calculations and working sprinkler drawings.
f. Furnish and install seismic restraint and equipment designed for use in seismic conditions described in Section 21 05 50.
1.3 COORDINATION DRAWINGS
Refer to Section 01 31 00 Project Management and Coordination.
1.4 QUALITY ASSURANCE
Refer to Section 01 40 00 Quality Requirements.
Utility Company Requirements:
1. Secure from the appropriate private or public utility company all applicable requirements.
PMIS/PKG NO. 242900/253127 21 05 00 - 2
2. Comply with all utility company requirements.
3. Make application for and pay for service connections.
4. Make application for and pay for all meters and metering systems required by the utility company.
Electronic Media/Files:
1. Construction drawings for this project have been prepared utilizing Revit.
2. Contractors and Subcontractors may request electronic media files of the contract drawings and/or copies of the specifications. Specifications will be provided in
PDF format.
3. Upon request for electronic media, the Contractor shall complete and return a signed “Electronic File Transmittal” form provided by IMEG.
4. If the information requested includes floor plans prepared by others, the Contractor will be responsible for obtaining approval from the appropriate Design
Professional for use of that part of the document.
5. The electronic contract documents can be used for preparation of shop drawings and as-built drawings only. The information may not be used in whole or in part for any other project.
6. The drawings prepared by IMEG for bidding purposes may not be used directly for ductwork layout drawings or coordination drawings.
7. The use of these CAD documents by the Contractor does not relieve them from their responsibility for coordination of work with other trades and verification of space available for the installation.
8. The information is provided to expedite the project and assist the Contractor with no guarantee by IMEG as to the accuracy or correctness of the information provided. IMEG accepts no responsibility or liability for the Contractor’s use of these documents.
1.5 SUBMITTALS
Refer to Section 01 33 23 Submittal Procedures.
1.6 EQUIPMENT SUPPLIERS' INSPECTION
The following equipment shall not be placed in operation until a competent installation and service representative of the manufacturer has inspected the installation and certified that the equipment is properly installed, adjusted and lubricated; that preliminary operating instructions have been given; and that the equipment is ready for operation:
1. Fire Seal Systems
PMIS/PKG NO. 242900/253127 21 05 00 - 3
2. Seismic Restraints and Equipment Bracing
Contractor shall arrange for and obtain supplier's on-site inspection(s) at proper time(s) to assure each phase of equipment installation and/or connection is in accordance with the manufacturer's instructions.
Submit copies of start-up reports to the Contracting Officer and include copies of Operation and Maintenance Manuals.
1.7 PRODUCT DELIVERY, STORAGE, HANDLING & MAINTENANCE
Exercise care in transporting and handling to avoid damage to materials. Store materials on the site to prevent damage. Keep materials clean, dry and free from harmful conditions.
Immediately remove any materials that become wet or that are suspected of becoming contaminated with mold or other organisms.
Keep all bearings properly lubricated and all belts properly tensioned and aligned.
Coordinate the installation of heavy and large equipment with the General Contractor and/or Contracting Officer. If the Mechanical Contractor does not have prior documented experience in rigging and lifting similar equipment, he/she shall contract with a qualified lifting and rigging service that has similar documented experience. Follow all equipment lifting and support guidelines for handling and moving.
Contractor is responsible for moving equipment into the building and/or site. Contractor shall review site for path locations and any required building modifications to allow movement of equipment. Contractor shall coordinate his/her work with other trades.
1.8 NETWORK / INTERNET CONNECTED EQUIPMENT
These specifications may require certain equipment or systems to have network, Internet and/or remote access capability (“Network Capability”). Any requirement for Network
Capability shall be interpreted only as a functional capability and is not to be construed as authority to connect or enable any Network Capability. Network Capability may only be connected or enabled with the express written consent of the Contracting Officer.
1.9 PROJECT COMMISSIONING
The Contractor shall work with the Commissioning Agent (CxA) as described in Section
01 91 13 and provide all services as described in the Commissioning Plan.
PART 2 - PRODUCTS
NOT APPLICABLE
PMIS/PKG NO. 242900/253127 21 05 00 - 4
PART 3 - EXECUTION
3.1 EXCAVATION, FILL, BACKFILL, COMPACTION
General:
1. Prior to the commencement of any excavation or digging, the Contractor shall verify all underground utilities with the regional utility locator. Provide prior notice to the locator before excavations. Contact information for most regional utility locaters can be found at the following website (https://call811.com/) or by calling 811.
2. The Contractor shall do all excavating, filling, backfilling and compacting associated with his/her work.
Excavation:
1. Make all excavations to accurate, solid, undisturbed earth, and to proper dimensions.
2. Where excavations are made in error below foundations, concrete of same strength as specified for the foundations or thoroughly compacted sand-gravel fill, as determined by the Contracting Officer, shall be placed in such excess excavations.
Place thoroughly compacted, clean, stable fill in excess excavations under slabs on grade, at the Contractor's expense.
3. Trim bottom and sides of excavations to grades required for foundations.
4. Protect excavations against frost and freezing.
5. Take care in excavating not to damage surrounding structures, equipment, or buried pipe. Do not undermine footing or foundation.
6. Perform all trenching in a manner to prevent cave-ins and risk to workers.
7. Where original surface is pavement or concrete, the surface shall be saw cut to provide clean edges and assist in the surface restoration.
8. Where satisfactory bearing soil for foundations is not found at the indicated levels, the Contracting Officer or their representative shall be notified immediately, and no further work shall be done until further instructions are given by the Contracting
Officer or their representative.
Dewatering:
1. Contractor shall furnish, install, operate, and remove all dewatering pumps and pipes needed to keep trenches and pits free of water.
Underground Obstructions:
1. Known underground piping, foundations, and other obstructions in the vicinity of construction are shown on the drawings. Use great care in making installations near underground obstruction.
https://call811.com/
PMIS/PKG NO. 242900/253127 21 05 00 - 5
2. If objects not shown on the drawings are encountered, remove, relocate, or perform extra work as directed by the Contracting Officer.
Fill and Backfilling:
1. No rubbish or waste material is permitted for fill or backfill.
2. Provide all necessary sand and/or CA6 for backfilling.
3. Dispose of the excess excavated earth as directed.
4. Backfill materials shall be suitable for required compaction, clean and free of perishable materials and stones greater than 4 inches in diameter. Water shall not be permitted to rise in unbackfilled trenches. No material shall be used for backfilling that contains frozen earth, debris, or earth with a high void content.
5. Backfill all trenches and excavations immediately after installing pipes or removal of forms, unless other protection is provided.
6. Around piers and isolated foundations and structures, backfill and fill shall be placed and consolidated simultaneously on all sides to prevent wedge action and displacement. Fill and backfill materials shall be spread in 6inch uniform horizontal layers with each layer compacted separately to required density.
7. Lay all piping on a compacted bed of CA6 at least 3 inches deep. Backfill around pipes with CA6, 6 inch layers, and compact each layer.
8. Use sand or CA6 for backfill up to grade for all piping under slabs or paved areas.
All other piping shall have sand or CA6 backfill to 6 inches above the top of the pipe.
9. Place all backfill above the sand/CA6 in uniform layers not exceeding 6 inches deep. Each layer shall be placed, then carefully and uniformly tamped, to eliminate lateral or vertical displacement.
10. Where the fill and backfill will ultimately be under a building, floor or paving, each layer of fill shall be compacted to 95% of the maximum density determined by AASHTO Designation T-99 or ASTM Designation D-698. Moisture content of soil at time of compaction shall not exceed plus or minus 2% of optimum moisture content determined by AASHTO T-99 or ASTM D-698 test.
Surface Restoration:
1. Where trenches are cut through graded, planted, or landscaped areas, the areas shall be restored to the original condition. Replace all planting removed or damaged to its original condition. A minimum of 6 inches of topsoil shall be applied where disturbed areas are to be seeded or sodded.
2. Concrete or asphalt type pavement, seal coat, rock, gravel or earth surfaces removed or damaged shall be replaced with comparable materials and restored to original condition.
PMIS/PKG NO. 242900/253127 21 05 00 - 6
3.2 PROJECT CLOSEOUT
Refer to Section 01 77 00 Closeout Procedures.
3.3 OPERATION AND MAINTENANCE MANUALS
Refer to Section 01 78 23 Operation and Maintenance Data.
3.4 INSTRUCTING THE CONTRACTING OFFICER’S REPRESENTATIVES
Refer to Section 01 79 00 Demonstration and Training.
3.5 SYSTEM STARTING AND ADJUSTING
The mechanical systems shall be complete and operating. System startup, testing, adjusting, and balancing to obtain satisfactory system performance is the responsibility of the Contractor. This includes calibration and adjustments of all controls, noise level adjustments and final comfort adjustments as required.
Complete all manufacturer-recommended startup procedures and checklists to verify proper motor rotation, electrical power voltage is within equipment limitations, equipment controls maintain pressures and temperatures within acceptable ranges, all filters and protective guards are in-place, acceptable access is provided for maintenance and servicing, and equipment operation does not pose a danger to personnel or property.
Operate all HVAC systems continuously for at least one week prior to occupancy to bring construction materials to suitable moisture levels. Areas with mechanical cooling shall be maintained below 60% RH.
Contractor shall adjust the mechanical systems and controls at season changes during the one year warranty period, as required, to provide satisfactory operation and to prove performance of all systems in all seasons.
All operating conditions and control sequences shall be tested during the start-up period.
Test all interlocks, safety shutdowns, controls, and alarms.
The Contractor, subcontractors, and equipment suppliers shall have skilled technicians to ensure that all systems perform properly.
3.6 RECORD DOCUMENTS
Refer to Section 01 77 00 Closeout Procedures.
3.7 PAINTING
This Contractor shall paint the following items:
1. Exposed piping. Color to be coordinated with Contracting Officer.
Paint all equipment that is marred or damaged prior to the Contracting Officer’s acceptance. Paint and color shall match original equipment paint and shall be obtained from the equipment supplier if available.
PMIS/PKG NO. 242900/253127 21 05 00 - 7
Equipment in finished areas that will be painted to match the room decor will be painted by others. Should this Contractor install equipment in a finished area after the area has been painted, he shall have the equipment and all its supports, hangers, etc., painted to match the room decor.
Equipment cabinets, casings, covers, metal jackets, etc., in equipment rooms or concealed spaces, shall be furnished in standard or prime finish, free from scratches, abrasions, chips, etc.
Equipment in occupied spaces, or if standard to the unit, shall have a baked primer with baked enamel finish coat free from scratches, abrasions, chips, etc. If color option is specified or is standard to the unit, this Contractor shall, before ordering, verify with the
Contracting Officer his color preference and furnish this color.
Paint all equipment in unfinished areas such as boiler room, mechanical spaces, storage room, etc., furnished by this Contractor. Equipment furnished with a factory coat of paint and enamel need not be painted, provided the factory applied finish is not marred or spattered. If so, equipment shall be refinished with the same paint as was factory applied.
Paint all outdoor uninsulated steel piping the color selected by Contracting Officer.
After surfaces have been thoroughly cleaned and are free of oil, dirt, and other foreign matter; paint all pipes and equipment with the following:
1. Bare Metal Surfaces - Apply one coat of primer suitable for the metal being painted. Finish with two coats of Alkyd base enamel paint.
2. Insulated Surfaces - Paint insulation jackets with two coats of semi-gloss acrylic latex paint.
3.8 ADJUST AND CLEAN
Thoroughly clean all equipment and systems prior to the Contracting Officer’s final acceptance of the project. Clean all foreign paint, grease, oil, dirt, labels, stickers, and other foreign material from all equipment.
Clean all drain pans and areas where moisture is present. Immediately report any mold, biological growth, or water damage.
Remove all rubbish, debris, etc., accumulated during construction from the premises.
3.9 SPECIAL REQUIREMENTS
Contractor shall coordinate the installation of all equipment, valves, dampers, operators, etc., with all trades to maintain clear access area for servicing.
All equipment shall be installed in such a way to maximize access to parts needing service or maintenance. Review the final field location, placement, and orientation of equipment with the Contracting Officer’s designated representative prior to setting equipment.
END OF SECTION 21 05 00
PMIS/PKG NO. 242900/253127 21 05 00 - 8
READINESS CERTIFICATION PRIOR TO FINAL JOBSITE OBSERVATION
To prevent the final job observation from occurring too early, we require that the Contractor review the completion status of the project and, by copy of this document, certify that the job is indeed ready for the final job observation. The following is a typical list of items that represent the degree of job completeness expected prior to your requesting a final job observation.
1. Penetrations fire sealed and labeled in accordance with specifications.
2. All pumps operating and balanced.
3. Fire protection system operational.
4. Pipes labeled.
Accepted by:
Prime Contractor _______________________________________________
By ___________________________________ Date ___________________
Upon Contractor certification that the project is complete and ready for a final job observation, we require the Contractor to sign this agreement and return it to the Contracting Officer so that the final observation can be scheduled.
It is understood that if the Contracting Officer finds the job not ready for the final observation and that additional trips and observations are required to bring the project to completion, the costs incurred by the
Contracting Officers for additional time and expenses will be deducted from the Contractor's contract retainage prior to final payment at the completion of the job.
PMIS/PKG NO. 242900/253127 21 05 05 - 1
FIRE SUPPRESSION DEMOLITION FOR REMODELING
SECTION 21 05 05 - FIRE SUPPRESSION DEMOLITION FOR REMODELING
1.1 SECTION INCLUDES
A. Mechanical demolition.
B. Cutting and Patching.
PART 2 - PRODUCTS
2.1 MATERIALS AND EQUIPMENT
A. Materials and equipment shall be as specified in individual Sections.
PART 3 - EXECUTION
3.1 EXAMINATION
A. THE DRAWINGS ARE INTENDED TO INDICATE THE GENERAL SCOPE OF
WORK AND DO NOT SHOW EVERY PIPE, DUCT, OR PIECE OF EQUIPMENT
THAT MUST BE REMOVED.
B. Where walls, ceilings, etc., are shown as being removed on general drawings, the
Contractor shall remove all mechanical equipment, devices, fixtures, piping, ducts, systems, etc., from the removed area.
C. Where ceilings, walls, partitions, etc., are temporarily removed and replaced by others, the Contractor shall remove, store, and replace equipment, devices, fixtures, pipes, ducts, systems, etc.
D. Verify that abandoned utilities serve only abandoned equipment or facilities. Extend services to facilities or equipment that shall remain in operation following demolition.
E. Coordinate work with the Contracting Officer. Schedule removal of equipment to avoid conflicts.
F. The Contractor shall verify all existing equipment sizes and capacities where equipment is scheduled to be replaced or modified, prior to ordering new equipment.
3.2 PREPARATION
A. Disconnect fire protection systems in walls, floors, and ceilings scheduled for removal.
B. Provide temporary connections to maintain existing systems in service during construction. When work must be performed on operating equipment, use personnel experienced in such operations.
PMIS/PKG NO. 242900/253127 21 05 05 - 2
3.3 DEMOLITION AND EXTENSION OF EXISTING MECHANICAL WORK
A. Remove, relocate, and extend existing installations to accommodate new construction.
B. Remove abandoned piping to source of supply and/or main lines.
C. Remove exposed abandoned pipes, including abandoned pipes above accessible ceilings.
Cut pipes above ceilings, below floors and behind walls. Cap remaining lines. Repair building construction to match original. Remove all clamps, hangers, supports, etc.
associated with pipe and duct removal.
D. Disconnect and remove mechanical devices and equipment serving equipment that has been removed.
E. Repair adjacent construction and finishes damaged during demolition and extension work.
F. Maintain access to existing mechanical installations which remain. Modify installation or provide access panels as appropriate.
G. Extend existing installations using materials and methods compatible with existing installations, or as specified.
3.4 CUTTING AND PATCHING
A. This Contractor is responsible for all penetrations of existing construction required to complete the work of this project. Refer to Section 21 05 29 for additional requirements.
B. Penetrations in existing construction should be reviewed carefully prior to proceeding with any work.
C. Penetrations shall be neat and clean with smooth and/or finished edges. Core drill where possible for clean opening.
D. Repair existing construction as required after penetration is complete to restore to original condition. Use similar materials and match adjacent construction unless otherwise noted or agreed to by the Architect/Engineer prior to start of work.
E. This Contractor is responsible for all costs incurred in repair, relocations, or replacement of any cables, conduits, or other services if damaged without proper investigation.
3.5 CLEANING AND REPAIR
A. Clean and repair existing materials and equipment which remain or are to be reused.
B. Clean all systems adjacent to project which are affected by the dust and debris caused by this construction.
C. FIRE PROTECTION ITEMS REMOVED AND NOT RELOCATED REMAIN THE
PROPERTY OF THE GOVERNMENT. CONTRACTOR SHALL PLACE ITEMS
RETAINED BY THE GOVERNMENT IN A LOCATION COORDINATED WITH
THE CONTRACTING OFFICER’S REPRESENTATIVE. THE CONTRACTOR
PMIS/PKG NO. 242900/253127 21 05 05 - 3
SHALL DISPOSE OF MATERIAL THE GOVERNMENT DOES NOT WANT TO
REUSE OR RETAIN FOR MAINTENANCE PURPOSES.
3.6 SPECIAL REQUIREMENTS
A. Install temporary filter media over outside air intakes which are within 100 feet of the limits of construction or as noted on the drawings. This Contractor shall complete any cleaning required for existing systems which are affected by construction dust and debris.
B. Review locations of all new penetrations in existing floor slabs or walls. Determine construction type and review for possible interferences. Bring all concerns to the attention of the Contracting Officer before proceeding.
END OF SECTION 21 05 05
PMIS/PKG NO. 242900/253127 21 05 13 - 1
MOTORS
SECTION 21 05 13 - MOTORS
1.1 SECTION INCLUDES
A. Single Phase and Three Phase Electric Motors.
1.2 DELIVERY, STORAGE, AND HANDLING
A. Protect motors stored on site from weather and moisture by maintaining factory covers and suitable weatherproof coverings. For extended outdoor storage, follow manufacturer’s recommendations for equipment and motor.
1.3 OPERATION AND MAINTENANCE DATA
A. Refer to Section 01 78 23 Operation and Maintenance Data.
1.4 QUALIFICATIONS
A. Manufacturer: Company specializing in the manufacture of commercial and industrial motors and accessories, with a minimum of three years documented manufacturing experience.
PART 2 - PRODUCTS
2.1 GENERAL CONSTRUCTION AND REQUIREMENTS
A. Refer to the drawings for required electrical characteristics. Voltage is generally specified and scheduled as distribution voltage. Motor submittals may be based on utilization voltage if it corresponds to the correct distribution voltage.
Distribution/Nominal Voltage Utilization Voltage
120 115
208 200
240 230
277 265
480 460
B. Design motors for continuous operation in 40ºC environment, and for temperature rise in accordance with ANSI/NEMA MG 1 limits for insulation class, service factor, and motor enclosure type.
C. Explosion-Proof Motors: UL listed and labeled for the hazard classification shown on the drawing, with over-temperature protection.
D. Visible Nameplate: Indicating horsepower, voltage, phase, hertz, RPM, full load amps, locked rotor amps, frame size, manufacturer's name and model number, service factor, power factor, insulation class.
E. Electrical Connection: Boxes, threaded for conduit. For fractional horsepower motors where connection is made directly, provide conduit connection in end frame.
PMIS/PKG NO. 242900/253127 21 05 13 - 2
F. Unless otherwise indicated, motors 3/4 HP and smaller shall be single phase, 60 hertz, open drip-proof or totally enclosed fan-cooled type.
G. Unless otherwise indicated, motors 1 HP and larger shall be three phase, 60 hertz, squirrel cage type, NEMA Design Code B (low current in-rush, normal starting torque), open drip-proof or totally enclosed fan-cooled type.
H. Each contractor shall set all motors furnished by him.
I. All motors shall have a minimum service factor of 1.15.
J. All motors shall have ball or roller bearings with a minimum L-10 fatigue life of 150,000 hours in direct-coupled applications and 50,000 hours for belted applications. Belted rating shall be based on radial loads and pulley sizes called out in NEMA MG1-14.43.
K. Bearings shall be sealed type for 10 HP and smaller motors. Bearings shall be regreasable type for larger motors.
L. Aluminum end housings are not permitted on motors 15 HP or larger.
M. Provide all belted motors with a means of moving and securing the motor to tighten belts.
Motors over 2 HP shall have screw type tension adjustment. Motors over 40 HP shall have dual screw adjusters. Slide bases shall conform to NEMA standards.
2.2 PREMIUM EFFICIENCY MOTORS (INCLUDING MOST 3-PHASE GENERAL PURPOSE
MOTORS)
A. All motors, unless exempted by EPAct legislation that became federal law on December
19, 2010, shall comply with the efficiencies listed in that standard, which are reprinted below. These match the 2010 NEMA premium efficiency ratings. All ratings listed are nominal full load efficiencies, verified in accordance with IEEE Standard 112, Test Method
B. Average expected (not guaranteed minimum) power factors shall also be at least the following:
Full-Load Efficiencies %
Open Drip-Proof Totally Enclosed Fan Cooled
HP 1200
rpm rpm rpm rpm rpm rpm
1.0 82.5 85.5 77.0 82.5 85.5 77.0
1.5 86.5 86.5 84.0 87.5 86.5 84.0
2.0 87.5 86.5 85.5 88.5 86.5 85.5
3.0 88.5 89.5 85.5 89.5 89.5 86.5
5.0 89.5 89.5 86.5 89.5 89.5 88.5
7.5 90.2 91.0 88.5 91.0 91.7 89.5
10.0 91.7 91.7 89.5 91.0 91.7 90.2
15.0 91.7 93.0 90.2 91.7 92.4 91.0
20.0 92.4 93.0 91.0 91.7 93.0 91.0
25.0 93.0 93.6 91.7 93.0 93.6 91.7
30.0 93.6 94.1 91.7 93.0 93.6 91.7
40.0 94.1 94.1 92.4 94.1 94.1 92.4
50.0 94.1 94.5 93.0 94.1 94.5 93.0
B. Motor nameplate shall be noted with the above ratings.
PMIS/PKG NO. 242900/253127 21 05 13 - 3
2.3 MOTORS ON VARIABLE FREQUENCY DRIVES
A. All motors driven by VFDs shall be premium efficiency type.
B. Motors shall be designed for use with VFDs in variable torque applications with 1.15 service factor. Motors shall not be equipped with auxiliary blowers.
C. Motors driven by VFDs shall have Class F or H insulation and be designated by the motor manufacturer to be suitable for inverter duty service in accordance with NEMA MG 1
Section IV, “Performance Standards Applying to All Machines,” Part 31 “Definite-Purpose
Inverter-Fed Polyphase Motors.
D. All 480-volt motors controlled by VFDs shall be equipped with an alternate discharge path, such as a shaft grounding ring or grounding brush, to divert adverse shaft currents from the motor bearings on the drive end of the motor shaft. Motor shafts 2” and larger require shaft grounding on the drive end and the non-drive end. This Contractor shall ensure (via field observation and measurement) that the shaft is effectively grounded upon startup.
1. Providing grounding rings internal to the motor housing is an acceptable solution, provided the motor is affixed with a label clearly indicating the presence of a grounding assembly. The grounding ring shall be listed for 40,000 hours of motor service and shall be accessible via the drive endplate.
2.4 MOTOR DRIVEN EQUIPMENT
A. No equipment shall be selected or operate above 90% of its motor nameplate rating. Motor size may not be increased to compensate for equipment with efficiency lower than that specified.
B. If a larger motor than specified is required on equipment, the contractor supplying the equipment is responsible for all additional costs due to larger starters, wiring, etc.
2.5 SHEAVES
A. All sheaves shall conform to NEMA Standard MG1-14.42, which lists minimum diameters and maximum overhangs. Locate motors to minimize overhang.
B. When replacing sheaves, use sheaves of at least the originally supplied sizes.
C. Contractor responsible for motor shall also be responsible for replacement sheaves.
Coordinate with testing and balancing of the equipment.
PART 3 - EXECUTION
3.1 INSTALLATION
A. All rotating shafts and/or equipment shall be completely guarded from all contact. Partial guards and/or guards that do not meet all applicable OSHA standards are not acceptable.
Contractor is responsible for providing this guarding if it is not provided with the equipment supplied.
PMIS/PKG NO. 242900/253127 21 05 13 - 4
B. For flexible coupled drive motors, mount coupling to the shafts in accordance with the coupling manufacturer’s recommendations. Align shafts to manufacturer’s requirements or within 0.002 inch per inch diameter of coupling hub.
END OF SECTION 21 05 13
PMIS/PKG NO. 242900/253127 21 05 29 - 1
FIRE SUPPRESSION SUPPORTS AND ANCHORS
SECTION 21 05 29 - FIRE SUPPRESSION SUPPORTS AND ANCHORS
1.1 SECTION INCLUDES
A. Hangers, Supports, and Associated Anchors.
B. Equipment Bases and Supports.
C. Sleeves and Seals.
D. Flashing and Sealing of Equipment and Pipe Stacks.
E. Cutting of Openings.
F. Escutcheon Plates and Trim.
1.2 QUALITY ASSURANCE
A. Support Sprinkler Piping in conformance with NFPA 13.
B. Support Standpipes in conformance with NFPA 14.
1.3 WORK FURNISHED BUT INSTALLED UNDER OTHER SECTIONS
A. Furnish sleeves and hanger inserts to General Contractor for placement into formwork.
PART 2 - PRODUCTS
2.1 SEISMIC RESTRAINTS
A. Refer to Section 21 05 50 for additional requirements for seismic restraints.
2.2 HANGER RODS
A. Hanger rods for single rod hangers supporting steel, copper, and CPVC piping shall conform to the following:
Pipe Size Rod Size
4" and smaller 3/8”
5”, 6", 8” 1/2”
10" and12" 5/8”
B. Hanger rods and accessories used in mechanical spaces or otherwise dry areas shall have
ASTM B633 electro-plated zinc finish.
2.3 PIPE HANGERS AND SUPPORTS
A. General:
1. All pipe hangers, clamps, and supports shall conform to Manufacturers
Standardization Society MSS-SP-58, 69, 89, and 127 (where applicable).
PMIS/PKG NO. 242900/253127 21 05 29 - 2
B. Vertical Supports:
1. Support and laterally brace vertical pipes at every floor level in multi-story structures, and more frequently when required by applicable codes, but never at intervals over 15 feet. Support vertical pipes with riser clamps installed below hubs, couplings or lugs. Provide sufficient flexibility to accommodate expansion and contraction without compromising fire barrier penetrations and other fixed takeoff locations.
Acceptable Products:
Anvil - Fig. CT121
Cooper/B-Line - Fig. B3373CT
Erico - Model 510
Nibco/Tolco - Fig. 82
2. Wall supports shall be used where vertical height of structure exceeds minimum spacing requirements. Install wall supports at same spacing as hangers or strut supports along vertical length of pipe runs.
3. Masonry Anchors: Fasten to concrete masonry units with expansion anchors or self-tapping masonry screws. For expansion anchors into hollow concrete block, use sleeve-type anchors designed for the specific application. Do not fasten in masonry joints. Do not use powder actuated fasteners, wooden plugs, or plastic inserts.
C. Hangers and Clamps:
1. Hangers in direct contact with bare copper pipe shall include plastic pipe insert similar to Unistrut Cush-A-Clamp, Hydra-Zorb, Erico Cushion Clamp or Cooper
Vibra-Clamp.
2. Unless otherwise indicated, hangers shall be as follows:
a. Clevis Type:
Service: Bare Metal Pipe
Rigid Plastic Pipe
Acceptable Products: Bare Steel, Plastic or Insulated Pipe
Bare Copper Pipe
Anvil Fig. 260 Fig. CT65
Cooper/B-Line Fig. 3100 Fig. B3104CT
Erico Model 400 Model 402
Nibco/Tolco Fig. 1 Fig. 81
b. Adjustable Swivel Ring Type:
Service: Bare Metal Pipe - 4 inches and Smaller
Acceptable Products: Bare Steel Pipe Bare Copper Pipe
Anvil Fig. 69 Fig. CT69
Cooper/B-Line Fig. B3170NF Fig. B170CT
Erico Model FCN
Nibco/Tolco Fig. 200 Fig. 202
PMIS/PKG NO. 242900/253127 21 05 29 - 3
3. Support may be fabricated from U-channel strut or similar shapes. Piping less than
4” in diameter shall be secured to strut with clamps of proper design and capacity as required to maintain spacing and alignment. Strut shall be independently supported from hanger drops or building structure. Size and support shall be per manufacturer’s installation requirements for structural support of piping. Clamps shall not interrupt piping insulation.
4. Strut used in mechanical spaces or otherwise dry areas shall have ASTM B633 electro-plated zinc finish.
5. Strut used in damp areas listed in hanger rods shall have ASTM A123 hot-dip galvanized finish applied after fabrication.
6. Unless otherwise indicated, pipe supports for use with struts shall be as follows:
a. Clamp Type:
Service: Bare Metal Pipe
Rigid Plastic Pipe
1) Clamps in direct contact with copper pipe shall include plastic pipe insert similar to Unistrut Cush-A-Clamp, Hydra-Zorb, Erico
Cushion Clamp or Cooper Vibra-Clamp.
2) Pipes subject to expansion and contraction shall have clamps slightly oversized to allow limited pipe movement.
Acceptable Products: Bare Steel, Plastic or Insulated Pipe
Bare Copper Pipe
Unistrut Fig. P1100 or P2500
Cooper/B-Line Fig. B2000 or B2400 Fig. BVT
Nibco/Tolco Fig. A-14 or 2STR
D. Upper (Structural) Attachments:
1. Unless otherwise shown, upper attachments for hanger rods or support struts shall be as follows:
a. Steel Structure Clamps:
1) C-Type Wide Flange Beam Clamps (for use on top and/or bottom of wide flanges. Not permitted for use with bar-joists.):
Acceptable Products:
Anvil Fig. 92
Cooper/B-Line Fig. B3033/B3034
Erico Model 300
Nibco/Tolco 68
2) Scissor Type Beam Clamps (for use with bar-joists and wide flange):
PMIS/PKG NO. 242900/253127 21 05 29 - 4
Acceptable Products:
Anvil Fig. 228, 292
Cooper/B-Line Fig. B3054
Erico Model 360
Nibco/Tolco Fig. 329
b. Concrete:
1) Concrete Anchors: Fasten to concrete using cast-in or post-installed anchors designed per the requirements of Appendix D of
ACI 318-05. Post-installed anchors shall be qualified for use in cracked concrete by ACI-355.2.
2) Masonry Anchors: Fasten to concrete masonry units with expansion anchors or self-tapping masonry screws. For expansion anchors into hollow concrete block, use sleeve-type anchors designed for the specific application. Do not fasten in masonry joints. Do not use powder actuated fasteners, wooden plugs, or plastic inserts.
c. Steel Structure Welding:
1) Unless otherwise noted, hangers, clips, and auxiliary support steel may be welded in lieu of bolting, clamping, or riveting to the building structural frame. Take adequate precautions during all welding operations for fire prevention and for protecting walls and ceilings from being damaged by smoke.
2.4 FOUNDATIONS, BASES, AND SUPPORTS
A. Basic Requirements:
1. Furnish and install foundations, bases, and supports (not specifically indicated on the Drawings or in the Specifications of either the General Construction or
Mechanical work as provided by another Contractor) for mechanical equipment.
2. All concrete foundations, bases and supports, shall be reinforced. All steel bases and supports shall receive a prime coat of zinc chromate or red metal primer. After completion of work, give steel supports a final coat of gray enamel.
B. Concrete Bases (Housekeeping Pads):
1. Refer to Section 21 05 50 for additional requirements for concrete bases in seismic applications.
2. Unless shown otherwise on the drawings, concrete bases shall be nominal 4 inches thick and shall extend 3 inches on all sides of the equipment (6 inches larger than factory base).
3. Where a base is less than 12 inches from a wall, extend the base to the wall to prevent a “dirt-trap”.
PMIS/PKG NO. 242900/253127 21 05 29 - 5
4. Concrete materials and workmanship required for the Contractor's work shall be provided by him. Materials and workmanship shall conform to the applicable standards of the Portland Cement Association. Reinforce with 6” x 6”, W1.4-W1.4 welded wire fabric. Concrete shall withstand 3,000 pounds compression per square inch at 28 days.
5. Equipment requiring bases is as follows:
a. Fire Pump
C. Supports:
1. Provide sufficient clips, inserts, hangers, racks, rods, and auxiliary steel to securely support all suspended material, equipment and conduit without sag.
2. Hang heavy equipment from concrete floors or ceilings with Architect-approved concrete inserts, furnished and installed by the Contractor whose work requires them, except where indicated otherwise.
D. Grout:
1. Grout shall be non-shrinking premixed (Master Builders Company "Embecco"), unless otherwise indicated on the drawings or approved by the Contracting Officer.
2. Use Mix No. 1 for clearances of 1" or less, and Mix No. 2 for all larger clearances.
3. Grout under equipment bases, around pipes, at pipe sleeves, etc., and where shown on the drawings.
2.5 OPENINGS IN FLOORS, WALLS AND CEILINGS
A. Exact locations of all openings for the installation of materials shall be determined by the
Contractor and given to the General Contractor for installation or construction as the structure is built.
B. Coordinate all openings with other Contractors.
C. Hire the proper tradesman and furnish all labor, material and equipment to cut openings in or through existing structures, or openings in new structures that were not installed, or additional openings. Repair all spalling and damage to the satisfaction of the Contracting
Officer. Make saw cuts before breaking out concrete to ensure even and uniform opening edges.
D. Said cutting shall be at the complete expense of each Contractor. Failure to coordinate openings with other Contractors shall not exempt the Contractor from providing openings at his expense.
E. Do not cut structural members without written approval of the Architect or Structural
Engineer.
PMIS/PKG NO. 242900/253127 21 05 29 - 6
2.6 PIPE SLEEVES AND LINTELS
A. Each Contractor shall provide pipe sleeves and lintels for all openings required for the
Contractor’s work in masonry walls and floors, unless specifically shown as being by others.
B. Fabricate all sleeves from standard weight black steel pipe or as indicated on the drawings.
Provide continuous sleeve. Cut or split sleeves are not acceptable.
C. Fabricate all lintels for masonry walls from structural steel shapes or as indicated on the drawings. Have all lintels approved by the Architect or Structural Engineer.
D. Sleeves through the floors on exposed risers shall be flush with the ceiling, with planed squared ends extending 1" above the floor in unfinished areas, and flush with the floor in finished areas, to accept spring closing floor plates.
E. Sleeves shall not penetrate structural members or masonry walls without approval from the
Structural Engineer. Sleeves shall then comply with the Engineer’s design.
F. Openings through unexcavated floors and/or foundation walls below the floor shall have a smooth finish with sufficient annular space around material passing through opening so slight settling will not place stress on the material or building structure.
G. Install all sleeves concentric with pipes. Secure sleeves in concrete to wood forms. This
Contractor is responsible for sleeves dislodged or moved when pouring concrete.
H. Where pipes rise through concrete floors that are on earthen grade, provide 3/4" resilient expansion joint material (asphalt and cork) wrapped around the pipe, the full depth of concrete, at the point of penetration. Secure to prevent shifting during concrete placement and finishing.
I. Size sleeves large enough to allow expansion and contraction movement. Provide continuous insulation wrapping.
J. Wall Seals ("Link-Seals"):
1. Where shown on the drawings, pipes passing through walls, ceilings, or floors shall have their annular space (sleeve or drilled hole - not tapered hole made with knockout plug) sealed by properly sized sealing elements consisting of a synthetic rubber material compounded to resist aging, ozone, sunlight, water and chemical action.
2. Sleeves, if used, shall be standard weight steel with primed finish and waterstop/anchor continuously welded to sleeve or thermoplastic with integral water seal and textured surface.
3. Sleeves shall be at least 2 pipe sizes larger than the pipes.
4. Pressure shall be maintained by stainless steel bolts and other parts. Pressure plates may be of composite material for Models S and OS.
PMIS/PKG NO. 242900/253127 21 05 29 - 7
5. Sealing element shall be as follows:
Model Service Element
Material
Temperature
Range
T Fire Seals (1 hour) Silicone -67ºF to 400ºF
6. Acceptable Manufacturers: Thunderline Corporation "Link-Seals", O-Z/Gedney
Company, Calpico, Inc., Innerlynx, or Metraflex Company (cold service only).
2.7 ESCUTCHEON PLATES AND TRIM
A. Fit escutcheons to all insulated or uninsulated exposed pipes passing through walls, floors, or ceilings of finished rooms.
B. Escutcheons shall be heavy gauge, cold rolled steel, copper coated under a chromium plated finish, heavy spring clip, rigid hinge and latch.
C. Install galvanized steel (unless otherwise indicated) trim strip to cover vacant space and raw construction edges of all rectangular openings in finished rooms. This includes duct and pipe openings.
2.8 PIPE PENETRATIONS
A. Seal all pipe penetrations. Seal non-rated walls and floor penetrations with grout or caulk.
Backing material may be used.
B. Seal fire rated wall and floor penetrations with fire seal system as specified.
2.9 PIPE ANCHORS
A. Provide all items needed to allow adequate expansion and contraction of all piping. All piping shall be supported, guided, aligned, and anchored as required.
B. Repair all piping leaks and associated damage. Pipes shall not rub on any part of the building.
2.10 FINISH
A. Prime coat exposed steel hangers and supports. Hangers and supports in crawl spaces, pipe shafts, and suspended ceiling spaces are not considered exposed.
PART 3 - EXECUTION
3.1 FIRE SUPPRESSION SUPPORTS AND ANCHORS
A. General Installation Requirements:
1. Install all items per manufacturer's instructions.
2. Coordinate the location and method of support of piping systems with all installations under other Divisions and Sections of the Specifications.
PMIS/PKG NO. 242900/253127 21 05 29 - 8
3. Where pipe support members are welded to structural building framing, scrape, brush clean, and apply one coat of zinc rich primer to welding.
4. Supports shall extend directly to building structure. Do not support piping from duct hangers. Do not allow lighting or ceiling supports to be hung from piping supports.
B. Supports Requirements:
1. Install roof pipe supports to resist wind movement per manufacturer’s recommendations. Method of securing base to roof shall be compatible with roofing materials.
2. Where building structural steel is fireproofed, all hangers, clamps, auxiliary steel, etc., which attach to it shall be installed prior to application of fireproofing. Repair all fireproofing damaged during pipe installation.
3. Set all concrete inserts in place before pouring concrete.
4. Furnish, install and prime all auxiliary structural steel for support of piping systems that are not shown on the Drawings as being by others.
5. Install hangers and supports complete with lock nuts, clamps, rods, bolts, couplings, swivels, inserts and required accessories.
6. Hangers for horizontal piping shall have adequate means of vertical adjustment for alignment.
C. Pipe Requirements:
1. Support all piping and equipment, including valves, strainers, and other specialties and accessories to avoid objectionable or excessive stress, deflection, swaying, sagging or vibration in the piping or building structure during erection, cleaning, testing and normal operation of the systems.
2. Do not, however, restrain piping to cause it to snake or buckle between supports or to prevent proper movement due to expansion and contraction.
3. Support piping at equipment and valves so they can be disconnected and removed without further supporting the piping.
4. Piping shall not introduce strains or distortion to connected equipment.
5. Parallel horizontal pipes may be supported on trapeze hangers made of structural shapes and hanger rods; otherwise, pipes shall be supported with individual hangers.
6. Trapeze hangers may be used where ducts interfere with normal pipe hanging.
7. Provide additional supports where pipe changes direction, adjacent to flanged valves and strainers, at equipment connections and heavy fittings.
8. Provide at least one hanger adjacent to each joint in grooved end steel pipe with
PMIS/PKG NO. 242900/253127 21 05 29 - 9
mechanical couplings.
D. Provided the installation complies with all loading requirements of truss and joist manufacturers, the following practices are acceptable:
1. Loads of 100 lbs. or less may be attached anywhere along the top or bottom chords of trusses or joists with a minimum 3’spacing between loads.
2. Loads greater than 100 lbs. must be hung concentrically and may be hung from top or bottom chord, provided one of the following conditions is met:
a. The hanger is attached within 6” from a web/chord joint.
b. Additional L2x2x1/4 web reinforcement is installed per manufacturer’s requirements.
3. It is prohibited to cantilever a load using an angle or other structural component that is attached to a truss or joist in such a fashion that a torsional force is applied to that structural member.
4. If conditions cannot be met, coordinate installation with truss or joist manufacturer and contact Contracting Officer.
E. After piping and insulation installation are complete, cut hanger rods back at trapeze supports so they do not extend more than 3/4" below bottom face of lowest fastener and blunt any sharp edges.
F. Do not exceed 25 lbs. per hanger and a minimum spacing of 2’-0” on center when attaching to metal roof decking (limitation not required with concrete on metal deck). This 25 lbs.
load and 2’-0” spacing include adjacent electrical and architectural items hanging from deck. If the hanger restrictions cannot be achieved, supplemental framing off steel framing will need to be added.
G. Do not exceed the manufacturer's recommended maximum load for any hanger or support.
H. Spacing of hangers shall in no case exceed the following:
Pipe Material Maximum Spacing
1. Steel (All steel pipe unless otherwise noted):
1-1/4" & under 12'-0"
1-1/2" & larger 15'-0"
2. Steel (Schedule 40 lightweight alternative):
3" & under 12'-0"
3. Hard Drawn Copper:
1" & under 8'-0"
1-1/4" to 1-1/2" 10'-0"
2" to 3" 12'-0"
3-1/2" & larger 15'-0"
PMIS/PKG NO. 242900/253127 21 05 29 - 10
I. Installation of hangers shall conform to MSS SP-58, 69, 89, and applicable NFPA standards.
END OF SECTION 21 05 29
PMIS/PKG NO. 242900/253127 21 05 48 - 1
FIRE PROTECTION VIBRATION ISOLATION
SECTION 21 05 48 - FIRE PROTECTION VIBRATION ISOLATION
1.1 SECTION INCLUDES
A. Bases.
B. Vibration Isolation.
C. Flexible Connectors.
1.2 SUBMITTALS
A. Submit shop drawings per Section 01 33 23.
B. Vibration isolation submittals may be included with equipment being isolated but must comply with this section.
C. Base submittals shall include equipment served, construction, coatings, weights, and dimensions.
D. Isolator submittals shall include:
1. Equipment served
2. Type of Isolator
3. Load in Pounds per Isolator
4. Recommended Maximum Load for Isolator
5. Spring Constants of Isolators (for Spring Isolators)
6. Load vs. Deflection Curves (for Neoprene Isolators)
7. Specified Deflection
8. Deflection to Solid (at least 150% of calculated deflection)
9. Loaded (Operating) Deflection
10. Free Height
11. Loaded Height
12. Kx/Ky (horizontal to vertical stiffness ratio – for spring isolators)
13. Materials and Coatings
14. Spring Diameters
E. Make separate calculations for each isolator on equipment where the load is not equally distributed.
F. Flexible connector shop drawings shall include overall face-to-face length and all specified properties.
G. Submit certification that equipment, accessories, and components will withstand seismic forces defined in Section 21 05 50. Include the following:
1. Basis for Certification: Indicate whether certification is based on actual test of assembled components or on calculation.
a. The term "withstand" means "the unit will remain in place without separation of any parts from the device when subjected to the seismic forces specified."
PMIS/PKG NO. 242900/253127 21 05 48 - 2
2. Dimensioned Outline Drawings of Equipment Unit: Identify center of gravity and locate and describe mounting and anchorage provisions.
3. Detailed description of equipment anchorage devices on which the certification is based and their installation requirements.
PART 2 - PRODUCTS
2.1 BASIC CONSTRUCTION AND REQUIREMENTS
A. Vibration isolation for this project is subject to seismic restraint requirements of
Section 21 05 50.
B. Vibration isolators shall have either known undeflected heights or other markings so deflection under load can be verified.
C. All isolators shall operate in the linear portion of their load versus deflection curve. The linear portion of the deflection curve of all spring isolators shall extend 50% beyond the calculated operating deflection (e.g., 3" for 2" calculated deflection). The point of 50% additional deflection shall not exceed the recommended load rating of the isolator.
D. The lateral to vertical stiffness ratio (Kx/Ky) of spring isolators shall be between 0.8 and
2.0.
E. All isolators shall be designed or treated for corrosion resistance. Steel bases shall be cleaned of welding slag and primed for interior use. Bolts, nuts and washers shall be zinc electroplated. All damage to coatings shall be field repaired with two coats of zinc rich coating.
F. Equip all mountings used with structural steel bases with height-saving brackets. Bottoms of the brackets shall be 1-1/2" to 2-1/2" above the floor or housekeeping pad, unless shown otherwise on the drawings. Steel bases shall have at least four points of support.
G. Provide motor slide rails for belt-driven equipment per Section 21 05 13.
H. All isolators, except M1, shall have provision for leveling.
2.2 MOUNTINGS
A. Type M3:
1. Free standing, laterally stable spring isolators without housings and complete with 1/4" neoprene friction pads.
2. Units shall have bolt holes but need not be bolted down unless called for or needed to prevent movement. If bolted down, prevent short circuiting with neoprene bushings and washers between bolts and isolators. Bolt holes shall not be within the springs.