B08_Attachment_1a_Project_Manual_VOL_1.pdf

PDF 8 MB Posted

Attached to
Old Courthouse Phase 2 Renovations, Gateway Arch N Federal contract opportunity
Solicitation number
140P2022R0159
Issued by
Department of the Interior National Park Service National Office

About this file

This solicitation is for the Old Courthouse Phase 2 Renovations project at Gateway Arch National Park in St. Louis, Missouri. The work includes installation of a new interior elevator, accessibility improvements, replacement of the existing steam radiator system with a new 4-pipe mechanical system, upgrades to fire suppression, lighting, power, security and IT infrastructure, and structural reinforcement. The solicitation also requires hazardous material abatement including asbestos, lead, and household hazardous waste removal. Responses are due by July 15, 2022. The National Park Service will award a single prime contract for the project.

View the file

Other files for this federal contract opportunity

Other files attached to Old Courthouse Phase 2 Renovations, Gateway Arch N, newest first.
File Type Posted
Amendment_09_Questions_and_Answers_9-9-22_09.docx DOCX document
Sol_140P2022R0159_Amd_09.pdf PDF
Amendment_09_SF_30_9-9-22_09.pdf PDF
Amendment_08_Ground_Penetrating_Radar_08.docx DOCX document
Amendment_08_STL_OCH_Ramp_Project_Irrigation_As_Built__08.pdf PDF
Amendment_08_Questions_and_Answers_9-8-22_08.docx DOCX document
Amendment_08_SF_30_9-8-22_08.pdf PDF
Sol_140P2022R0159_Amd_08.pdf PDF
Amendment_07_Questions_and_Answers_9-2-22_07.docx DOCX document
Sol_140P2022R0159_Amd_07.pdf PDF
Amendment_07_SF_30_9-2-22_07.pdf PDF
Amendment_06_AS_BUILTS__JEFF_007895__Unistrut_Catwalk_06.pdf PDF
Amendment_06_Wage_Determination_MO20220051_7-29-22_06.pdf PDF
Sol_140P2022R0159_Amd_06.pdf PDF
Amendment_06_SF_30_8-26-22_06.pdf PDF
Amendment_06_Questions_and_Answers_8-26-22_06.docx DOCX document
Amendment_05_08_24_22_Contractor_Walk_Thru_at_the_OCH_05.pdf PDF
Sol_140P2022R0159_Amd_05.pdf PDF
Amendment_05_08_16_22_OCH_CONTRACTOR_SIGN_IN_05.pdf PDF
Amendment_05_SF_30_8-25-22_05.pdf PDF
Amendment_05_Questions_and_Answers_8-25-22_05.docx DOCX document
Amendment_05_08_18_22_OCH_CONTRACTOR_SIGN_IN_05.pdf PDF
Amendment_04_SF_30_8-19-22_04.pdf PDF
Amendment_04_Questions_and_Answers_8-19-22_04.docx DOCX document
Sol_140P2022R0159_Amd_04.pdf PDF
Amendment_03_Questions_and_Answers_8-12-22_03.docx DOCX document
Sol_140P2022R0159_Amd_03.pdf PDF
Amendment_03_Old_Courthouse_Preservation_Plan_Matrix_2022_08_03_03.pdf PDF
Amendment_03_SF_30_8-12-22_03.pdf PDF
Amendment_03_Past_Performance_Questionaire_03.docx DOCX document
Amendment_03_Project_Experience_Form_03.docx DOCX document
Amendment_02__Sign_In_Sheet_140P2022R0159_GANP_242900___2537127_02.pdf PDF
Amendment_02_PreBid_Conference_Presentation_7-29-22_02.pptx PPTX presentation
Amendment_02_Questions_and_Answers_8-9-22_02.docx DOCX document
Amendment_02_SF_30_8-9-22_02.pdf PDF
Amendment_02_TripReport_Schilling_and_Devore_11_20_final_02.pdf PDF
Sol_140P2022R0159_Amd_02.pdf PDF
Amendment_01_SF_30_7-29-22_01.pdf PDF
Sol_140P2022R0159_Amd_01.pdf PDF
Amendment_01_Questions_and_Answers_7-29-22_01.docx DOCX document
B08_Attachment_4_Wage_Determination_5-27-2022.pdf PDF
B08_GANP_242900_Sol_140P2022R0159_SF1442_and_Clauses_7-25-22.pdf PDF
Sol_140P2022R0159.pdf PDF
B08_Attachment_3b_DOI_Memo_Certification_of_Vaccination_Form.pdf PDF
B08_Attachment_5_Proposal_Submission_Package_Portfolio_7-25-22.pdf PDF
B08_Attachment_1b_Project_Manual_VOL_2.pdf PDF
B08_Attachment_2_Drawings.pdf PDF
B08_Attachment_1c_Project_Manual_VOL_3.pdf PDF
B08_Attachment_1d_Project_Manual_VOL_4.pdf PDF
B08_Attachment_3a_DOI_Memo_Implementation_of_Cert.pdf PDF
Show all 50

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GATEWAY ARCH NATIONAL PARK

ST. LOUIS, MO

OLD COURTHOUSE ACCESSIBILITY IMPROVEMENTS PHASE 2

PMIS/PKG NO. 242900/253127

Final Construction Documents

NATIONAL PARK SERVICE

DENVER SERVICE CENTER

July 1, 2022

VOLUME 1 OF 4

PMIS/PKG NO. 242900/253127 00 01 01 - 1

PROJECT DIRECTORY

SECTION 00 01 01 – PROJECT DIRECTORY

Specifications for Gateway Arch National Park Old Courthouse Accessibility Improvements Phase 2 St. Louis, Missouri

PMIS # 199879

Owner Gateway Arch Park Foundation National Park Service Midwest Regional Office (MWRO)

Architect Trivers 100 N. Broadway, Ste. 1800 St. Louis, MO 63102 Telephone: 314-241-2900 Fax: 314-241-2909 Amy Gilbertson, FAIA agilbertson@trivers.com

Civil Engineer Civil Design, Inc.

1552 S. 7th St.

St. Louis, MO 63104 Telephone: 314-863-5570

Structural Engineer KPFF Consulting Engineers 1630 Des Peres Rd., Ste. 100 St. Louis, MO 63131 Telephone: 314-835-0524

MEP Engineer IMEG Corp 15 Sunnen Dr., Suite 104 Maplewood, Missouri 63143 Telephone: 314.645.1132

Accessibility Consultant Cohen Hilberry 4941 McPherson Ave St. Louis, MO 63108 Telephone: 314.367.8300

Landscape Architect SWT Design 7722 Big Bend Blvd St. Louis, MO 63119 Telephone: 314.644.5700

Signage Consultant Kuhlmann Leavitt 7400 Pershing Ave St. Louis, MO 63130 Telephone: 314.369.6616

PMIS/PKG NO. 242900/253127 00 01 01 - 2

PROJECT DIRECTORY

Environmental Engineering Professional Environmental Engineers, Inc.

2665 Scott Ave, Suite B St. Louis, MO 63103 Telephone: 314.486.3772

Elevator Consultant KH Lemp 211 Third St, Valley Park, MO 63088 Telephone: 314.560.5300

Smoke Modeling Code Consultants, Inc.

2043 Woodland Pkwy, #300 St. Louis, MO 63146 Telephone: 314.991.2633

Ground Penetrating Radar Scanning Geotechnology, Inc.

11816 Lackland Road, Suite 150 St. Louis, MO 63146 Telephone: 314.280.9850

Cost Estimating Crawford Consulting 239 Highland Avenue East Pittsburgh, PA 15112 Telephone: 412.823.0400

Exhibit Design Haley Sharpe Design 11-15 Guildhall Lane, Leicester, LE1 5FQ, United Kingdom Telephone: +44.776.840.0281

PMIS/PKG NO. 242900/253127 000116 - 1

TABLE OF CONTENTS

SECTION 000116 - TABLE OF CONTENTS

DIVISION 00 – PROCUREMENT & CONTRACTING REQUIREMENTS

(to be included in Final Construction Documents when issued for bid)

000101 Project Directory 000107 Seals Page 000115 List of Sheets 000116 Table of Contents 001113 Advertisement for Bids 002113 Instructions to Bidders 002513 Pre-Bid Meetings 003113 Preliminary Schedules 003119 Existing Conditions Information 003126 Existing Hazardous Material Information 003132 Geotechnical Data 003143 Permit Application 004113 Bid Form – Stipulated Sum (Single Prime Contract) 004313 Bid Security Forms 006000 Project Forms

DIVISION 01 - GENERAL REQUIREMENTS

011100 Summary of Work 012601 Contract Modification Procedures 012700 Definition of Contract Line Items 013100 Project Management & Coordination 013216 Construction Schedule 013233 Photographic Documentation for Historic Preservations Projects 013323 Submittal Procedures 013513 Archeological Protection 013523 Safety Requirements 013591 Historic Preservation Treatment Procedures 014000 Quality Requirements 014200 Reference Standards 015000 Temporary Facilities and Controls 015719 Indoor Air Quality Management 015723 Storm Water Pollution Prevention / Under-An-Acre Pollution Prevention 016700 Product Requirements 017329 Cutting and Patching 017340 Execution 017419 Construction Waste Management and Disposal 017700 Closeout Procedures 017823 Operation and Maintenance Data 017900 Demonstration and Training 018113 Sustainable Design Requirements 019113 Commissioning Requirements

PMIS/PKG NO. 242900/253127 000116 - 2

DIVISION 02 – EXISTING CONDITIONS

024119 Selective Demolition 024296 Historic Removal and Dismantling 028200 Asbestos Abatement 028300 Lead Renovation, Repair, Painting 028600 Disposal of Hazardous Waste

DIVISION 03 – CONCRETE

033000 Cast-In-Place Concrete

DIVISION 04 – MASONRY

042200 Concrete Unit Masonry

DIVISION 05 – METALS

051200 Structural Steel 055000 Metal Fabrications 057000 Decorative Metal 057313 Glazed Decorative Metal Railings

DIVISION 06 – WOODS, PLASTICS & COMPOSITES

061053 Miscellaneous Rough Carpentry 062023 Interior Finish Carpentry

DIVISION 07 – THERMAL & MOISTURE PROTECTION

071616 Crystalline Waterproofing 078413 Penetration Firestopping 078443 Joint Firestopping 079200 Joint Sealants 079219 Acoustical Joint Sealants

DIVISION 08 – OPENINGS

080352 Historic Treatment of Wood Windows 081113 Hollow Metal Doors and Frames 081433 Stile and Rail Wood Doors 083113 Access Doors and Frames 087100 Door Hardware 089119 Fixed Louvers

DIVISION 09 – FINISHES

090320 Historic Treatment of Plaster

PMIS/PKG NO. 242900/253127 000116 - 3

092216 Non-Structural Metal Framing 092900 Gypsum Board 093013 Ceramic Tiling 096340 Stone Flooring 096519 Resilient Tile Flooring 096813 Tile Carpeting 096816 Sheet Carpeting 099113 Exterior Painting 099123 Interior Painting

DIVISION 10 – SPECIALTIES

101400 Wall Signage 102800 Toilet, Bath & Laundry Accessories 102920 Bird & Pest Anti-Roosting System 104416 Fire Extinguishers

DIVISION 11 – EQUIPMENT

113013 Residential Appliances

DIVISION 12 – FURNISHINGS

122413 Roller Window Shades 123216 Manufactured Plastic-Laminate-Clad Casework 123661 Solid Surfacing Countertops

DIVISION 13 – SPECIAL CONSTRUCTION

Not Used

DIVISION 14 – CONVEYING EQUIPMENT

142400 Hydraulic Elevators

DIVISION 21 – FIRE SUPPRESSION

210500 Basic Fire Suppression Requirements 210505 Fire Suppression Demolition for Remodeling 210513 Motors 210529 Fire Suppression Supports and Anchors 210548 Fire Protection Vibration Isolation 210550 Seismic Requirements for Equipment and Supports 210553 Fire Suppression Identification 211300 Fire Protection Systems 213000 Fire Pumps 211500 Nitrogen Generation Corrosion Inhibiting System

DIVISION 22 – PLUMBING

PMIS/PKG NO. 242900/253127 000116 - 4

220500 Basic Plumbing Requirements 220505 Plumbing Demolition for Remodeling 220513 Motors 220529 Plumbing Supports and Anchors 220550 Seismic Requirements for Equipment and Supports 220553 Plumbing Identification 220719 Plumbing Piping Insulation 221000 Plumbing Piping 221030 Plumbing Specialties 221429 Sump Pumps 224000 Plumbing Fixtures

DIVISION 23 – HEATING, VENTILATION AND AIR CONDITIONING (HVAC)

230500 Basic HVAC Requirements 230505 HVAC Demolition for Remodeling 230513 Motors 230516 HVAC Expansion Compensation 230529 HVAC Supports and Anchors 230548 HVAC Vibration Isolation 230550 Seismic Requirements for Equipment and Supports 230553 HVAC Identification 230593 Testing, Adjusting and Balancing 230713 Ductwork Insulation 230716 HVAC Equipment Insulation 230719 HVAC Piping Insulation 230900 Controls 230913 Instrumentation 231000 Fuel Storage and Delivery Systems 232100 Hydronic Piping 232123 HVAC Pumps 232200 Steam and Steam Condensate Piping 232218 Steam and Steam Condensate Specialties 232500 Chemical (Water) Treatment 233100 Ductwork 233300 Ductwork Accessories 233416 Centrifugal Fans 233700 Air Inlets and Outlets 234000 Air Cleaning 235700 Heat Exchangers 236430 Air Cooled Water Chillers 238126 Split System Air Conditioning Units 238200 Terminal Heat Transfer Units

DIVISION 26 – ELECTRICAL

260500 Basic Electrical Requirements 260505 Electrical Demolition for Remodeling

PMIS/PKG NO. 242900/253127 000116 - 5

260513 Wire and Cable 260517 Electrical Heat Trace and Snow Melt 260526 Grounding and Bonding 260527 Supporting Devices 260533 Conduit and Boxes 260535 Surface Raceways 260548 Seismic Requirements for Equipment and Supports 260553 Electrical Identification 260573 Power System Study 260933 Lighting Control Systems 262000 Service Entrance 262200 Dry Type Transformers 262413 Switchboards 262416 Panelboards 262726 Wiring Devices 262816 Disconnect Switches 262923 Variable Frequency Drives 263213 Packaged Engine Generator Systems 263600 Transfer Switch 264300 Surge Protection Devices 265100 Lighting

DIVISION 27 – COMMUNICATIONS

270500 Basic Communications Systems Requirements 270505 Technology Demolition for Remodeling 270528 Interior Communication Pathways 270533 Conduit and Boxes 270553 Identification and Administration 271100 Communication Equipment Rooms 271300 Backbone Cabling Requirements 271500 Horizontal Cabling Requirements 271710 Testing 271720 Support and Warranty

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

280500 Basic Electronic Safety and Security Systems Requirements 281300 Electronic Access Control 281600 Intrusion Detection System 282300 Video Surveillance 283100 Fire Alarm and Detection Systems

DIVISION 31 – EARTHWORK

311000 Site Clearing 312000 Elevator Excavation 312001 Interior Building Excavation 312323 Flowable Fill

PMIS/PKG NO. 242900/253127 000116 - 6

DIVISION 32 – EXTERIOR IMPROVEMENTS

321313 Concrete Paving 321416 Brick Unit Paving 323119 Metal Railings and Fences 329200 Turf and Grasses 329300 Plants 331116 Water Utility Distribution Piping

APPENDICES:

Appendix A Product Data (For Information Only)*

Appendix B Statement of Structural Tests and Inspections

Appendix C Not Used

Appendix D Not Used

Appendix E Not Used

Appendix F Not Used

Appendix G Signage and Wayfinding

Appendix H Asbestos, Lead and HHW Removal Work Plan & Report of Findings

Appendix I Under an Acre Pollution Prevention Plan [UPPP] – For Reference

Appendix J Subsurface Scanning Report (For Information Only)*

Appendix K Energy Analysis (For Information Only)*

Appendix L Smoke Model Analysis Including Egress Analysis (For Information Only)*

Appendix M Not Used

Appendix N Not Used

Appendix O Structural Calculation Package (For Information Only)*

Appendix P Electrical Calculation Package (For Information Only)*

Appendix Q Excerpt from the Historic Preservation Plan: Part II: General Hierarchy of Decisions and

Protections (For Information Only)*

Appendix R Accessibility Report (For Information Only)*

PMIS/PKG NO. 242900/253127 000116 - 7

Appendix S Historic Structures Report (For Information Only)*

Appendix T Historic Preservation Plan Matrix (will be issued as an amendment)

*Appendices noted with an asterisk are provided for contractor’s reference only; refer to Construction Drawings and Specifications for design intent and scope.

PMIS/PKG NO. 242900/253127 01 11 00 - 1

051121 SUMMARY OF WORK

SECTION 011100 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes the following:

1. Work covered by the Contract Documents.

2. Work phases.

3. Work under other contracts.

4. Government Furnished Materials.

5. Contractor use of premises.

6. Public use of site.

7. Occupancy requirements for buildings.

8. Work Restrictions.

9. Special Construction Requirements.

10. Soils Investigation Report.

11. Additional Reports.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Location: The Old Courthouse in Gateway Arch National Park, St. Louis, MO.

B. The Work consists of the following:

1. The Work includes installation of a new interior elevator, accessibility improvements, family restrooms, floor ramps, interior wayfinding signage, replacement of existing steam radiator system with new 4-pipe mechanical system, new fire-sprinkler system with detectors and alarms, upgrades to lighting, power, security and IT infrastructure, structural floor reinforcement, and replacement of window sashes and repair/ refurbishment of window frames. Work also includes removal and disposal of asbestos containing materials, lead-based paint and household hazardous waste items as noted in a Work Plan included in the Appendices of the Construction Documents.

C. Project will be constructed under a single prime contract.

1.3 WORK UNDER OTHER CONTRACTS

A. General: Cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate the Work of this Contract with work performed under separate contracts.

B. Future Work: Government will award separate contract(s) for the following additional work to be performed at site after Substantial Completion. Completion of that work will depend on successful completion of preparatory work under this Contract.

PMIS/PKG NO. 242900/253127 01 11 00 - 2

1. A separate contract will be awarded for renovation/improvements to exhibit galleries.

1.4 CONTRACTOR USE OF SITE

A. General: Contractor shall have full use of the site for construction operations during the construction period. Contractor's use of the site is limited only by the Government's right to perform work or to retain other contractors on portions of Project.

B. Storage of Materials: Subject to allowable site loading restrictions, confine storage of materials to the Southwest and Northwest courtyards. Occupy the surrounding sidewalk only with permission of the Contracting Officer.

C. Preservation of Natural Features:

1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

2. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer and remove agreed-on roots and branches that interfere with construction.

3. Do not fasten ropes, cables, or guys to existing trees.

4. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.

1.5 PUBLIC USE OF SITE

A. The building will be closed to the public during construction.

1.6 OCCUPANCY REQUIREMENTS FOR BUILDINGS

A. Existing Buildings

1. The Government will occupy a room in the North basement during the contract period.

Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government's day-to-day operations. Maintain existing exits, unless otherwise indicated.

a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the Contracting Officer.

b. Maintain existing building in a weather tight condition throughout construction period. Repair damage caused by construction operations. Protect building and its occupants during construction period.

PMIS/PKG NO. 242900/253127 01 11 00 - 3

1.7 CONDUCT OF OPERATIONS

A. At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.

B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed without prior consent from the Contracting Officer. Submit requests 48 hours in advance of the work to the Contracting Officer for approval.

C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.

1.8 WORK RESTRICTIONS

A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 8 a.m. to 5 p.m., Monday through Friday, except when otherwise indicated.

1. Weekend Hours: Only with prior written permission from the Contracting Officer

2. Early Morning Hours: Only with prior written permission from the Contracting Officer.

3. Hours for core drilling, concrete sawing, and other noise/vibration causing construction activities: To be established by Contracting Officer

B. Existing Utilities

1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.

2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.

3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

1. Notify Contracting Officer not less than seven days in advance of proposed utility interruptions.

2. Do not proceed with utility interruptions without Contracting Officer’s written permission.

3. Utility interruptions shall not exceed 4 hours.

D. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor air intakes.

1.9 SPECIAL CONSTRUCTION REQUIREMENTS

A. Project Website: A project website administered by the NPS will be used for purposes of managing communication and documents during the construction stage.

PMIS/PKG NO. 242900/253127 01 11 00 - 4

1. See Section 01 31 00 “Project Management and Coordination” for requirements on using the Project Website.

1.10 ADDITIONAL REPORTS

A. Reports regarding ground penetrating radar investigation of the interior floors and toxic materials inspections have been prepared.

B. Copies of the reports are available to all plan holders with this package.

C. If conflicts occur between the report and drawings or specifications, the drawings and specifications govern.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 011100

PMIS/PKG NO. 242900/253127 01 26 01 - 1

012721 CONTRACT MODIFICATION PROCEDURES

PART 1 - SECTION 012601 – CONTRACT MODIFICATION PROCEDURES

PART 2 - GENERAL

2.1 SUMMARY

A. The work of this section consists of administrative and procedural requirements for contract modifications.

2.2 DEFINITIONS AND ALLOWANCES

A. Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):

1. Rent

2. Utilities

3. Furnishings

4. Office equipment

5. Executive and management staff not exclusively assigned to the project

6. Support, accounting, and administrative staff

7. Preparation of cost proposals, estimating, and schedule analyses connected with

Modifications

8. Estimating and preconstruction services

9. Mortgage costs

10. Real estate and corporate taxes

11. Automobile maintenance and travel costs for home office personnel

12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.

13. Depreciation of equipment and other assets

14. Home office supplies (paper, staples, etc.)

15. Legal services

16. Accounting and data processing

17. Professional fees/registration

B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:

1. Project Manager, Assistant Project Manager

2. Superintendent, Assistant Superintendent

3. Quality Control, Safety Officer, Environmental Manager, etc.

4. Engineers

5. Travel, lodging, and per diem (as established by Federal Travel Regulations)

PMIS/PKG NO. 242900/253127 01 26 01 - 2

6. Scheduling

7. Field Office Trailers and associated temporary utilities

8. Field office supplies

a. Mailing and couriers

b. Reproduction costs

c. Storage

d. Phones

e. Computers

f. Copiers

9. Personal vehicles i.e., Superintendent Pickup trucks

C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating General Requirements:

1. Hoisting

2. Material handling

3. Temporary fencing

4. Port-a-lets

5. Trash removal, dumpsters

6. Barricades

7. Small tools

8. Safety supplies

9. Scaffolding

10. Daily cleaning

11. Traffic control

12. Temporary signage

13. Temporary heating and power

D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40-hour week and no overtime or holiday pay will be allowed.

1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:

a. Base Rate: This is the hourly rate paid directly to the worker

b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums , such as:

1) Social Security

2) Medicare

3) Workers Compensation– Policy and company calculation to be made available.

4) FUTA– Cap Rate and percentage to be proportionally allocated over one year.

5) SUTA– Cap Rate and percentage to be proportionally allocated over one year.

PMIS/PKG NO. 242900/253127 01 26 01 - 3

6) Union agreement costs – Other costs required under an enforceable collective bargaining agreement.

c. Fringe Benefits: Various non-wage compensations provided to employees such as:

1) Health Care Insurance Premiums

2) Cell Phone

3) Clothing

4) 401K and Pensions

5) Vehicle allowances

6) Gas allowance

7) Life insurance premiums

8) Disability insurance

9) Other Fringe Benefits required under an enforceable collective bargaining agreement

E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.

F. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.

G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.

H. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.

2.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS

A. General:

1. Your proposal must be received in the format and within the time frame specified in the Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.

2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement.

Contractor may utilize the government provided Contractor Estimate Form, or their ow http://en.wikipedia.org/wiki/Employee http://en.wikipedia.org/wiki/Surety_bond http://en.wikipedia.org/wiki/Insurance http://en.wikipedia.org/wiki/Bank http://www.nps.gov/dscw/publicforms.htm

PMIS/PKG NO. 242900/253127 01 26 01 - 4

n form, provided that it contains the same information and level of detail as the Gov’t provided form.

3. Requests for extensions of contract time as a result of this change must be justified with a Time Impact Analysis (TIA). Refer to Division 01 Specification, “Construction Schedule”, for time impact analysis requirements. TIA and associated costs must be received with the proposal by the date shown within the Request for Proposal letter.

Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving the right for additional time and no time extension will be allowed.

4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.

5. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.

6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.

B. Labor:

1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work.

Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.

2. Itemize labor costs for equipment operators separate from equipment costs.

3. The labor cost for foremen shall only be costs for related work required for the modification.

C. Materials:

1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.

2. No markup shall be applied to any material provided by the NPS.

D. Equipment:

1. Equipment used for the project must be appropriately sized for the work being performed.

2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.

3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:

a. U.S. Army Corps of Engineers, Ownership and Operating Expense Schedule (use latest edition and applicable region)

b. Construction Blue Book

PMIS/PKG NO. 242900/253127 01 26 01 - 5

c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.

4. The estimated equipment rates shall include the operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per FAR 31.105(d)(2)), depreciation, storage, insurance, and all incidentals.

Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.

5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.

6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above. If the US Army Corp of Engineers is utilized, then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs, major repair and overhaul will be accepted.

7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.

8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.

9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.

10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.

E. Establishment and Application of Overhead and Profit Percentages:

1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.

Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work. For contract modifications where Prime Contractor does not self-perform the work the maximum percentage shall be 3%:

Overhead…………8% Profit……………9.2%

2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.

3. If contractors form a partnership, than the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3,E,1 above). It is the responsibility of the partners to decide on the division of revenue.

4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.

5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.

PMIS/PKG NO. 242900/253127 01 26 01 - 6

PART 3 - PRODUCTS

PART 4 - EXECUTION

END OF SECTION 012601

PMIS/PKG NO. 242900/253127 01 27 00 - 1

082714 DEFINITION OF CONTRACT LINE ITEMS

SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS

PART 1 - GENERAL

1.1 SUMMARY

A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends, and another begins.

B. If no contract line item exists for a portion of the work, include the costs in a related item.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 LIST OF CONTRACT LINE ITEMS

Reduce Deferred Maintenance on Old Courthouse (PMIS 253127 Partner Centennial)

Base Bid – Contract Line Item No. 0001 - Conveying Systems

1. This item will address the accessibility improvements to both the exterior and interior of the Old Courthouse, specifically the installation of the elevator and associated elements.

Work includes the structural foundations and basement work associated with the elevator

Demolition associated with both universal access and conveying systems will be included in this item.

2. Measurement for payment will be percentage complete of line item per scheduled value.

3. Payment shall be made at the contract lump sum price

Base Bid – Contract Line Item No. 0002 – Universal Access Improvements

1. This item will address the accessibility improvements to both the exterior and interior of the Old Courthouse. Work will include removal of the mechanical wheelchair lift and replacing it with two ramp structures at both the East and West main entrances, universal access to exhibit galleries, court rooms, and the Park’s library and other accessibility improvements as noted in the Contract Documents.

Work includes all landscaping and site preparation required for these accessibility improvements at the exterior

Work includes accessibility to the restrooms and related plumbing fixtures, interior partitions, interior finishes and furnishings

2. Measurement for payment will be percentage complete of line item per scheduled value.

PMIS/PKG NO. 242900/253127 01 27 00 - 2

3. Payment shall be made at the contract lump sum price

Base Bid – Contract Line Item No. 0003 – Interior Signage & Wayfinding

1. This item will address the procurement/fabrication and installation of the interior signage and wayfinding in the Old Courthouse. Work is referenced in the Construction Documents and in Appendix G: Kuhlmann Leavitt, Inc. Final Construction Document Package (including Location Plans and Signage List).

2. Measurement for payment will be percentage complete of line item per scheduled value.

3. Payment shall be made at the contract lump sum price

Reduce Deferred Maintenance on Old Courthouse (PMIS 253127 Park Centennial)

Base Bid – Contract Line Item No. 0004 – Fire Suppression System

1. This item includes work to upgrade the Fire Suppression/Monitoring/Detection systems;

related Electrical wiring/routing/fixtures associated with Fire Suppression System; related Plumbing systems and components associated with Fire Suppression systems; associated Hazardous Material Abatement and related site preparation work.

Plumbing excludes accessories and components associated with restrooms/kitchenettes improvements for accessibility (refer to Contract Line Item 0002).

Fire Suppression includes installation of water tank and fire pumps for suppression system.

2. Measurement for payment will be percentage complete of line item per scheduled value.

3. Payment shall be made at the contract lump sum price.

Base Bid – Contract Line Item No. 0005 - Hazardous Material Abatement

1. This item consists of all the hazardous material abatement and remediation – lead paint, asbestos and unforeseen conditions, not specifically called out in other Contract Price Schedules associated work items. Scope of work includes the Asbestos, Lead and HHW Removal Work Plan and Report of Findings by Professional Environmental Engineers, Inc. (Appendix H).

Work includes conducting the Clearance Air Sampling and Analysis by a 3rd party environmental consultant, hired by the contractor.

2. Measurement for payment will be percentage complete of line item per scheduled value.

3. Payment shall be made at the contract lump sum price.

Rehabilitate Critical Systems and Safety Features at Historic Old Courthouse (PMIS 242900

LIC)

Base Bid – Contract Line Item No. 0006 - Replace Critical Systems

1. This item consists of upgrades to the existing building systems to address life safety deficiencies. The systems include Plumbing (domestic and sanitary), Electrical Service and Distribution (including minor hazardous components abatement) along with associated site utilities work with the installation of the Ameren Vault, HVAC with all

PMIS/PKG NO. 242900/253127 01 27 00 - 3

the heating/cooling/environmental management controls and distribution components and the Testing/Balance/Commissioning. All interior finishes and construction related to the above systems are included in this item.

General Conditions – site demolition, preparation, protection, and development including landscaping and pedestrian paving.

Work also includes the removal of old radiators installed in 1920.

Work also includes replacement of all the windows related to the air infiltration and work associated with the upgraded HVAC system (identified as BASE in the Bid Phase of the Window Schedule). Provide costs for full replacement, repair and restoration as noted in the Contract Documents. The work includes preparation, grills, birdwire, and interior finishes associated with these windows. This work excludes the Contract Line Item 0008.

2. Measurement for payment will be percentage complete of line item per scheduled value.

3. Payment shall be made at the contract lump sum price.

Bid Option 1 – Contract Line Item No. 0008 – Replace Additional Windows

1. This item consists of replacing the remaining windows in the Old Courthouse, outside of Base Bid Contract Line Item 0005 (identified as C.O.1 in the Bid Phase of the Window Schedule). Provide costs for full replacement, repair and restoration as noted in the Contract Documents. The work includes preparation, grills, birdwire, and interior finishes associated with these windows.

2. Measurement for payment will be percentage complete of line item per scheduled value.

3. Payment will be made at the contract lump sum price.

Rehabilitate Critical Systems and Safety Features and Historic Old Courthouse (PMIS 242900

FLREA)

Base Bid – Contract Line Item No. 0007- Acquire the Ameren Duct Bank.

1. This item consists of the materials, labor and fabrication for the Ameren Duct Bank. The Ameren Vault is associated with the HVAC scope in Contract Line Item 0006 (HVAC scope).

2. Measurement for payment will be percentage complete of line item per scheduled value.

3. Payment will be made at the contract lump sum price.

END OF SECTION 01 27 00

PMIS/PKG NO. 242900/253127 01 32 18 - 1

051121 CONSTRUCTION SCHEDULE

SECTION 013216 – CONSTRUCTION SCHEDULE

PART 1 - GENERAL

1.1 SUMMARY

A. This Section consists of Construction Schedule requirements including but not limited to the following:

1. Schedule of Values

2. Construction Schedule Requirements.

3. Construction Schedule Updates.

4. Time Impact Analysis.

B. Purpose: The purpose of the Construction Schedule is to ensure adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. The Construction Schedule will assist the Contractor and Contracting Officer in monitoring the progress of the work, evaluating proposed changes, and processing the Contractor's monthly progress payment.

1.2 DEFINITIONS

A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.

1. Critical activities are activities on the critical path. They must start and finish on the planned early start and finish times.

2. Predecessor Activity: An activity that precedes another activity in the network.

3. Successor Activity: An activity that follows another activity in the network.

B. Cost Loading: The allocation of the Schedule of Values for the completion of an activity as scheduled. The sum of costs for all activities must equal the total Contract Sum, unless otherwise approved by the Contracting Officer.

C. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.

D. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.

E. Float: The measure of leeway in starting and completing an activity.

1. Float: Float is not for the exclusive use or benefit of either the Government or the Contractor but is jointly owned.

2. Free float is the amount of time an activity can be delayed without adversely affecting the early start of the successor activity.

PMIS/PKG NO. 242900/253127 01 32 18 - 2

3. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.

F. Resource Loading: The allocation of manpower and equipment necessary for the completion of an activity as scheduled.

G. Fragnet: A partial or fragmentary network that breaks down activities into smaller activities for greater detail.

1.3 SUBMITTALS

A. Electronic Copies: All schedules and reports submitted shall be posted on the NPS DSC SharePoint project website, provided in the native electronic file format. It is the intent of the Government to limit the number of printed reports to only those reports determined by the project team to be essential.

B. Schedule of Values: After contract award and before the Pre-Construction conference submit a schedule of dollar values based on the Contract Price Schedule.

C. Construction Baseline Schedule: After contract award and before the Pre-Construction conference, submit two paper copies of baseline schedule, large enough to show entire schedule for entire construction period.

D. CPM Reports: Concurrent with CPM schedule, submit three paper copies of each of the following computer-generated reports. Format for each activity in reports shall contain activity number, activity description, resource loading, original duration, remaining duration, early start date, early finish date, late start date, late finish date, and total float in calendar days.

1. Activity Report: List of all activities sorted by activity number and then early start date, or actual start date if known.

2. Logic Report: List of predecessor and successor tasks for all activities, sorted in ascending order by activity number and then early start date, or actual start date if known.

3. Total Float Report: List of all activities sorted in ascending order of total float.

E. Construction Schedule Updates: On or before the 7th day preceding the progress payment request date, submit estimates of the percent completion of each schedule activity and necessary supporting data. Provide two paper copies.

F. Construction Schedule Revisions and Time Impact Analysis: For each Construction Schedule revision submit two paper copies of a Time Impact Analysis. Each Time Impact Analysis shall include a Fragmentary Network (Fragnet), incorporated into the currently accepted Construction Schedule, demonstrating how the Contractor proposes to incorporate a modification, change, delay, or Contractor request.

1.4 QUALITY ASSURANCE

A. The Contractor shall meet with the Contracting Officer on the day of the preconstruction conference to go over the following:

PMIS/PKG NO. 242900/253127 01 32 18 - 3

1. Review software limitations, content and format for reports.

2. Verify availability of qualified personnel needed to develop and update schedule.

3. Discuss constraints, including phasing, work stages, area separations, interim milestones and partial Government occupancy.

4. Review delivery dates for Government-furnished products.

5. Review schedule for work of separate Government contracts.

6. Review time required for review of submittals and re-submittals.

7. Review requirements for tests and inspections by independent testing and inspecting agencies.

8. Review time required for completion and startup procedures.

9. Review time required for obtaining and activating permits.

10. Review and finalize list of construction activities to be included in schedule.

11. Review baseline schedule comments, resolve issues and progress on incorporating them

12. Review procedures for updating schedule.

13. Discuss reporting requirements and establish a protocol for naming and transmitting electronic schedules.

B. Contractor's Schedule Representative: Before or at the preconstruction conference, designate an authorized representative to be responsible for the preparation and maintenance of the Construction Schedule. A resume outlining the qualifications of the Scheduler shall be submitted to the Contracting Officer for acceptance. The Scheduler shall have prepared and maintained at least 5 previous schedules of similar size and complexity similar to this Contract, demonstrating proficiency in the use of scheduling software. The authorized representative will be responsible for preparing the Baseline Schedule, all required updates, revisions, Time Impact Analyses, and preparation of reports.

1.5 COORDINATION

A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate Contractors.

B. Coordinate Construction Baseline Schedule with the Schedule of Values, list of subcontracts, Submittals Schedule, progress reports, payment requests, and other required schedules and reports.

1. In developing the Construction Baseline Schedule, ensure that the Subcontractor’s work at all tiers, as well as the prime Contractor’s work, is included and coordinated.

2. Secure time commitments for performing critical elements of the Work from parties involved.

3. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.

PMIS/PKG NO. 242900/253127 01 32 18 - 4

PART 2 - PRODUCTS

2.1 SCHEDULE OF VALUES

A. Breakdown each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule submitted under this specification. The total costs for the component work activities shall equal the contract price for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. Include mobilization, general condition costs, overhead and profit in the total dollar value of unit price items and in the component work activities for each lump-sum item. Do not include mobilization, general condition costs, overhead or profit as a separate item.

B. Do not break down unit price items. Use only the contract price for unit price items.

C. The total cost of all items shall equal the contract price. The Schedule of Values will form the basis for progress payments.

D. An acceptable Schedule of Values shall be agreed upon by the Contractor and Contracting Officer before the first progress payment is processed.

2.2 CONSTRUCTION SCHEDULE REQUIREMENTS

A. Construction Baseline Schedule: Prepare Construction Baseline Schedule using a computerized, cost and resource-loaded, time-scaled CPM network analysis diagram for the Work.

1. Develop and finalize Construction Baseline Schedule so it can be accepted for use no later than 30 days after date established for the Notice of Award.

a. Failure to include any work item required for performance of this Contract shall not excuse Contractor from completing all work within applicable completion dates, regardless of Governments acceptance of the schedule.

2. Establish procedures for monitoring and updating Construction Baseline Schedule and for reporting progress. Coordinate procedures with progress meeting and payment request dates.

B. Construction Baseline Schedule Preparation: Prepare a list of all activities required to complete the Work. Using the preliminary CPM network diagram, prepare a skeleton network to identify probable critical paths.

1. Activities: Indicate the estimated duration, sequence requirements, and relationship of each activity in relation to other activities.

2. Critical Path Activities: Identify critical path activities, including those for interim completion dates. Scheduled start and completion dates shall be consistent with Contract milestone dates.

3. Processing: Process data to produce output data on a computer-drawn, time-scaled network. Revise data, reorganize activity sequences, and reproduce as often as necessary to produce the CPM schedule within the limitations of the Contract Time.

PMIS/PKG NO. 242900/253127 01 32 18 - 5

4. The Construction Baseline Schedule as developed shall show the sequence and interdependence of activities required for complete performance of the work. Ensure all work sequences are logical and the Construction Baseline Schedule shows a coordinated plan of the work.

5. Resource loading of each activity shall include all personnel by labor category and equipment type and capacity proposed to complete the activity in the duration shown.

6. Consider seasonal weather conditions in planning and scheduling all work influenced by high and low ambient temperatures, wind, or precipitation to ensure completion of all work within the contract time.

7. Time Frame: Proposed duration assigned to each activity shall be the Contractor's best estimate of time required to complete the activity considering the scope and resources planned for the activity.

a. An early finish date may be shown but the late finish date must be the same date as the last day of the contract period. An early completion schedule must contain the following:

1) Insert an activity titled “Project Float” as a successor to the last activity in the early project completion schedule network.

2) Add a milestone titled “Contract End Date” as a successor to the activity “Project Float”.

3) Add duration to the activity “Project Float” as required so the milestone “Contract End Date” equals the last day of the Contract Period.

b. Contract completion date shall not be changed by submission of a schedule that shows an early completion date.

c. The Contractor shall limit use of lead or lag durations between schedule activities.

d. Project Calendars: Develop and incorporate the following calendars:

1) Administrative Calendar: Include a calendar that is based on a 7 day week to be used on any activities that are based on calendar days. Apply this calendar to administrative tasks or any other tasks that are not affected by non-working days (Federal Holidays, weather, etc.).

2) Project Calendar: Include a calendar that is based on the planned work week for the project. Include Federal Holidays, weekends, and any other non-work days indicated in the contract documents. Apply this calendar to activities which are not anticipated to be affected by weather.

3) Weather Calendar: Utilize the Project Calendar and show anticipated normal downtime related to weather as non-working time. Weather days shall be based on data for the local area from a reliable source like the National Oceanic and Atmospheric Administration (NOAA), National Park Service records, or source acceptable to the Contracting Officer. Apply this calendar to activities that are anticipated to be affected by weather.

e. Activity Duration: Define activities so no activity is longer than 15 days, except for non-construction activities…

This is the start of the file's text. The full file is on GovTribe.