This document contains questions and answers related to Amendment 3 of Solicitation 140P2022R0159 for the Old Courthouse Phase 2 Renovations project at Gateway Arch National Park in St. Louis, Missouri. The National Park Service is seeking to renovate the Old Courthouse to install an elevator, improve accessibility, upgrade restrooms, reinforce floors, replace windows, and remove asbestos and lead-based materials. A notice of award is expected on October 21, 2022 with an estimated notice to proceed of January 16, 2023 and an 18-month period of performance. The solicitation requires a minimum of 20% work to be performed by small businesses and has a goal of 44% small business participation. Offerors should submit experience on relevant projects and past performance questionnaires for evaluation.

View the file

Other files

File Type Posted
Sol_140P2022R0159_Amd_09.pdf PDF
Amendment_09_Questions_and_Answers_9-9-22_09.docx DOCX document
Amendment_09_SF_30_9-9-22_09.pdf PDF
Amendment_08_Questions_and_Answers_9-8-22_08.docx DOCX document
Amendment_08_STL_OCH_Ramp_Project_Irrigation_As_Built__08.pdf PDF
Sol_140P2022R0159_Amd_08.pdf PDF
Amendment_08_Ground_Penetrating_Radar_08.docx DOCX document
Amendment_08_SF_30_9-8-22_08.pdf PDF
Amendment_07_SF_30_9-2-22_07.pdf PDF
Amendment_07_Questions_and_Answers_9-2-22_07.docx DOCX document
Sol_140P2022R0159_Amd_07.pdf PDF
Amendment_06_Questions_and_Answers_8-26-22_06.docx DOCX document
Sol_140P2022R0159_Amd_06.pdf PDF
Amendment_06_Wage_Determination_MO20220051_7-29-22_06.pdf PDF
Amendment_06_AS_BUILTS__JEFF_007895__Unistrut_Catwalk_06.pdf PDF
Amendment_06_SF_30_8-26-22_06.pdf PDF
Amendment_05_SF_30_8-25-22_05.pdf PDF
Amendment_05_08_16_22_OCH_CONTRACTOR_SIGN_IN_05.pdf PDF
Amendment_05_08_24_22_Contractor_Walk_Thru_at_the_OCH_05.pdf PDF
Sol_140P2022R0159_Amd_05.pdf PDF
Amendment_05_Questions_and_Answers_8-25-22_05.docx DOCX document
Amendment_05_08_18_22_OCH_CONTRACTOR_SIGN_IN_05.pdf PDF
Sol_140P2022R0159_Amd_04.pdf PDF
Amendment_04_Questions_and_Answers_8-19-22_04.docx DOCX document
Amendment_04_SF_30_8-19-22_04.pdf PDF
Amendment_03_Project_Experience_Form_03.docx DOCX document
Amendment_03_Old_Courthouse_Preservation_Plan_Matrix_2022_08_03_03.pdf PDF
Amendment_03_Past_Performance_Questionaire_03.docx DOCX document
Sol_140P2022R0159_Amd_03.pdf PDF
Amendment_03_SF_30_8-12-22_03.pdf PDF
Amendment_02__Sign_In_Sheet_140P2022R0159_GANP_242900___2537127_02.pdf PDF
Amendment_02_SF_30_8-9-22_02.pdf PDF
Amendment_02_Questions_and_Answers_8-9-22_02.docx DOCX document
Sol_140P2022R0159_Amd_02.pdf PDF
Amendment_02_PreBid_Conference_Presentation_7-29-22_02.pptx PPTX presentation
Amendment_02_TripReport_Schilling_and_Devore_11_20_final_02.pdf PDF
Amendment_01_SF_30_7-29-22_01.pdf PDF
Amendment_01_Questions_and_Answers_7-29-22_01.docx DOCX document
Sol_140P2022R0159_Amd_01.pdf PDF
B08_Attachment_1d_Project_Manual_VOL_4.pdf PDF
B08_Attachment_2_Drawings.pdf PDF
B08_Attachment_3a_DOI_Memo_Implementation_of_Cert.pdf PDF
B08_Attachment_1c_Project_Manual_VOL_3.pdf PDF
B08_Attachment_5_Proposal_Submission_Package_Portfolio_7-25-22.pdf PDF
B08_Attachment_4_Wage_Determination_5-27-2022.pdf PDF
B08_GANP_242900_Sol_140P2022R0159_SF1442_and_Clauses_7-25-22.pdf PDF
Sol_140P2022R0159.pdf PDF
B08_Attachment_3b_DOI_Memo_Certification_of_Vaccination_Form.pdf PDF
B08_Attachment_1a_Project_Manual_VOL_1.pdf PDF
B08_Attachment_1b_Project_Manual_VOL_2.pdf PDF
Show all 50

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Old Courthouse Phase 2 Renovations, Gateway Arch National Park (GANP 242900/253127) (Formerly Jefferson National Expansion Memorial (JEFF 199879)), St. Louis, Missouri

Solicitation 140P2022R0159 – Questions and Answers

Amendment 1, issued 7/29/22:

1. Contracting Officer’s Note 1: The language issued in “Section C – Specification / Drawings”, page 9 of 55 is incorrect. The correct language is as follows:

The Work includes installation of a new interior elevator, accessibility improvements, family restrooms, floor ramps, interior wayfinding signage, replacement of existing steam radiator system with new 4-pipe mechanical system, new fire-sprinkler system with detectors and alarms, upgrades to lighting, power, security and IT infrastructure, structural floor reinforcement, and replacement of window sashes and repair/refurbishment of window frames. Work also includes removal and disposal of asbestos containing materials, lead-based paint and household hazardous waste items as noted in a Work Plan included in the Appendices of the Construction Documents.

2. Contracting Officer’s Note 2: Please add the following requirement to Division 1 Specification Section 01 50 00 Temporary Facilities and Controls Part 4.3 Support Facilities Installation D. Project Identification and Temporary Signs:

Provide access to NPS for the installation of Artistic banners/signage on the temporary construction chain-link fencing for the duration of this project. Signage material will be suitable for use on temporary construction fencing. Exact locations and size of signage is to be determined; assume installations along all four perimeter streets. Installation and maintenance of these artworks will be the responsibility of NPS in consultation and/or under guidance of the artist.

Amendment 2, issued 8/9/22:

3. Contracting Officer’s Note:

Section 28 31 00 – Fire Alarm and Detection Systems, Part 2 – Products, 2.1 Acceptable Manufacturers is revised. The only acceptable manufacturer is option A, “Johnson Controls – Simplex 4100 ES”. This is necessary to be compatible with the existing Simplex 4100 ES system and with the new Security Command Center Fire alarm Network via the existing fiber backbone.

Amendment 3, issued 8/12/22:

4. Question: Does the steam pipe in the tunnels need to be abated for ACMs?

Answer: No. All steam pipe going to the tunnels will be abated and pipe removed. Once it goes into the tunnel, the steam pipe will be abandoned in place as well as the ACM covering. Exposed ends of the ACM covering at the tunnels should be sealed to prevent any ACM release into atmosphere.

5. Question: I am inquiring to request a copy of the 8/2/22 Pre-Bid Meeting & 8/4/22 Site Visit Sign In Sheets for the JEFF 199879 - Old Courthouse Phase 2 Renovations, Gateway Arch National Park, Jefferson National Expansion project.

Answer: See Amendment 2

6. Question: At the 1pm site visit last week, it was stated that an additional site visit can be scheduled in which all of the access points will be opened to the various catwalks. Will NPS schedule this additional site visit similar to the original site visit or do we need to schedule it per individual contractor?

Answer: The additional site visits will be held on August 16/Tuesday at 9am AND August 18/Thursday at 9am on the west entrance steps, N Broadway.

7. Question: Solicitation Page 15, Section H – Special Contract Requirements (Requirement 3) indicates a Quality Manager as part of the Key Personnel. Please confirm whether the Quality Manager can perform other duties on the project. In addition, is the safety manager required to be onsite full time?

Answer: Quality Control Manager CANNOT be the site superintendent. Quality Control Manager can perform other duties on site and is full time.

8. Question: Solicitation Page 15, Section H – Special Contract Requirements (Requirement 3) indicates a Safety Manager as part of the Key Personnel. Please confirm whether the Safety Manager can perform other duties on the project. In addition, is the safety manager required to be onsite full time?

Answer: Safety Manager can perform other duties on site and is full time.

9. Question: Solicitation Page 48-49, Factor 2, Subfactor 2A, Element 3 requires an organization chart. The associated written narrative (entirety of Factor 2) is limited to 3 pages. Please confirm that the organization chart is not part of the 3-page limit.

Answer: The Organization Chart is not part of the 3 page count.

10. Question: Solicitation Page 48-49, Factor 2, Subfactor 2A, Element 3 – can the org chart be an 11x17 sheet?

Answer: The org chart can be an 11x17 sheet.

11. Question: Solicitation Page 49, Factor 3, Subfactor 3A will utilize the Project Experience Questionnaire form provided as an Attachment to the RFP. The form provided with the RFP is a static PDF, though it appears this is supposed to be a fillable/editable form. Can a live/editable version be provided for use on this project? Or are we to recreate the form?

Answer: The pdf can be edited through Adobe Pro, however, a Word document version of the Project Experience Form is included in Amendment 03.

12. Question: Factor 3, Subfactor 3A - Project Experience Questionnaire form allows for expanding the response sections to adequately address each question (to multiple pages if needed). Once expanded for responses, is there a page limit for each form?

Answer: There is no page limit.

13. Question: Factor 3, Subfactor 3A requires us to “describe the experience and capability of key trades identified in Section H…”. No key trades were identified, only key personnel. Please clarify the requirement of this portion of Subfactor 3A.

Answer: There are no Key Trades identified for this project.

14. Question: Factor 4 - The Past Performance Questionnaire form provided as an attachment to the RFP is a static PDF, though it appears this is supposed to be a fillable/editable form. Can a live/editable version of the PPQ be provided for use on this project (since this will be transmitted directly from our references to the Contracting Officer)? Or are we to recreate the form?

Answer: The pdf can be edited through Adobe Pro, however, a Word document version of the Past Performance Questionnaire Form is included in Amendment 03.

15. Question: Please provide the “Hazardous Material Identification Listing” form that is referenced on page 50 of the Solicitation and is required to be submitted as part of the technical proposal. The form was not provided as part of the RFP. Note, this form is also listed on the cover page of Attachment 5.

Answer: The Hazardous Material Identification Listing Form is no longer required.

16. Question: Solicitation page 16, Special Requirement 4: Small Business Participation indicates a minimum of 20% of the total contract value is to be performed by Small Business. Page 51 of the solicitation lists a small business goal of 44% for Small Businesses. Likewise, the Small Business Subcontracting plan template provided as an attachment to the RFP lists a goal of 44%. Please clarify the small business requirements – is 20% a required minimum with 44% the goal?

Answer: 20% is the requirement, 44% is the goal.

17. Question: Report on Limitations on Subcontracting. The cover page included in Attachment 5 of the RFP indicates that this is a required submittal. Please confirm that this is not required as the project is not a sole source or set-aside solicitation.

Answer: Report on Limitations on Subcontracting is not required, as this solicitation is Full and Open.

18. Question: RFP attachment 5 – Cover page – is there a specific form to address “Proposed Equals”? If so, please provide. Note, this form is also referenced on page 50 of the solicitation.

Answer: The Proposed Equals form is no longer required during solicitation. This will be addressed by a submittal after award.

19. Question: Most Appendices, including “Appendix G – Signage and Wayfinding”, as mentioned in the Table of Contents of the Construction Documents on page 200116-6 appear to be unissued. Will these documents be forthcoming?

Answer: Signage and Wayfinding Plans are included as Appendix G.

20. Question: Specification section 01 91 13 – Commissioning Requirements – will the Government be providing the services of the Commissioning Agent (CxA) directly? Or are these costs to be included by the Offeror?

Answer: Cost of Commissioning Agent being provided by Partner and no costs are to be included by offeror.

21. Question: Regarding schedule – there are conflicting schedules within the solicitation - please verify which of the below schedule timelines is correct: a. Solicitation pages 10 and 48 indicate a Notice to Proceed by January 16, 2023, with completion required no later than 18 months after Notice to Proceed, or July 26, 2024. Page 48 indicates a Notice of Award on October 21, 2022. b. Solicitation page 3 indicates a period of performance from 10/21/2022 to 04/21/2024. This was also indicated at the pre-proposal conference and suggests a Notice to Proceed of 10/21/2024.

Answer: The Notice to Proceed and Notice of Award are separate events. The period of performance will be adjusted once the Notice to Proceed is issued and will extend to 18 months from the Notice to Proceed. Typically, the Notice to Proceed is issued 1 to 2 months after the Notice of Award. It is the Government's intention to award this contract by October 21, 2022. Given this date, it is the Government's estimate that the Notice to Proceed will be issued on January 16, 2023.

22. Question: Solicitation page 25-26, FAR 52.236-4 – the documents listed in this section were not issued as part of this RFP (though they were issued in the previously cancelled solicitation). Will these documents be reissued as part of this RFP? Specifically:

a. Historic Structure Report – July 2013

b. Historic Preservation Plan – Nov 2021

c. HazMat Reports (4)

d. Ceiling Table Mar 2020

e. Draft Report of Asbestos Findings MAR 2014

f. Environmental Work Plan JUL 2019

g. Report of Findings Asbestos Lead Paint HHW APR 2014

h. Archeology Reports (3)

i. Noble Aug 2007

j. Schilling Jul 2014

k. Trip Report from Schilling & Barnett Jan 2014 (End of clause)

Answer: Refer to the Table of Contents in Volume 1 of the Project Manual as some of the mentioned documents are included in the Appendices. And reference all the amendments. Refer to this solicitation only for the documents needed for this project.

23. Question: I am reaching out to request additional access/walk-through of the Old Courthouse. We would like to set something up on Tuesday, August 16 at the earliest time available. We would specifically like to see the basement as well as the floors above the 2nd floor.

Answer: The additional site visits will be held on August 16/Tuesday at 9am AND August 18/Thursday at 9am on the west entrance steps, N Broadway.

24. Question: On A-505, elevation 8 shows that there are two accessories on the back of the door that are called out as a changing table(11). I believe these are meant to be coat hooks(12). Please verify.

Answer: Yes, elevation 8 on A-505, the note 11 should read 12 for coat hook (similar to elevation 4).

25. Question: What is the correct flooring in Breakroom 215C? Sheet A-905 shows LVT-1 and CPT-2. If both are to be installed, please provide extents.

26. Question: Please clarify required blocking in Rooms 215C, D & E? Do both sides of the wall need blocking? A-205 and A-502 have conflicting information.

Answer: Provide blocking full north-south length on east face of west wall in Room 215D. Blocking not required in 215B, 215C or 215E.

27. Question: Please confirm CPT-3 and WB-2 as the proposed flooring/trim finishes for the Elevator Machine Room 209A.

Answer: As referenced in the schedule sheet, A-906, the flooring is CPT-3 with WB-2 as the base.

28. Question: Please confirm if all windows on Sheet A-801 noted as “BASE” and “C.O. 1” are to have complete sash replacement per Bid Phase Notes. If this is incorrect, is there any way to decipher between the different processes for repair/restoration noted below from spec 080352 for each window.

a. Wood Window Patch-Type Repair

b. Wood Window Member-Replacement Repair

c. Wood Window Unit Replacement

Answer: Wood patching and/or replacement of existing window members is not related to Sheet A-801. Each individual BASE or C.O. 1 window shall be evaluated and repaired per specified methods. Specified wood window unit replacement method shall be followed at all sash replacements.

29. Question: A bidder has commented on the use of laminated glass and the putty glazing method. They noted that the oils in the putty conflict/breakdown the lamination of the glass. Please provide any clarification on this process or information regarding an approved alternative method.

Answer: We are unaware of stated issues using specified glazing compound (See 080352 2.6.B.1). Historic appearance requires use of glazing putty - Other products can be considered if submitted under 012223 2.3.E Approved Equals

30. Contracting Officer’s Note: Government solicitations are officially issued on sam.gov. There is not a “Plan Holder’s List” on this site. To find contractors who are interested in this project you can look at the Site Visit Sign-in sheets published in Amendment 2. However, there may be third party redistributers of the solicitation documents published from sam.gov that could have a Plan Holder’s List. Please inquire with them.