01_27_00_DEFINITION_OF_CONTRACT_LINE_ITEMS_ADDEN3_0003.pdf

PDF 467 KB Posted

Attached to
GOGA 212511D Repair West Wing of Fort Mason, Build
Solicitation number
140P2022R0072
Issued by

About this file

This document defines contract line items for seismic strengthening work on the West Wing of Fort Mason Building 201. The project includes seismically strengthening structural elements, hazardous materials abatement, relocating server rooms, tenant improvements, minor seismic upgrades, architectural casework, exterior painting, and historic window rehabilitation or replacement. The work is divided into eleven contract line items covering the base bid and eight options. Payment will be made on a lump sum basis for most line items and on a unit price per cubic yard basis for hazardous soil disposal. The related federal contract opportunity is solicitation number 140P2022R0072 issued by the National Park Service for seismic repair of the West Wing at the Golden Gate National Recreation Area.

View the file

Other files

File Type Posted
B09_Wage_Determination_SF_1_19_23_0010.pdf PDF
Sol_140P2022R0072_Amd_0010.pdf PDF
B09_Wage_Determination_Updated_11_4_22_0009.txt TXT text file
AS-CONST_GOGA_Ft_Mason_Bldg_201_Elect_Rehab_0009.pdf PDF
B09_Amd_9_Schedule_of_Changes_Q_A_0009.pdf PDF
Sol_140P2022R0072_Amd_0009.pdf PDF
B09_Amd_8_Schedule_of_Changes_Q_A_Respones_0008.pdf PDF
Sol_140P2022R0072_Amd_0008.pdf PDF
Sol_140P2022R0072_Amd_0007.pdf PDF
B09_Amd_7_Schedule_of_Changes_Q_A_0007.pdf PDF
GOGA_212511D_Virtual_Project_Overview-20221014_100154-Meeting_Recording_0006.mp4 MP4 file
Sol_140P2022R0072_Amd_0006.pdf PDF
Image_0006.jpeg JPEG file
Sol_140P2022R0072_Amd_0005.pdf PDF
14_October_MS_Teams_Invite_0005.pdf PDF
140P2022R0072_Virtual_Project_Review_Presentation_0004.pptx PPTX presentation
Sol_140P2022R0072_Amd_0004.pdf PDF
09_29_00_Gypsum_Board_ADDEND3_0003.pdf PDF
01_33_23a_SubmittalList-ReviewEstimate_rev_0003.xlsx XLSX spreadsheet
Sol_140P2022R0072_Amd_0003.pdf PDF
03_31_00_CAST-IN-PLACE_CONCRETE_ADDEN3_0003.pdf PDF
_22_0922_GOGA_FM201_West_FINAL_CD_combined_rev2_0003.pdf PDF
B09_Amd_2_Schedule_of_Changes_Q_A_0002.pdf PDF
Sol_140P2022R0072_Amd_0002.pdf PDF
IMG_7944_0001.JPG JPG image
DSCN0951_0001.JPG JPG image
IMG_7798_0001.JPG JPG image
IMG_7945_0001.JPG JPG image
IMG_7801_0001.JPG JPG image
DSCN0622_0001.JPG JPG image
DSCN0903_0001.JPG JPG image
DSCN0914_0001.JPG JPG image
IMG_7950_0001.JPG JPG image
DSCN0952_0001.JPG JPG image
DSCN0895_0001.JPG JPG image
IMG_7803_0001.JPG JPG image
DSCN1048_0001.JPG JPG image
IMG_7739_0001.JPG JPG image
DSCN0944_0001.JPG JPG image
IMG_7937_0001.JPG JPG image
DSCN0611_0001.JPG JPG image
IMG_7746_0001.JPG JPG image
IMG_7768_0001.JPG JPG image
IMG_7938_0001.JPG JPG image
DSCN0915_0001.JPG JPG image
DSCN1053_0001.JPG JPG image
DSCN0919_0001.JPG JPG image
DSCN0938_0001.JPG JPG image
DSCN0912_0001.JPG JPG image
B201_BASEMENT_0001.zip ZIP file
Show 40 more

Latest 50 of 195 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GOGA – 212511D 01 27 00 - 1 DEFINITION OF CONTRACT LINE

ITEMS

SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS

PART 1 - GENERAL

A

1.1 SUMMARY

A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.

B. If no contract line item exists for a portion of the work, include the costs in a related item.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 LIST OF CONTRACT LINE ITEMS

A. Base Bid – Seismic Strengthening of the West Wing and Related Work:

1. Contract Line Item 1:

2. This item consists of labor, equipment and material to seismically strengthen the East and West Wings of Fort Mason Building 201 in two phases of construction and will include:

constructing new steel moment frames and collectors on the first, second, third floors, and attic space of the three-story building; new concrete foundations and shear walls at basement level that are integral to moment frames above; strengthening roof framing at WWII Infill; providing positive connections between the wood framing and foundations of the crawlspace; connecting existing floor diaphragms, removal and reinstallation or relocating mechanical, electrical and plumbing system components related to seismic strengthening throughout the building; improvements to seismic hazards related to the mechanical, electrical and plumbing system components and removal of abandoned non-historically significant pipes, ducts, and conduits throughout; relocating and modifying portions of historic interior wood partitions with doors, glass relights, and cabinets to accommodate new moment frames; repairs and replacement of historic ceiling and wall finishes, resilient flooring, wall bases, and carpets associated with new moment frames and collectors; painting opaque interior surfaces throughout, including new structural members and trims, walls, ceilings, interior partitions, exposed electrical conduits/raceways, fire sprinkler piping, and mechanical ductwork; relocating two exterior doors and removing two windows at west wall Basement Level, providing new exterior landings, steps and handrails; removal and reconstruction of exterior wood porch and stair; mobilization, demobilization, and general conditions as related to this line item along with protection, remediation of hazardous materials, cutting, patching, repair and painting of adjacent finishes, excavation for new footings; segregating, stockpiling, testing, and disposal of Class III Non-Hazardous excavated soils, import clean fill and all other work necessary to return the system working order.

Existing construction, materials and finishes are considered historic fabric in all locations.

As a historic rehabilitation project, the goal is to disturb as little existing historic fabric as possible. Demolition must be selective to minimize the loss of historic fabric and damage

GOGA – 212511D 01 27 00 - 2 DEFINITION OF CONTRACT LINE

to historic finishes. Care must be taken when salvaging materials for reinstallation or salvage, to prevent or minimize damage to the material removed and the surrounding historic building fabric. Any disturbance to historic fabric must be approved by the contracting officer prior to removal. See specifications sections 013591 - Historic Preservation Treatment Procedures, 024105 - Selective Demolition, and 024119 - Selective Structural Demolition for detailed information and procedures.

3. Payment will be made at the contract lump sum price.

B. Base Bid - Soil Disposal Class I Cal – Hazardous Waste

1. Contract Line Item 2

2. This item consists of the labor, equipment, and material premium for abatement of soils documented as Class I Cal Hazardous waste.

3. Measurement for payment will be on a unit price per cubic yard basis based on an approved schedule of values.

4. Payment will be made at the contract unit price per cubic yard.

C. Base Bid – Relocation of Information Technologies Server Rooms 116 and 316A to Room B03

1. Contract Line Item 3

2. This item consists of the labor, equipment, and materials to relocate and consolidate Information Technologies Server Rooms, including new wire mesh partitions with locking doors and grounding, insulate ceiling/floor assembly above, painted gypsum board ceiling, rubber flooring, four 2 ½” conduits with pull-cords connecting Rooms B10 to B03, electrical power and lighting, and mechanical cooling system as Drawings indicate.

This option also includes abatement of known hazardous materials (asbestos) as described in the referenced survey report.

D. Option A – Not Used.

E. Option B – East Wing Tenant Improvements

1. Contract Line Item 5:

2. This item consists of labor, equipment, and materials for the addition of interior partitions, interior doors, and a service-counter, modifying fire suppression, mechanical, electrical, and lighting systems as required, and Drawings indicate.

3. Payment will be made on at the contract lump sum price.

F. Option C – Miscellaneous Minor East Wing Seismic Upgrade Elements

1. Contract Line Item 6:

2. This item consists of labor, equipment, and materials for the completion of structural strengthening components providing positive connections between the wood floor framing and masonry wall at second floor and removal of existing and installation of new wall, and floor finishes required to complete structural work.

3. Payment will be made on at the contract lump sum price.

G. Option D– Architectural Casework, Marble Countertops, and Fireplace Hearth and Surrounds at

GOGA – 212511D 01 27 00 - 3 DEFINITION OF CONTRACT LINE

East Wing Rooms 104, 123, and 125

1. Contract Line Item 7:

2. Provide finished painted Information Desk, and storage cabinets with book shelves, wood face-frame and raised panel doors, wood fireplace mantel, marble countertop, marble fireplace hearth and surrounds as Drawings indicate.

H. Option E – Repaint Exterior of Fort Mason Building 201 East Wing

1. Contract Line Item 8:

2. This item consists of the labor, equipment, and materials to abate exterior Lead-based Paint, and prepare surfaces to receive new paint and the application of new paint to wood siding, painted wood doors, wood and metal windows, metal downspouts, gutters, louvers, wood and metal soffits, wood steps, wood decks, wood and metal rails of the East Wing, as Drawings indicate.

I. Option F - Rehabilitate 31 Historic Window Units and Replace of 22 Window Unit Sashes on East Wing

1. Contract Line Item 9:

2. This item consists of the labor, equipment, and materials to remove, rehabilitate, and reinstall 31 historic window frames and sashes of double hung, casement, and fixed windows. Abate lead-based paint from 53 frames and 31 historic window unit sashes, prime and paint, interior wood sash and frame surfaces, prime exterior frame and sash surfaces, except sash runs. Repair decayed sash and frame elements. Replace broken glass and reglaze rehabilitated historic windows. Repair or replace operation hardware, pulleys, sash cords, or chains, and counterweights. Provide new hardware where missing or malfunctioning. Provide weather stripping and air seals and reset stops as Drawings indicate. Replace 22 existing window unit sashes with new primed and painted custom redwood sashes with true divided lites of insulated glass units configured per drawings, new sash cords. Reinstall cam locks and sash lifts.

J. Option G – Repaint Exterior of Fort Mason Building 201 West Wing

1. Contract Line Item 10:

2. This item consists of the labor, equipment, and materials to abate exterior Lead-based Paint, and prepare surfaces to receive new paint and the application of new paint to wood siding, painted wood doors, wood and metal windows, metal downspouts, gutters, louvers, wood and metal soffits, wood steps, wood decks, wood and metal rails of the West Wing, as Drawings indicate.

K. Option H - Rehabilitate 37 Historic Window Units and Repair of 123 Window Unit Sashes on West Wing

1. Contract Line Item 11:

2. This item consists of the labor, equipment, and materials to remove, rehabilitate, and

GOGA – 212511D 01 27 00 - 4 DEFINITION OF CONTRACT LINE

reinstall 37 historic window frames and sashes of double hung, casement, and fixed windows. Abate lead-based paint from 161 frames and 37 historic window unit sashes, prime and paint, interior wood sash and frame surfaces, prime exterior frame and sash surfaces, except sash runs. Repair decayed sash and frame elements. Replace broken glass and reglaze rehabilitated historic windows. Repair or replace operation hardware, pulleys, sash cords, or chains, and counter weights. Provide new hardware where missing or malfunctioning. Provide weather stripping and air seals and reset stops as Drawings indicate. Replace 124 existing window unit sashes with new primed and painted custom redwood sashes with true divided lites of insulated glass units configured per drawings, new sash cords. Reinstall cam locks and sash lifts.

END OF SECTION 01 27 00