This document provides details for a federal solicitation to rehabilitate the Hurricane Ridge Day Lodge located within Olympic National Park. The solicitation seeks to improve electrical, plumbing, and fire detection systems; replace the roof, windows, doors, and flooring; improve accessibility; and renew heating and ventilation components including an underground fuel storage tank. The project aims to resolve structural issues causing water penetration and bring the lodge into compliance with current codes. Bids are due by August 17, 2022 with award anticipated by September 2022. The solicitation is designated for small businesses under NAICS code 238210 - Electrical Contractors and Allied Services, with a set-aside type of Total Small Business. The National Park Service is the contracting agency.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140P2022R0068 x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
PDS
Denver CO 80225-0287 P.O. Box 25287 12795 W. Alameda Pkwy DOI, NPS, DSC Contracting Services
PDS
Denver CO 80225-0287 P.O. Box 25287 12795 W. Alameda Pkwy NPS, DSC Contracting Services Div
07/25/20220005
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
06/17/2022
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of Amendment 0005 is to:
1) Provide official government responses to questions, view the SF-30 continuation sheet for complete details.
All other terms and conditions remain unchanged by this Amendment 0005.
*Solicitation 140P2022R0068 - Issued 6/17/2022.
*Amendment 0001 - Issued 7/1/2022.
*Amendment 0002 - Issued 7/7/2022.
*Amendment 0003 - Issued 7/14/2022.
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Amber Hughes
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 3
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140P2022R0068/0005
*Amendment 0004 - Issued 7/20/2022.
*Amendment 0005 - Issued 7/25/2022.
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
40 There are various fuel piping elements that cannot be installed per the plans and specs.
We suggest the following additions to the scope of work by the gov’t.adding a tank sump collar. Can this be asked to the gov’t so other bidders know this as well?
a. Adding a tank sump collar, tank, and a tank manway.
b. Remote fill isolation valve. Required for filling control.
c. Flex connectors – required for the connections between types of piping.
d. Grade level manways – required to access the above sump and other shell-mounted processes such as venting and gauging.
e. Transition sump for the fill piping. This is required for the fill piping for a contained and monitored space to transition from aboveground iron piping to underground fiberglass piping.
f. Transition sump for the oil supply piping for the same reason as the fill piping – transition from aboveground iron piping to underground fiberglass piping.
The tank is used solely for heating a structure which exempts it from a lot of requirements that other types of fuel and oil tanks have to meet (both state and federal).
a. Tank and tank manway are already in the plans and specs.
b. Remote fill isolation valve is included in the remote fill box based on model number listed in the specs.
c. Included in specifications provided by Interface Engineering, but not called out on civil plans.
d. Not included in the plans or specs.
e. Not included in the plans or specs.
f. Not included in the plans or specs.
41 Keynote N22 on Sheet A4.0 identifies that the new exterior concrete wainscotting is to be “Poured in Place with a Textured Finish”.
However, details 1,6 & 7 on S1.3 identifies the wainscot as Precast. In reviewing the specifications, there did not appear to be any special mention of this building component.
Please clarify what your intent is for this element of work.
The concrete wainscot shall be cast in place board formed concrete per Spec Section 03 30 00.