Sol_140P2022R0045_Amd_0005.pdf

PDF 89 KB Posted

Attached to
ACAD-151309, Demo/Const New Maint Facility (GAOA)
Solicitation number
140P2022R0045
Issued by

About this file

This document is an amendment to a federal solicitation. It extends the proposal submission deadline from August 31st to September 14th in response to vendor questions. The solicitation is for the Acadia National Park project to demolish an existing maintenance facility and construct a new one in Hancock County, Maine. The National Park Service is the contracting agency. The amendment provides responses to vendor questions and notifications that COVID-related attestations will no longer be required for onsite contractors per updated federal guidance. It replaces certain clauses in the original solicitation and does not otherwise change any terms or conditions.

View the file

Other files

File Type Posted
140P2022R0045-0007_Att01_QuestionsAndResponses-Final_01-129_220912_0007.pdf PDF
Sol_140P2022R0045_Amd_0007.pdf PDF
140P2022R0045-0006_Att01a-Q18_SpecSection334600-Subdrainage_220805_0006.pdf PDF
140P2022R0045-0006_Att01_QuestionsAndResponses_01-129_220907_0006.pdf PDF
140P2022R0045-0006_Att01b-Q40_Revised_Drawing_C1_220805_0006.pdf PDF
Sol_140P2022R0045_Amd_0006.pdf PDF
140P2022R0045-0005_Att01b-Q60_SpecSect321443-PorousUnitPaving_220819_0005.pdf PDF
140P2022R0045-0005_Att01a-Q35_SpecSect334120-HighDensityPolyethylenePipe_220819_0005.pdf PDF
140P2022R0045-0005_Att01_QuestionsAndResponses_01-107_0005.pdf PDF
140P2022R0045-0005_Att02_RevClausesAndProvisions_220823_0005.pdf PDF
140P2022R0045-0004_Att01c-Q51_RevSpecSect334120-HighDensityPolyethylenePipe_220803_0004.pdf PDF
Sol_140P2022R0045_Amd_0004.pdf PDF
140P2022R0045-0004_Att02_DVB_GD_No_MA08_Maine-Building_220805_0004.pdf PDF
140P2022R0045-0004_Att01a-Q36_RevSpecSect323223_01-MechStabilizedEarthWall_220803_0004.pdf PDF
140P2022R0045-0004_Att01_QuestionsAndResponses_01-65_0004.pdf PDF
140P2022R0045-0004_Att01b-Q50_BollardDwg_220726_0004.pdf PDF
140P2022R0045-0003_Att01c-Q16_CarmonProductCutsheets_170620_0003.pdf PDF
140P2022R0045-0003_Att01b-Q09_SpecSect028214-AsbestosAbatement_Rev220725_0003.pdf PDF
140P2022R0045-0003_Att01a-Q03_ACAD151309B_GeotechnicalFinalDesignReport_211201_0003.pdf PDF
Sol_140P2022R0045_Amd_0003.pdf PDF
140P2022R0045-0003_Att01-QuestionsAndResponses_01-51_220727_0003.pdf PDF
140P2022R0045-0002_Att01b-PreProposal_Mtg_SignIn_Sheets_220713_0002.pdf PDF
Sol_140P2022R0045_Amd_0002.pdf PDF
140P2022R0045-0002_Att01a-PreProposal_Mtg_Presentation_w-Notes_220713_0002.pdf PDF
Sol_140P2022R0045_Amd_0001.pdf PDF
140P2022R0045-0001_Att01_Revised_SF1442_220707_0001.pdf PDF
140P2022R0045_Att01b-100pctSpecifications-Vol2of2_220325.pdf PDF
140P2022R0045_Att02-100pctDrawings_220325.pdf PDF
140P2022R0045_Att04a-ProposalSubmissionPackage_220707.zip ZIP file
140P2022R0045_Att01a-100pctSpecifications-Vol1of2_220325.pdf PDF
Sol_140P2022R0045.pdf PDF
140P2022R0045_Att05-Vaccination-Certification-Notification_210824.pdf PDF
140P2022R0045_Att04b-ProposalSubmissionPackage-Sample_220707.pdf PDF
140P2022R0045_Att07-SubKPlanForm_220519.docx DOCX document
140P2022R0045_Att06-Certification-of-Vaccination-Form_Exp250228.pdf PDF
140P2022R0045_Att08-Closeout-OM_List_220413.pdf PDF
140P2022R0045_Att03-DVB_GD_No_MA08_Maine-Building_220401.pdf PDF
Show all 37

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

140P2022R0045 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

PDS

Denver CO 80225-0287 P.O. Box 25287 12795 W. Alameda Pkwy NPS, DSC Contracting Services Div

08/23/20220005

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

07/07/2022

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Acadia National Park

Demolish and Construct New Maintenance Facility (GAOA Project) (ACAD 151309)

Hancock County, Maine

Amendment 0005 extends the proposal submission deadline to 4:00 pm Eastern Daylight Time, Wednesday, September 14, 2022. As a result of this Amendment 0005, the deadline for submitting questions is extended to 4:00 pm Eastern Daylight Time, Wednesday, September 7, 2022.

Amendment 0005 provides responses to vendor questions to date. See Attachment 01 (Questions and Answers) and supporting attachments 01a (Question 35_Specifications Section 334120 -

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Jeffery Hepp

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 2

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

140P2022R0045/0005

High Density Polyethylene Pipe, which was inadvertently listed in Amendment 0004 as a response to Question 51) and 01b (Question

60_Specifications Section 321443 - Porous Unit

Paving).

Amendment 0005 provides notification that the

Safer Federal Workforce Taskforce has updated their COVID guidance in several areas, including procedures for onsite contractors. One significant change is that as of August 22, 2022, attestation will no longer be required for onsite contractors. As a result, Attachments 5 and 6 as identified in Section J of the original contract clauses and provisions are no longer required under this solicitation and the resulting contract and reference to these attachments has been removed from Special Clause 4 to Section H.

The attached revised contract clauses and provisions replace the clauses provided in the original solicitation. See Attachment 02.

All other terms and conditions are unchanged.

LIST OF CHANGES:

Bids due date : 31-AUG-22 changed to 14-SEP-22

Date distributed : 27-JUL-22 changed to 23-AUG-22