This document contains questions and responses related to a solicitation for the demolition and construction of a new maintenance facility at Acadia National Park in Bar Harbor, Maine. The solicitation is issued by the National Park Service seeking bids for the removal of existing structures and construction of a new building to house maintenance operations. Services required include demolition, site work, structural work, exterior and interior construction, mechanical, electrical and plumbing systems. Bids are to provide a lump sum price for the base project and unit prices for various optional items that may or may not be awarded. The pre-bid document includes 107 questions from contractors seeking clarification on requirements and details and the corresponding responses from the agency to ensure all parties have a shared understanding of the project scope.
View the file
Other files
Show all 37
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
140P2022R0045 Questions and Answers – Amendment #0005 08/05/2022
The following is a consolidated list of current vendor questions. Responses in red shall address questions not previously responded or to provide updates to questions in which responses had been previously provided. Please note that responses in blue (other than email or web page links) are pending responses, which will be provided in a future amendment.
1. Will all six base bid prices be awarded as one package?
Response: Yes, base bid items shall be awarded as one package. Any or all options may be awarded in the original award.
2. Section H, in the solicitation mentions the Government may pick from the separate options and contractor will need to hold the price for 180 days after award. Most material suppliers are only holding pricing for 15 days or less at this time. We assume this would not apply if all six base bids are awarded as one?
Response: Bid proposals will need to hold prices as indicated in the solicitation, price proposals will reflect the risk.
3. Have any Geotechnical investigations been performed onsite? Would it be possible to have the reports issued?
Response: Final Geotechnical Report attached. See Attachment 01a-Q03-Geotech Report to Amendment 0003.
4. We recommend an allowance be carried in the bid for utility connections at the street. Often times the utilities companies will not give contractors a solid estimated cost.
Response: We did not include costs for utility connections, because water/sewer/telcom are all connecting to existing NPS systems on the site. A new electrical service connection is being made, with a new branch from the main power line along Rte 233 to our pole, but the connection cost is included in their service contract. This was confirmed again this week with the Versant representative.
5. Please provide Utility Company point of contact who is established for the project, so we can coordinate their scope with electrical subcontractor.
Response: The Versant Power representative is Robert Peaseley (robert.peaseley@versantpower.com; office: 207-973-2518; cell: 207-299-5834). This information is provided on drawing E12.
6. Could not find appendix with Geotechnical Report prepared by WSP, thanks.
Response: Response provided in Question 3.
7. Documents indicates polished concrete. The plans and specs do not indicate required aggregate sizes and the gloss(level, diamond grit, sheen & appearance, and gloss reading) finished. A/E please advise.
Response: Polished concrete finish to be Level 3, high sheen, 800 grit. Aggregate sizes as indicated in section 033000-Cast-in-place Concrete.
8. The plans show sealed concrete, there is no spec section for sealed concrete. A/E please provide sealed concrete specs.
mailto:ROBERT.PEASELEY@VERSANTPOWER.COM
Response: There is no separate concrete sealer section. Section 033000 – Cast-in-Place Concrete includes the liquid floor treatment, which is a combined densifier/sealer.
9. Specs section 028212 Asbestos Abatement states, “The specific ACM to be abated is identified in the reports titled “Final Environmental Services Report for Cuyahoga Park” for all properties in the scope of work prepared by WSP, dated June 9, 2020, as well as Abatement Drawings, provided in the specification appendices.” Documents did not include a specification appendix and/or “Final Environmental Services Report” A/E please provide.
Response: This section (attached) has been revised to delete the incorrect references and to add a schedule of abatement scope. See Attachment 01b-Q09, Revised asbestos Abatement specification, to Amendment 0003.
10. Spec section 11 11 00 – Part 2 – Product, 2.2, L. 1 references old for the 4 post SM30 part number two RJ150BK rolling jacks has been discounted. The new part number is RJ152BK. A/E please confirm this is acceptable.
Response: The updated parts # RJ152BK for the rolling jacks will work just fine.
11. Same Spec section L 2. It references Air Line Kit FC5760-14 part number is only for 18,000lb and lower 4 post lifts with rolling jacks. Rotary does not make an airline like for the SM30 30,000lb 4 post lift. Techs bring airline to the bridge jacks as needed from the hose on the wall or from GRACO air reel. A/E please advise.
Response: NPS can/will bring an air hose to the jacks.
12. In the air piping section 22 15 13 -3 allows for aluminum piping with push to connect fittings however we use Aircom piping on all our jobs (public works and new car dealerships) which is aluminum but has socket fittings. A/E please confirm this is acceptable.
https://aluminumpipenow.com/?gclid=CjwKCAjw2rmWBhB4EiwAiJ0mtXlFgs7UjCgi6EEje85zSpcR JfrxCyA_Iuj04cU28eAjGbyyDfd78xoC8NkQAvD_BwE Response: The Aircom piping is also acceptable.
13. Documents shows air drops and no air reels. A/E please confirm that this is correct.
Response: Confirmed – no air reels are required. The scope of work is limited to air drops at walls and columns.
14. Discrepancy between plans and specs. Specs section for air compressor 22 15 19 – 4 2.4 calls for a dual piston pump however Sheet P19 CAS-1 shows a rotary screw compressor. A/E please verify the correct equipment.
Response: Sheet P19 is correct. The Park requested a rotary screw compressor.
15. Vehicle Exhaust systems EF-4 indicated on sheet M15 under Fan Schedule – does not indicate a location or show specific location on the plans. A/E please advise.
Response: Refer to the Level 1 / Zone 1 ductwork plan on sheet M3. EF-4 is located near the intersections of columns B and 7.
16. The Vehicle Exhaust system listed on M15 under Fan Schedule. A/E please confirm this is the same as a vehicle exhaust removal system on an overhead trolley.
Response: Fan EF-4 is a fixed vehicle exhaust fan – not an overhead trolley. See Attachment 01c-Q16 to Amendment 0003, Product Cutsheet.
https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Faluminumpipenow.com%2F%3Fgclid%3DCjwKCAjw2rmWBhB4EiwAiJ0mtXlFgs7UjCgi6EEje85zSpcRJfrxCyA_Iuj04cU28eAjGbyyDfd78xoC8NkQAvD_BwE&data=05%7C01%7CAlan_Stormont%40nps.gov%7Caeb248453ea849ff551308da66966cd1%7C0693b5ba4b184d7b9341f32f400a5494%7C0%7C0%7C637935093506961681%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=DDqy%2Fc86sDvNEH%2BxD06KUUiI1I6KlYEyQonSpaKJhaQ%3D&reserved=0 https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Faluminumpipenow.com%2F%3Fgclid%3DCjwKCAjw2rmWBhB4EiwAiJ0mtXlFgs7UjCgi6EEje85zSpcRJfrxCyA_Iuj04cU28eAjGbyyDfd78xoC8NkQAvD_BwE&data=05%7C01%7CAlan_Stormont%40nps.gov%7Caeb248453ea849ff551308da66966cd1%7C0693b5ba4b184d7b9341f32f400a5494%7C0%7C0%7C637935093506961681%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=DDqy%2Fc86sDvNEH%2BxD06KUUiI1I6KlYEyQonSpaKJhaQ%3D&reserved=0
17. I’m wondering if you may be able to help me determine if this project for the Demolish and Construct New Maintenance Facility includes any vehicle lifts. We’re a heavy duty factory direct lift distributor specializing in fleet maintenance facilities and DOD projects throughout the US.
Response: Yes, a two post and a four post vehicle lift. You can find the information on the drawings and in the spec too (SECTION 11 1100–VEHICLE LIFTS).
18. I don’t find the Subdrainage Spec. 33 46 00 in Division 33 – Utilities, thanks.
Response: Refer to attached Spec Section 33 46 00 – Subdrainage. The attachment will be provided in a forthcoming amendment.
19. Specifications Section 024113 Demolition: 1.8D states that it is not anticipated that hazardous materials will be encountered. 028214 Asbestos Abatement.is included. Has a survey of Hazardous Materials been completed? We need to be able to quantify the scope of work for this section.
Response: Section 028214 Asbestos Abatement has been updated to include a survey of hazardous materials.
20. Specifications Section 028214 Asbestos: 1.3.1 Indicates there was an environmental report done in 2020. But it looks like for the wrong project.
Response: This section (attached) has been revised to delete the incorrect references and to add a schedule of abatement scope. See Attachment 01b-Q09 to Amendment 0003.
21. Specifications Section 028214 Asbestos: 1.3.2 Further states that three bulk asbestos tests will be at the Contractors expense and any further testing and removal will be paid for by equitable adjustment in the contract price by contract clause “changes”. Please verify extend of Asbestos removal required of the contractor.
Response: Section 028214 Asbestos Abatement has been updated to include a survey of hazardous materials.
22. Specifications Section 221626 Liquified Petroleum Gas: 3.12 Installation of storage containers.
Subsection 3.12b Instructs the installer to fill the container to 80% capacity. Is the contractor to supply the propane or will owner’s supplier furnish the propane?
Response: NPS supplier will furnish the propane. Keep in mind that the contractor will be responsible for testing the system prior to finalizing the punch list.
23. Specifications Section 238236: Reviewing the fin tube it appears that the scheduled capacity is based on hot water whereas the fluid shown is 35% PG solution. This will reduce capacity by about 8%, please advise.
Response: This was taken into account when selecting finned tube radiation.
24. Specifications Section 221519: Paragraph 2.4 A 3 mentions a two stage 7.5HP compressor 208/3 on a 120 gallon horizontal compressor. This would be a reciprocating type of compressor.
However, this compressor is not shown on the Plumbing Equipment Schedule (Sheet 179) of the drawings Response: Spec section 221519: paragraph 2.4 A 3 is incorrect. Sheet P19 is correct, refer to tag CAS-1, Compressed Air Skid. The Park requested a single rotary screw compressor.
25. Drawing Sheet 179: The Plumbing Equipment Schedule shows an R11n-TAS with no tank. This compressor is a 15HP variable speed TAS (Total Air System). TAS means that it has a built-in dryer and filters. Did the 7.5HP get dropped? Should there be a tank with the 15HP?
Response: NPS requires 50CFM @ 120 PSI the 7.5HP only provided 40CFM. Spec section 221519 calls for a ASME 120 gallon horizontal receiver.
26. Specifications Section 233113: 3.3 C 1 and 2 conflict one another. Stainless or galvanized.
Response: All ductwork exposed to weather shall be Type 316 stainless steel.
27. Specifications Section 238129: 3.11 B mentions delegated design for electrical power to mechanical equipment. We assume this will determined by the equipment schedule on sheet 193 of the drawings which show amperage and voltage required?
Response: This paragraph is meant to ensure that the Mechanical contractor won’t divert from the construction documents regarding electrical amperage and voltage. If for whatever reason this happens, the Mechanical contractor is responsible for coordinating with the Electrical contractor at no additional cost to the government.
28. Specifications Section 015000: 3.3 B. Is a bathroom required in the contracting officer’s field trailer? Would a portable toilet and hand sanitizer be acceptable? It may be difficult to find an office trailer with a bathroom and have utilities run to the office trailer.
Response: Contracting officer's field trailer, bathroom, portable toilet and/or hand sanitizer will not be required.
29. Spec SECTION 05 12 00 - STRUCTURAL STEEL FRAMING refer to Section 09 96 00 "High-
Performance Coatings" for painting requirements. Specs does not include spec section 09 96
00. A/E please provide.
Response: There is no section 09 96 00. The specification for painting structural steel framing is included in Section 09 91 13 “Exterior Painting”.
30. Document shows FAR and Fire Garage to be relocated. During the walkthrough we noticed existing attached stairs. A/E please verify if the stairs to be detached and relocated with the buildings.
Response: The entire assembly for both buildings, including stairs, are to be relocated, essentially replacement in kind.
31. NPS please confirm all of Phase 1 to be completed before NTP.
Response: Confirmed – Phase I tasks will be completed before the NTP is issued.
32. Document indicates the existing fuel tank to be relocated. Will the tanks be empty by NPS? A/E please confirm.
Response: The contractor will be responsible for emptying the tanks prior to construction actions.
33. Are we to assuming all existing furnishing and material in the Maintenance Building to be removed (completely empty) by NPS. NPS please confirm.
Response: Yes, this is accurate all “removable content” will be removed. Salvaged materials are the responsibility of the GC/Sub per contract documents/spec.
34. Document does not have a Geotech report. A/E please provide.
Response: See response to Question #3.
35. Table of Contents shows 33 41 20 High-Density Polyethylene Pipe and 33 46 00
Subdrainage. There is no Specs Section for both. A/E please provide.
Response: Refer to attached Spec Section 33 41 20 – High-Density Polyethylene Pipe and Section 33 46 00 – Subdrainage. See Attachment 01a-Q35 to this Amendment 0005.
36. SECTION 32 32 23.01 - MECHANICALLY STABILIZED EARTH WALL shows related requirements
Section 313719: Boulders. There is no Specs. A/E please provide.
Response: Refer to Revised Spec Section 32 32 12.01 Mechanically Stabilized Earth Wall.
Reference to Section 313719 Boulders has been removed. See Attachment 01a-Q36 to this Amendment 0004.
37. Documents show required Certification of Vaccination. NPS please confirm this is required for this specific project.
Response: Until otherwise notified, contractor employees under the employment of the NPS are required to have the attached vaccination certification form in their possession if requiring access to NPS indoor facilities.
38. Specification sections 06 10 00 rough carpentry, 06 20 23 interior finish carpentry, 06 41 16
Plastic Laminate Clad cabinets, 07 42 10 Composite Cladding Support System, 08 14 16 Flush Wood Doors, 08 41 13 Aluminum Framed Entrances and Storefronts, 08 91 19 Fixed Louvers, 09 21 16 Gypsum Board Shaft Walls Assemblies, 09 29 00 Gypsum Board, 09 84 36 Sound- Absorbing Ceiling unit, state under “Regional Materials” and or “Certified Wood” that the Manufacture of such products are to be within 100 miles of the project site and that materials are to have been extracted, harvested, or recovered, as well as manufactured within 100 miles.
We are having difficulty in meeting these requirements and request the regional materials portion of the specifications be either eliminated or revised.
Response: Please follow a guideline of “being pragmatic” and the best route to not adversely impact project schedule and or project cost while maximizing ability to stay green and sustainable per original design. we understand that locally sourced materials may not be available given local and current manufacturing requirements.
39. Same question as above for Certified Wood: Most of the same specifications state that “FSC
Pure or FSC Mixed Credit” wood will need to be provided. Not only is this lumber costly, but also has long lead times. Please confirm FSC lumber is required for the above-mentioned specification sections.
Response: Please follow a guideline of “being pragmatic” and the best route to not adversely impact project schedule and or project cost while maximizing ability to stay green and sustainable per original design.
40. Drawing C1: Utility Notes #1 mentions design as needed. These utility designs are typically unknown until after award of the contract. Would an allowance be acceptable for these unknowns?
Response: Refer to Revised Drawing C1 – Utility Note #1 revised to remove reference to design of permanent utilities. Contractor is only responsible for the design of temporary utilities, if needed. All permanent utilities have already been fully designed and included in the bid set.
41. Insurance: Is Builders Risk Insurance required for the project? If so is it to be paid for by
Government or contractor?
Response: Required and paid for by the GC and associated subs.
42. Is Owner’s Protective Insurance Required for the project? If so is it to be paid for by
Government or contractor?
Response: Required and paid for by the GC and associated subs.
43. Insurance: Are there any other special insurances required?
Response: Other than general liability, automobile and workman’s compensation insurance, no other insurances are required at this time.
44. Spec. 015000: Section 1.3 states that the owner will supply electricity and water at no cost to the contractor. The Solicitation dated 7/7/2022 section 52.236-14 states that the contractor must meter and pay Government for utilities. Which of these is correct?
Response: The construction zone will require a new meter (sub-meter be assigned to this specific project. Set up temporary meter/permit, GC/Subs will need to setup via coordination with local power company and park (park will facilitate permission). Regarding the water, water for domestic use will be covered/shared by the park. however, construction water will need to be accounted for by the GC/Sub separately and brought to the site as needed. Coordinate with park as needed.
45. Spec. 323113: Chain link fence is specified but there is steel backed timber rail shown on drawing C34. Where is the chain link fence to be installed?
Response: Chain link fencing is shown enclosing the propane tank farm and fuel station tank.
Refer to drawing L6, details 3 and 4.
46. Drawing C34: Fence Detail says to use weathering steel hardware. Our fence contractor recommends hot dipped galvanized.
Response: Hot dipped galvanized is acceptable.
47. Drawing C7: Does the fence continue the entire length of the retaining wall or does is it have breaks at the ends of the block pavers?
Response: The guardrail extends continuously along the parking areas with breaks at the islands between block pavers. See Landscape Plan L4 for clarification.
48. Drawing A21: Are windows marked SF1, and SF2 to be hollow metal frame or aluminum?
Please provide window schedule or description of what windows are aluminum and what are hollow metal.
Response: All windows are aluminum storefront systems. There are no hollow metal windows in this project. Refer to Drawing A64 for exterior storefront types.
49. Solicitation page 9: Contract Price Schedule. Option B says landscape plant material. Are we to include material only for landscaping? No labor? Please define this option for what is included and not included in the base bid versus the optional price.
Response: Options including option B are deductive, they include both materials and labor associated savings. An additional response will be provided.
50. Spec. 055000: 2.10 metal bollards are described to be built with a base plate and bolted to a concrete slab. Drawing C33 or Page 38 of the drawings shows a concrete encased bollard with only three feet depth of concrete. We don’t recommend either of these in the State of Maine.
We usually use a precast bollard with a minimum 4’ tall or taller concrete base or similar to the attached drawing which are cost effective. Would these be acceptable?
Response: Proposed solution is acceptable to NPS. See Attachment 01b-Q50 to this Amendment 0004.
51. Spec. 221316: Paragraph 2.7 encasement for underground metal piping. Would schedule 40 PVC be an acceptable alternative for DMV? If not please provide a detail, product, and manufacturer for the desired material.
Response: Specified polyethylene encasement would be POLYWRAP by Trumbull Manufacturing or similar. Mfg_Catalog.indd (trumbull-mfg.com). See Attachment 01c-Q51 to this Amendment 0004.
52. Can you clarify which systems are to be commissioned?
In Section 019114 1.1 A systems are listed as:
- HVAC & BAS
- Lighting Control
- Building Envelope
- Fire Alarm and Suppression
- Electrical (Including Generator & PV)
- Access Control Security
- Lightning Protection
In Section 019114 3.10 Systems to be commissioned are listed as:
- Fire Suppression
- Plumbing
- HVAC
- Electrical
So, specifically are Fire alarm, Access Control, Lightning Protection and Building Envelop included in the scope of commissioning or not?
Response: Yes, fire alarm, access control, lightning protection and building envelope are to be commissioned.
53. Drawing A61: Doors 143H and 145B have hardware STC 52 rating. Are these doors required to be sound rated (STC)? If so, what is the STC rating?
Response: The doors should have an STC rating of 52 as well.
54. Drawing A16: Keynote 150 shows overhead hoist beams rated for 6,000 lbs. capacity. What size and shape beams are required? How are they attached?
Response: Hoist beam is to be designed by PEMB manufacturer per note on dwg A58.
55. Drawing A16: Is a hoist required for the hoist beams? If so, please specify what is required.
Response: No hoist is required to be provided in the project.
56. Spec. 334120: HDPE spec is shown in the table of contents but is missing from the specifications.
Response: This specification section 334120 is attached. See Attachment 01a-Q35 to this Amendment 0005.
57. Septic Treatment: Our earthwork contractor is unable to get accurate pricing for the septic treatment system or septic dispersal system because they are not designed. Could this be assigned an allowance then be designed and priced accordingly? The State of Maine requires systems over a certain threshold be an engineered system.
Response: It is the Contractor’s responsibility to contact suppliers and include costs in the bid.
https://www.trumbull-mfg.com/wp-content/uploads/Trumbull-Polyethylene-Encasement-Tubing-09-01-20.pdf
58. Existing Septic: What are the sizes of the existing septic tanks shown to be filled with crushed material and abandoned?
Response: There are two (2) 6,000 gallon underground storage tanks to be filled with crushed material and abandoned.
59. Spec. 323223.02: Where are the Wire Mesh Gabion Walls located in the drawings?
Response: The Wire Mesh Gabion Wall has been removed from the project scope. This specification section will be deleted.
60. Drawings C37: Detail 3 shows precast porous concrete blocks. Can a specification or more information about these be issued showing size, concrete mixture, and manufacturer?
Response: This specification section 321443 is attached. See Attachment 01b-Q60 to this Amendment 0005.
61. Drawing C13: Shows the underground propane piping going under the slab. Is it possible to bring the underground gas piping above grade adjacent to the exterior wall then enter the mechanical room above grade?
Response: This would be acceptable, but the manual shutoff valve must be located in the mechanical room.
62. Drawings C38 and C-39: Our pipe supplier needs detailed layouts/plan views to accurately price the Strormtech storm water detention system, these questions come from the manufacturer, outlines appear to be MC-3500 (45” tall chambers) while elevations appear to be for the SC- 160LP (12” tall chambers) additional information is needed to provide pricing.
Response: Profile view of the systems is inclusive of chambers and stone envelopes. Refer to details on C38 and C39 for criteria and details on systems and installation, the EOR used 12” high chambers for this project. Plans and details do not reference a specific manufacturer – contractor may use any manufacturer that meets plans and specifications.
63. Drawings A56 and A57: Please provide dimensions for lockers. We need length, width, and height dimensions in order to provide pricing.
Response: Nominal 18”D x 15”W x 62”H lockers.
64. Drawings: When the pdf drawings are opened in Adobe Acrobat there are many thousands of
AutoCAD SHX Text comments that come up in the comment viewer. This continually causes Acrobat to crash. Are these comments all included on the drawings? Are considered bidding documents?
Response: SHX Text comments not required in the PDF, document is a standalone document.
65. Spec 074113.16: Standing-Seam Metal Roof Panels. Our Pre-Engineered Metal Building
Manufacturer is unable to supply panels to meet the requirements. We have attached the roof and siding specs for the panels offered by our supplier. There is a discrepancy that the Loc360 panel is not available in a 3 coat Kynar finish. We would like the metal building manufacturer to supply all siding and roofing to avoid problems with color match and warranty.
Response: Please meet intent of the specification, substitutions are allowed per spec(substitution must be or equal or better).
66. Would it be possible to have the CADD Files for the Civil Drawings (existing & proposed grades) posted on the website? This will greatly assist in our estimating ability for the site grading work.
Response: CADD files to be released and will be made available. Requests should be sent to both the Contracting Officer, Jeff Hepp, jeffery_hepp@nps.gov, and the Contract Specialist, Alan Stormont, alan_stormont@nps.gov.
67. Bid Schedule shows Option B, (Landscape plant materials). Documents do not clearly show what is base bid and Option B. All plant material (topsoil, mulch, seeding, trees, and etc.) on L8 thru L10 including L15 and L16 Option B. A/E please clarify.
Response: Pending response
68. Sheet A53 Finish Schedule ACP-1 Acoustic Ceiling Panels Armstrong, Invisacoustics indicates
4’x8’. Sheet A58 RCP Legend ACP-1 show 2’x4’. A/E please advise which one is correct.
Response: ACP-1 panels are 2’x4’.
69. Detail 1/A47 Showers 125 & 126 shows grab bars, benches, and rods. Documents do not indicate CFCI or GFGI. A/E please confirm.
Response: They are CFCI.
70. S3 Foundation plan shows F5 and Footing Schedule does not have an F5. A/E please advise.
Response: F5: 5’-0”x5’-0”x12” with #5 @ 12” O.C. T&B.
71. Documents indicates to include material sales tax for this project. NPS please confirm this is correct.
Response: Pending response.
72. Section 22 11 16-5: 3.2 B Refer to CDA Copper Tube Handbook. No information can be found regarding under slab installation.
Response: The current Copper Tube Handbook no longer addresses this, so refer to the CDA - Copper Development Association website (www.copper.org/applications/plumbing/water_service/installation.php) for underground copper piping best practices.
73. Drawing S1: Note F3 describes the foundation design. When reactions and loads are calculated by the successful Pre-Engineered Metal Building Manufacturer, will the Government’s Structural Engineer re-engineer the foundations? Will the contractor be allowed to re-estimate the concrete and reinforcing quantities?
Response: On Sheet S2, note S2 states that if the loading is different than the stated loads as shown in note S1, than the contractor is to notify the Structural Engineer to redesign the loads.
74. Drawing S3 and S4: What size are footings labeled F5? Not shown in the footing schedule.
Response: See response to RFI 70.
75. Demolition: Please help us understand the demolition scope. How many boilers are to be removed? Oil tanks, feet of duct work, refrigerant? Or list of existing equipment to be removed.
76. Drawing S5: What product is required for waterstop shown at several locations of the water tank?
Response: Acceptable waterstops as follows:
mailto:jeffery_hepp@nps.gov
Self-Expanding Butyl Strip Waterstops: Manufactured rectangular or trapezoidal strip, butyl rubber with sodium bentonite or other hydrophilic polymers, for adhesive bonding to concrete, 3/4 by 1 inch. Acceptable products are:
1. Waterstop-RX by CETCO.
2. Conseal CS-231 by Concrete Sealants, Inc.
3. Swellstop by Greenstreak, Inc.
4. Earth Shield Type 20 by JP Specialties, Inc.
5. Mirastop RT by Carlisle Coatings & Waterproofing
77. 096513-3: Note D calls for base to be 34” tall, please confirm.
Response: This is a typo that should be 4” base.
78. Drawing M14: ACCU1 per mechanical schedule shows heating capacity of 324,000 BTU/H down to -15 degrees. This particular model is rated for 308,000 BTU/H at 47 degrees. Please provide total derate capacity required at –15 degrees.
Response: For ACCU-1, the derated capacity at -15degF Is 199.9 MBH.
79. Pavement Markings: Pease provide information on pavement markings. Are glass beads required in the paint?
Response: Glass beads are not required in the paint for pavement marking.
80. Drawing P11: Detail 8 shows ductile iron for under slab pipe work. Specification 22 11 16 states that the material to be used is type k soft copper. Please clarify Response: Detail 8 is for the water main entrance only. The Civil water pipe material can be brought through the foundation wall into the building below slab and terminate once above slab. The max distance from foundation wall to final civil pipe material termination shall be 5 feet. All other interior underground distribution water piping shall be Type K soft copper and follow CDA website guidelines and current plumbing code water pipe material.
81. Section 221116-10: 3.12 D states that under slab domestic water pipe to be solder joints. Is brazed connections acceptable? Is HDPE acceptable alternative?
Response: Per to CDA website guidelines; underground copper joining methods should be compression, flared, or packed joints. Solder and brazing should not be used on underground copper piping. HDPE is not an approved material for any water distribution piping within a building per current plumbing code.
82. The Grading Plan is very busy and is not legible as is. We will need a “cleaned-up” Grading Plan if we have to digitize.
83. The new maintenance building wash bay 134 calls for trusscore PVC wall panels. Spec 06 64 00 indicates PVC wall and ceiling panels. Wash bay includes high bay pendant lights and detail 3 on A24 indicates no PVC ceiling. 3/A24 also indicates wall panels stop at 14’ above the floor.
Please confirm 14’ high PVC walls and no PVC ceiling in the wash bay.
84. 061000: 2.3 E. Fire Retardant Treatment. Treat all rough carpentry unless otherwise noted.
Does all framing of out buildings need to be treated? Not sure we can get TJI joists and PSL beams in fire treated.
85. Drawing A5 and A39: Exterior wall type EW4 shows 1x4 wood strapping. All details on A39 show 7/8” hat channel. If hat channel is desired what gauge/galvanizing is required?
86. Drawing A30: Detail 2 shows a wall type EW1-C which is 10” thick and has gypsum, mineral wool insulation with z girts, and batt insulation. All other walls in the building are type EW4. Is the EW1-C correct?
87. Drawing A36: Keynote 14 says to refer to drawing A5 R1 for roof assembly It seems R2 would match the construction of the barricade, plow, trails storage building. Is R2 correct?
88. Drawing C13: Site Utilities Plan does not show underground electric to the Plow, Barricade, storage building or the Hazmat/Battery Storage Building.
89. Civil Drawings: Drawings show PVC pipe on the sanitary profile and HDPE on the plan view.
Which is required?
90. Wage Scale: Is this project considered Industrial Work? Or is any part of the work considered
Industrial Work? See Laborer.
91. Ledge Removal: If ledge is encountered how will it be paid for? Can an allowance be established by the Government and carried by the contractor?
92. Drawing C22: Storm drain structure table has a heading with structure diameter but shows no information, profile view of storm drains seems to indicate different size structures and there is a detail 2 on drawing C36 for a Type F catch basin, we can’t seem to find any, and we are assuming the 3” sump on detail is supposed to be 3’, Our site work contractor needs structure sizing in order to get accurate pricing.
93. 333945: 2.2 Precast Settling Tank. Where is this located on the drawings?
94. Light Pole Bases: Drawing C44 shows 7” light pole base going down into a 30” light pole base concrete base. There are typical light pole bases also shown on detail 2 of drawing E20. Which one of these is correct or to be used? How is the electrical conduit to be run into the bases?
95. Section 233113: Antimicrobial Coating – Part 2.4:C calls for antimicrobial coating on the inside and outside of all ductwork. Is this correct?
96. HVAC Ducts: Duct Liner – The specifications do not specify where to use duct liner. On the drawings I do not see it indicated anywhere. On drawing M11 detail 3 it shows liner 10 feet from exhaust/return grilles above a finished ceiling. Is this detail only applicable for return ducts above a finished ceiling? Or is it applicable to all return & exhaust grilles?
97. HVAC Ducts: Duct Liner – Closed cell liner has been specified in Section 233113 Part 2.5 A. In
Part 2.5 B:9 is it calling for a perforated inner wall. Is the inner wall required on lined ductwork when using the specified closed cell liner?
98. Section 233112: Sawdust Collection Ductwork – In Part 3.2: F through J mentions VMC multiple times. Can you indicate what VMC and direct us to where we can find the information.
99. Section 233113: Duct Cleaning – 3.9 it calls for all new ductwork to be cleaned. Since this is an entirely new system that will be protected during the construction process will duct cleaning be required?
100. Drawing C44: Note 6 guardrail embedded in 24”dia. concrete anchor 2.5’ depth, sheet C34 detail 1 shows guardrail post 4’-8” embedment below finish grade. Another detail on C34 shows a 24” depth concrete anchor on solid rock for short posts please clarify which method should be used.
101. Drawing A44: Detail 3 shows a whiteboard to be furnished and installed by the contractor.
There is no spec provided for this, please provide information.
102. Spec section 13 34 19 paragraph 2.1 indicates “one of the following” metal building system.
Chief is not listed. Can Chief Buildings be used in the new building for structure and panels?
https://chiefbuildings.com/
103. Septic System: Supplier Comments. Documents are showing a single 30/24 Bioclere which is larger than needed but given it’s already on the plans and there is no flow equalization, I assume stay with the Model 30/24 which will handle any seasonal surge loads.
104. Drawing C41: Supplier Comments. Page 46 references an old castle primary settling tank CST-
2500 which I suspect is 2,500 gallons. This septic tank is way too small. We will require a minimum 5,000-gallon, 2-compartment tank but prefer 7,500 gal primary settling tank. How would you like to proceed?
105. 062023: Section 2.1 Red cedar comes from the west coast and does not meet the 100 mile harvested or manufactured spec. Eastern cedar is cut in this area but probably is not going to be FSC. Do these requirements apply to the cedar?
106. 062023: Does the cedar have to meet flame spread and smoked developed spec? Will it need to have a fire retardant COATING APPLIED??
https://chiefbuildings.com/
107: 221626: Is it acceptable to run a higher pressure from the propane tank farm to the building/generator pad to decrease the pipe size? Pressure would then be brought down at the building. This seems to be a common practice.
(End of Amendment 0005 Q&As)