140P2022R0045_Att01a-100pctSpecifications-Vol1of2_220325.pdf
PDF 18 MB Posted
- Solicitation number
- 140P2022R0045
About this file
This document summarizes a federal solicitation for demolition and construction services. The solicitation number is 140P2022R0045 issued by the Department of the Interior National Park Service National Office. It seeks bids to demolish and construct a new maintenance facility at Acadia National Park in Bar Harbor, Maine. Responses are due by the date specified in the attached 100% specifications and drawings volume. The selected contractor will be awarded a firm fixed-price construction contract to complete the project in accordance with the specifications.
View the file
Other files
Show all 37
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NATIONAL PARK SERVICE
U.S. DEPARTMENT OF THE INTERIOR
NPS NATIONWIDE
DENVER SERVICE CENTER
Maintenance Building and Associated Sitework at
McFarland Hill, Acadia National Park, Bar Harbor, Maine
ACAD 151309B
Acadia National Park
Bar Harbor, Maine
SPECIFICATIONS
VOLUME I
FINAL CONSTRUCTION DOCUMENTS
100% SUBMISSION
March 25, 2022
Prepared by:
WSP USA, 1250 23rd Street NW, Washington, DC 20010
EYP, Independence Wharf, 470 Atlantic Avenue, 7th Floor, Boston, MA 02110
Rhodeside Harwell Inc., 510 King Street, Ste 300, Alexandria, VA 22314
03252022
This page intentionally left blank
ACAD 151309B 00 01 10 - 1
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 Summary of Work
01 26 01 Contract Modification Procedures
01 27 00 Definition of Contract Line Items
01 31 00 Project Management and Coordination
01 32 16 Construction Schedule
01 32 33 Photo Documentation
01 33 23 Submittal Procedures
01 35 23 Safety Requirements
01 35 25 Explosives 01 40 00 Quality Requirements
01 42 00 Reference Standards
01 50 00 Temporary Facilities and Controls
01 56 39 Temporary Tree and Plant Protection
01 57 19.11 Indoor Air Quality Management
01 57 19.12 Noise and Acoustics Management 01 57 23 Temporary Storm Water Pollution Prevention
01 67 00 Product Requirements
01 73 29 Cutting and Patching
01 73 40 Execution
01 74 19 Construction Waste Management and Disposal
01 77 00 Closeout Procedures
01 78 23 Operation and Maintenance Data
01 79 00 Demonstration and Training
01 81 13 Sustainable Design Requirements – Non-LEED Projects
01 91 14 Total Building Commissioning
DIVISION 02 - EXISTING CONDITIONS
02 41 13 Selective Site Demolition
02 41 16 Structure Demolition
02 82 14 Asbestos Abatement
DIVISION 03 - CONCRETE
03 10 00 Concrete Forming and Accessories
03 20 00 Concrete Reinforcing
03 30 00 Cast-in-Place Concrete
03 35 00 Cast-in-Place Concrete for Utilities
03 35 43 Polished Concrete Finishing
DIVISION 04 – MASONRY – Not Applicable
ACAD 151309B 00 01 10 - 2
DIVISION 05 - METALS
05 12 00 Structural Steel Framing
05 40 00 Cold Formed Metal Framing
05 50 00 Metal Fabrications
05 52 14 Landscape Pipe and Tube Railings
DIVISION 06 – WOOD, PLASTICS, & COMPOSITES
06 10 00 Rough Carpentry
06 16 00 Sheathing
06 20 23 Interior Finish Carpentry
06 41 16 Plastic-Laminate-Clad Architectural Cabinets
06 64 00 Plastic Paneling
DIVISION 07 – THERMAL AND MOISTURE PROTECTION
07 11 13 Bituminous Dampproofing
07 16 13 Polymer Modified Cement Waterproofing
07 21 00 Thermal Insulation
07 27 26 Fluid-Applied Membrane Air Barriers
07 41 13.16 Standing-Seam Metal Roof Panels
07 42 10 Composite Cladding Support Systems
07 46 19 Steel Siding
07 72 53 Snow Guards
07 84 13 Penetration Firestopping
07 84 43 Joint Firestopping
07 92 00 Joint Sealants
DIVISION 08 – OPENINGS
08 11 13 Hollow Metal Doors and Frames 08 11 25 Interior Aluminum-Framed Glass Walls
08 14 16 Flush Wood Doors
08 31 13 Access Doors and Frames
08 33 23 Overhead Coiling Doors
08 34 83 Floor Doors4
08 41 13 Aluminum-Framed Entrances and Storefronts
08 62 00 Unit Skylights
08 71 00 Door Hardware
08 80 00 Glazing
08 91 19 Fixed Louvers
DIVISION 09 – FINISHES
09 21 16.23 Gypsum Board Shaft Wall Assemblies
09 22 16 Non-Structural Metal Framing
09 29 00 Gypsum Board
09 30 13 Ceramic Tiling
09 51 13 Acoustical Panel Ceilings
09 65 13 Resilient Base and Accessories
09 65 19 Resilient Tile Flooring
09 68 13 Tile Carpeting
09 84 36 Sound-Absorbing Ceiling Units
09 91 13 Exterior Painting
09 91 23 Interior Painting
ACAD 151309B 00 01 10 - 3
09 93 00 Transparent Finishing
DIVISION 10 – SPECIALTIES
10 14 23.16 Room-Identification Panel Signage
10 21 13.19 Plastic Toilet Compartments
10 22 39 Operable Folding-Panel Partitions
10 28 00 Toilet, Bath Laundry Accessories
10 44 00 Fire Protection Specialties
10 51 13 Metal Lockers
10 56 13 Metal Storage Shelving
10 73 16 Fuel Station Canopies
DIVISION 11 – EQUIPMENT
11 11 00 Vehicle Lifts
11 11 26 Vehicle Washing Equipment
DIVISION 12 – FURNISHINGS
12 24 13 Roller Window Shades
12 36 61.19 Quartz Agglomerate Countertops
12 48 13 Entrance Floor Mats and Frames
DIVISION 13 – SPECIAL CONSTRUCTION
13 34 19 Metal Building Systems
13 34 20 Gas Cylinder Storage Cages
DIVISION 21 - FIRE SUPPRESSION
21 05 17 Sleeves and Sleeve Seals for Fire Suppression Piping
21 05 18 Escutcheons for Fire-Suppression Piping 21 05 53 Identification for Fire-Suppression Piping and Equipment
21 08 00 Commissioning of Fire Suppression
21 11 19 Fire-Department Connections
21 13 13 Wet-Pipe Sprinkler Systems
21 22 00 Clean-Agent Fire-Extinguishing Systems
21 32 13 Electric-Drive, Vertical-Turbine Fire Pumps
21 34 13 Pressure-Maintenance Pumps
DIVISION 22 – PLUMBING
22 05 13 Common Motor Requirements for Plumbing Equipment
22 05 16 Expansion Fittings and Loops for Plumbing Piping
22 05 17 Sleeves and Sleeve Seals for Plumbing Piping
22 05 18 Escutcheons for Plumbing Piping
22 05 19 Meters and Gages for Plumbing Piping
22 05 23.12 Ball Valves for Plumbing Piping
22 05 23.14 Check Valves for Plumbing Piping
22 05 29 Hangers and Supports for Plumbing Piping and Equipment
22 05 48.13 Vibration Controls for Plumbing Piping and Equipment
22 05 53 Identification for Plumbing Piping and Equipment
22 07 16 Plumbing Equipment Insulation
22 07 19 Plumbing Piping Insulation
22 08 00 Commissioning of Plumbing
22 11 16 Domestic Water Piping
ACAD 151309B 00 01 10 - 4
22 11 19 Domestic-Water Piping Specialties
22 11 23.13 Domestic-Water Packaged Booster Pumps
22 11 23.21 Inline, Domestic-Water Pumps
22 12 23.11 Facility Indoor Potable-Water Storage Tanks
22 13 16 Sanitary Waste and Vent Piping
22 13 19 Sanitary Waste Piping Specialties
22 13 19.13 Sanitary Drains
22 13 23 Sanitary Waste Interceptors
22 15 13 General-Service Compressed-Air Piping
22 15 19 General-Service Packaged Air Compressors and Receivers
22 16 26 Facility Liquefied-Petroleum Gas Piping
22 35 00 Domestic-Water Heat Exchangers
22 42 13.13 Commercial Water Closets
22 42 13.16 Commercial Urinals
22 42 16.13 Commercial Lavatories
22 42 16.16 Commercial Sinks
22 42 23 Commercial Showers
22 45 00 Emergency Plumbing Fixtures
22 47 16 Pressure Water Coolers
DIVISION 23 – HEATING VENTILATION AND AIR CONDITIONING
23 05 13 Common Motor Requirements for HVAC Equipment
23 05 16 Expansion Fittings and Loops for HVAC Piping
23 05 17 Sleeves and Sleeve Seals for HVAC Piping
23 05 18 Escutcheons for HVAC Piping
23 05 19 Meters and Gages for HVAC Piping
23 05 23.12 Ball Valves for HVAC Piping
23 05 23.13 Butterfly Valves for HVAC Piping 23 05 23.14 Check Valves for HVAC Piping
23 05 29 Hangers and Supports for HVAC Piping and Equipment
23 05 48.13 Vibration Controls for HVAC
23 05 53 Identification for HVAC Piping and Equipment
23 05 93 Testing, Adjusting, and Balancing for HVAC
23 07 13 Duct Insulation
23 07 16 HVAC Equipment Insulation
23 07 19 HVAC Piping Insulation
23 08 00 Commissioning of HVAC
23 09 23 Direct Digital Control (DDC) System for HVAC
23 21 13 Hydronic Piping
23 21 16 Hydronic Piping Specialties
23 21 23 Hydronic Pumps
23 23 00 Refrigerant Piping
23 25 00 HVAC Water Treatment
23 31 13 Metal Ducts
23 33 00 Air Duct Accessories
23 33 46 Flexible Ducts
23 34 23 HVAC Power Ventilators
23 37 13.13 Air Diffusers
23 37 13.23 Registers and Grilles
23 52 16 Condensing Boilers
23 72 23.19 Packaged Indoor Energy Recovery Ventilator Units
ACAD 151309B 00 01 10 - 5
23 81 29 Variable-Refrigerant-Flow HVAC Systems
23 82 36 Finned-Tube Radiation Heaters
23 82 39.13 Cabinet Unit Heaters
23 82 39.16 Propeller Unit Heaters
DIVISION 26 – ELECTRICAL
26 00 10 Supplemental Requirements for Electrical
26 00 11 Facility Performance Requirements for Electrical
26 05 13 Medium-Voltage Cables
26 05 19 Low-Voltage Electrical Power Conductors and Cables
26 05 26 Grounding and Bonding for Electrical Systems
26 05 29 Hangers and Supports for Electrical Systems
26 05 33 Raceways and Boxes for Electrical Systems
26 05 43 Underground Ducts and Raceways for Electrical Systems
26 05 44 Sleeves and Sleeve Seals for Electrical Raceways and Cabling
26 05 53 Identification for Electrical Systems
26 05 73.19 Arc-Flash Hazard Analysis
26 08 00 Commissioning of Electrical Systems
26 09 23 Lighting Control Devices
26 12 19 Pad-Mounted, Liquid-Filled, Medium-Voltage Transformers
26 13 23 Medium-Voltage Metal-Enclosed Switchgear
26 24 13 Switchboards
26 24 16 Panelboards
26 27 26 Wiring Devices
26 28 13 Fuses
26 28 16 Enclosed Switches and Circuit Breakers
26 31 00 Photovoltaic System Collectors
26 32 13.16 Gas-Engine-Driven Generator Sets 26 36 00 Transfer Switches
26 41 13 Lighting Protection for Structures
26 43 13 Surge Protective Devices for Low-Voltage Electrical Power Circuits
26 51 19 LED Interior Lighting
26 56 19 LED Exterior Lighting
DIVISION 27 – COMMUNICATIONS
27 05 26 Grounding and Bonding for Communications Systems
27 05 28 Pathways for Communications Systems
27 05 29 Hangers and Supports for Communications Systems
27 05 36 Cable Trays for Communications Systems
27 05 43 Underground Ducts and Raceways for Communications Systems
27 05 44 Sleeves and Sleeve Seals for Communications Pathways and Cabling
27 05 53 Identification for Communications Systems
27 11 00 Communications Equipment Room Fittings
27 11 16 Communications Racks, Frames, and Enclosures
27 13 13 Communications Copper Backbone Cabling
27 13 23 Communications Optical Fiber Backbone Cabling
27 15 13 Communications Copper Horizontal Cabling
27 15 23 Communications Optical Fiber Horizontal Cabling
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 10 00 Access Control
ACAD 151309B 00 01 10 - 6
28 14 00 Access Control System Hardware
28 20 00 Video Surveillance
28 31 00 Intrusion Detection
28 46 21.11 Addressable Fire-Alarm Systems
DIVISION 31 – EARTHWORK
31 10 00 Site Clearing
31 20 00 Earth Moving
31 23 00 Excavation and Backfill
31 23 19 Dewatering
31 25 00 Erosion and Sediment Control
31 50 00 Excavation Support and Protection
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 12 16 Asphalt Pavement
32 13 13 Concrete Paving
32 14 00 Unit Paving
32 31 13 Chain Link Fences and Gates
32 32 23.01 Mechanically Stabilized Earth Wall
32 32 23.02 Wire Mesh Gabion Wall
32 33 00 Site Furnishings
32 91 00 Planting Soil
32 92 00 Turf and Other Seeded Areas
32 93 00 Exterior Plants
DIVISION 33 – UTILITIES
33 05 26 Tracer Tape
33 11 25 Polyvinyl Chloride Non-Pressure Pipe and Fittings 33 11 30 Water Line Testing and Disinfection
33 12 50 Valves and Appurtenances
33 34 19 Premanufactured Waste Treatment Unit
33 34 51 Drainage Dispersal System
33 39 45 Precast Concrete Structures
33 39 50 Frames, Grates, Hatches and Covers
33 41 00 Storm Utility Drainage Piping
33 41 20 High-Density Polyethylene Pipe
33 46 00 Subdrainage
End of Table of Contents
ACAD 151309B 01 11 00 - 1
051121 SUMMARY OF WORK
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes the following:
1. Work Covered by Contract Documents
2. Work Phases
3. Work Conducted by Government Personnel
4. Government-Furnished Structures and Equipment
5. Contractor Use of Site
6. Public Use of Site
7. Occupancy Requirements for Buildings
8. Conduct of Operations
9. Work Restrictions
10. Special Construction Requirements
11. Soils Investigation Report
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: The site is located at Acadia National Park, 20 McFarland Hill Drive, Bar
Harbor ME 04609-0177.
B. The Work consists of:
1. Demolish 20,423 square feet of unsafe park maintenance structures.
2. Remove and dispose of 13,100 square feet of non-code compliant administrative facilities
3. Construct new maintenance facility to meet programmatic needs and address inadequate accessibility, fire, egress and code compliance requirements.
4. Site improvements including roadways, parking, site utilities, septic field, retaining walls, and stormwater management features.
5. Project is designed to comply with the Sustainable Design Requirements as specified in
Section 01 81 13 "Sustainable Design Requirements."
C. Project will be constructed under a single prime contract.
1.3 WORK PHASES
A. The Work shall be conducted in three phases in the following order, with each phase substantially complete before beginning next phase:
1. Phase 1 – Government Preparation and Building Relocation (see Dwg. A8): Work in this phase will be conducted by Government to move storage containers, trailers, sheds and other materials away from the new construction area. Except as otherwise noted, the
Contractor shall be responsible for disposal of structures, materials and utilities remaining within the new construction area after completion of Phase 1 work.
ACAD 151309B 01 11 00 - 2
2. Phase 2 – Building Relocation by Contractor (see Dwg. A9): Contractor to relocate three existing structures, including construction of new foundations, sitework and utilities as required to make them fully operational for Government occupancy and use.
3. Phase 3 – General site Grading and Utility Demolition (see Dwg. A10): Contractor to prepare site for construction and complete general regrading. The work of this phase includes the following: a) erection of construction fencing along with perimeter erosion and tree protection systems, b) demolition and disposal of abandoned structures, materials and utility systems, c) construction of retaining structures and general rough grading, including installation of below grade water retentions structures and d) construction of new septic system.
4. Phase 4 – Maintenance Facility Construction (see Dwg. A11): Contractor to complete construction of the new facility, including the following: a) construction of the new maintenance building and outbuildings, b) final grading, sitework and landscaping and c) construction of new fuel station, including relocation of existing tank, pumps and systems.
5. Phase 5 – Post-Occupancy Demolition (see Dwg. A12): After occupancy of the new maintenance facility by Government, the Contractor shall demolish the existing maintenance structures, dispose of indicated mobile office units, and complete sitework and landscape restoration at the former maintenance facility site as indicated.
1.4 WORK CONDUCTED BY GOVERNMENT PERSONNEL
A. General: Cooperate with Government so work performed directly by Government staff may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate
Work of this Contract with work performed by Government staff or under separate contracts.
B. Preceding Work: Government staff will relocate existing materials and structures from new construction area as described 1.3.A.1.
C. Concurrent Work: Government is not anticipating concurrent work on site.
D. Future Work: Government is not currently planning for future work at the site after Substantial
Completion.
1.5 GOVERNMENT-FURNISHED STRUCTURES AND EQUIPMENT
A. The project includes relocation by the Contractor of existing Government-owned structures and equipment.
1. Government will inspect existing condition of items prior to relocation work. Contractor shall be present for and assist in Government's inspection.
2. If existing structures and equipment are damaged as a result of Contractor's operations, Contractor shall repair or replace them.
3. Contractor shall install and otherwise incorporate Government-furnished items into Work.
B. Government-Furnished Structures and Equipment to be salvaged and relocated:
1. Existing wood framed structures including the Fire Building, the Fire Vehicle Garage, the Search and Rescue (SAR) Vehicle garage are to be relocated from current to new locations on the site.
ACAD 151309B 01 11 00 - 3
2. Above-ground fuel tank, fueling station pumps and associated safety, control and monitoring systems.
3. Option A: Relocation of the existing fueling station canopy structure is included as an option.
1.6 CONTRACTOR USE OF SITE
A. General: Contractor shall have limited use of site for construction operations. Limit use of premises to areas within the Construction limits indicated on drawings. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Limits: Confine constructions operations to areas within the Construction limits indicated on drawings.
B. Storage of Materials: Confine storage of materials to staging area shown on plans.
C. Parking: Confine parking to staging area shown on plans.
D. Stockpiling: Confine stockpiling to staging area shown on plans.
E. Preservation of Natural Features:
1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants beyond the designated Limit of Disturbance, at no additional expense to the Government.
2. Provide temporary barriers to protect existing trees and plants and root zones.
3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with
Contracting Officer (CO) and remove agreed-on roots and branches that interfere with construction.
4. Do not fasten ropes, cables, or guys to existing trees.
5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
F. Driveways and Entrances: Coordinate construction activities to keep entrances, driveways and roads serving the existing campus operations clear and available to Government employees, and emergency vehicles at all times, except as agreed to by the Contracting Officer. Restrict parking or storage of materials and construction operations to designated construction area.
1. Schedule deliveries to minimize use of campus roads, driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
G. Construction Camp: Establishment of a camp will be permitted in the staging area. Provide utilities as specified in Section 01 50 00 "Temporary Facilities and Controls". Adhere to park rules, animal deterrent policies, cleanliness policies, and return site to previous condition at completion of work. These requirements also apply to all Contractors’ employees who may, with prior approval, establish their own camping facilities.
H. Hauling Restrictions: Comply with legal load restrictions in hauling of materials. Load restrictions on park roads are identical to state load restrictions with such additional regulations
ACAD 151309B 01 11 00 - 4
as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
1.7 PUBLIC USE OF SITE
A. The area will be closed to the public during construction.
B. Contractor shall conduct his operations to ensure the least inconvenience to public. Road closures may be permitted, when required, upon specific approval of Contracting Officer.
1.8 OCCUPANCY REQUIRMENTS FOR BUILIDINGS
A. Existing Buildings
1. Existing buildings on the McFarland Hill campus will remain in operation and use by
Government staff for the duration of the construction period. Contractor shall minimize disruptions to Government operations at all times.
B. New Buildings
1. Government Occupancy of Completed Areas of Construction: Government reserves right to occupy and to place and install equipment in completed areas of building, provided such occupancy does not interfere with completion of the Work. Such placement of equipment and partial occupancy shall not constitute acceptance of the entire project.
a. Contracting Officer will prepare a Beneficial Occupancy letter for each specific portion of the Work to be occupied before Government occupancy.
b. Obtain a Certificate of Occupancy from National Park Service (NPS) before
Government occupancy.
c. Before partial Government occupancy, mechanical and electrical systems shall be fully operational, and required tests and inspections shall be successfully completed.
On occupancy, Government will operate and maintain mechanical and electrical systems serving occupied portions of building.
d. On occupancy, Government will assume responsibility for maintenance and custodial service for occupied portions of building.
1.9 CONDUCT OF OPERATIONS
A. Contractor shall conduct his operations in conformance with rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by Park Superintendent.
B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed unless stated in the Work Restrictions below or without prior consent from the Contracting Officer. Submit requests 3 business/calendar days in advance of the work to the Contracting Officer for approval.
ACAD 151309B 01 11 00 - 5
C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
1.10 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7:00 a.m. to 04:00 p.m., Monday through Friday, except when otherwise indicated.
1. Weekend Hours: as approved by the Contracting Officer.
2. Early Morning Hours: as approved by the Contracting Officer.
B. Existing Utilities
1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.
2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify Contracting Officer not less than two business days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without Contracting Officer’s written permission.
3. Hours and length of Utility Shutdowns: as approved by the Contracting Officer.
D. Nonsmoking Building/Tobacco Use/Vaping: Smoking is not permitted within all campus buildings or within 25 feet of entrances, operable windows, or outdoor air intakes.
1.11 SPECIAL CONSTRUCTION REQUIREMENTS
A. Project Website: A project website administered by NPS will be used for purposes of managing communication and documents during construction stage.
1. See Section 01 31 00 "Project Management and Coordination" for requirements on using
Project Website.
1.12 SOILS INVESTIGATION REPORT
A. The soils investigation report, prepared by WSP is an appendix with this package:
1. Geotechnical Report for the Proposed Maintenance Facilities and the New
HQ/Administrative Features at McFarland Hill HQ, APPA-151309B, Bar Harbor, Maine;
prepared by WSP, July 2019.
B. In case of conflict between report and drawings or specifications, the drawings and specifications govern.
ACAD 151309B 01 11 00 - 6
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 11 00
ACAD 151309B 01 26 01 - 1
CONTRACT MODIFICATION PROCEDURES
SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. Section consists of administrative and procedural requirements for contract modifications.
1.2 DEFINITIONS AND ALLOWANCES
A. Home Office Overhead: Costs incurred in support of all of a Contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):
1. Rent
2. Utilities
3. Furnishings
4. Office equipment
5. Executive and management staff not exclusively assigned to the project
6. Support, accounting, and administrative staff
7. Preparation of cost proposals, estimating, and schedule analyses connected with
Modifications
8. Estimating and preconstruction services
9. Mortgage costs
10. Real estate and corporate taxes
11. Automobile maintenance and travel costs for home office personnel
12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.
13. Depreciation of equipment and other assets
14. Home office supplies (paper, staples, etc.)
15. Legal services
16. Accounting and data processing
17. Professional fees/registration
B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with preparation of modifications will not be allowed. Costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:
1. Project Manager (PM), Assistant Project Manager
2. Superintendent, Assistant Superintendent
3. Quality Control, Safety Officer, Environmental Manager, etc.
4. Engineers
5. Travel, lodging, and per diem (as established by Federal Travel Regulations)
6. Scheduling
ACAD 151309B 01 26 01 - 2
7. Field Office Trailers and associated temporary utilities
8. Field office supplies
a. Mailing and couriers
b. Reproduction costs
c. Storage
d. Phones
e. Computers
f. Copiers
9. Personal vehicles i.e. Superintendent Pickup trucks
C. General Requirements: Costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate.
The following items, if applicable, are considered allowable costs for calculating General Requirements:
1. Hoisting
2. Material handling
3. Temporary fencing
4. Port-a-lets
5. Trash removal, dumpsters
6. Barricades
7. Small tools
8. Safety supplies
9. Scaffolding
10. Daily cleaning
11. Traffic control
12. Temporary signage
13. Temporary heating and power
D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on project site. Modification costs for salaried workers are only allowed within the structure of a 40-hour week and no overtime or holiday pay will be allowed.
1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:
a. Base Rate: The hourly rate paid directly to the worker
b. Labor Burden: Employer payments of all applicable burdens; includes insurance and taxes the business must pay on behalf of the worker to government entities and educational forums, such as:
1) Social Security
2) Medicare
3) Workers Compensation – Policy and company calculation to be made available.
4) Federal Unemployment Tax Act (FUTA) - Cap Rate and percentage to be proportionally allocated over one year.
5) State Unemployment Tax Act (SUTA) - Cap Rate and percentage to be proportionally allocated over one year.
ACAD 151309B 01 26 01 - 3
6) Union agreement costs - Other costs required under an enforceable collective bargaining agreement.
c. Fringe Benefits: Various non-wage compensations provided to employees such as:
1) Health Care Insurance Premiums
2) Cell Phone
3) Clothing
4) 401K and Pensions
5) Vehicle allowances
6) Gas allowance
7) Life insurance premiums
8) Disability insurance
9) Other Fringe Benefits required under an enforceable collective bargaining agreement
E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.
F. General Liability Insurance: An insurance policy that protects Contractor from claims resulting from bodily injury or property damage to a third party. Include as a separate line item within all modification proposals and provide a current insurance quote upon request.
G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees the Contractor will pay the labor and material costs incurred. Banks and Insurance companies charge a premium for individual project based on a sliding scale related to the size of the project.
Include as a separate line item in modification proposals and provide current company bonding rates upon request.
H. Builder’s Risk Insurance: Covers the contractor’s loss due to fire, high winds, or other natural forces. Not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.
1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS
A. General:
1. Proposal be received in the format and within the time frame specified in the Request for Proposal (RFP) letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.
2. Proposal shall be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Government’s form.
03252022 http://en.wikipedia.org/wiki/Employee http://en.wikipedia.org/wiki/Surety_bond http://en.wikipedia.org/wiki/Insurance http://en.wikipedia.org/wiki/Bank http://www.nps.gov/dscw/publicforms.htm#CP___PAGEID=396735|
ACAD 151309B 01 26 01 - 4
3. Requests for extensions of contract time as a result of change must be justified with a Time Impact Analysis (TIA). Refer to Section 01 32 16 "Construction Schedule", for time impact analysis requirements. TIA and associated costs shall be received with the proposal by the date shown within the Request for Proposal letter. Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving right for additional time and no time extension will be allowed.
4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer (CO) upon request.
5. Contractor shall review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.
6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.
B. Labor:
1. Contractor shall estimate cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing hours required for each craf t directly engaged in modification work. Any work proposed requiring overtime work or premium pay shall be itemized separately. Rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, Federal Insurance Contributions Act (FICA), FUTA, and other direct costs resulting from Federal, State or local laws.
2. Itemize labor costs for equipment operators separate from equipment costs.
3. Labor cost for foremen shall only be costs for related work required for the modification.
C. Materials:
1. Estimated cost for materials shall include quotes from multiple sources. Material prices shall include applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.
2. No markup shall be applied to any material provided by NPS.
D. Equipment:
1. Equipment used for the project must be appropriately sized for work being performed.
2. Do not include costs for "miscellaneous tools and equipment", in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 shall be broken out separately.
3. Regardless of ownership, rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:
a. United States (U.S.) Army Corps of Engineers, Ownership and Operating Expense Schedule (use latest edition and applicable region)
b. Construction Blue Book
c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.
ACAD 151309B 01 26 01 - 5
4. Estimated equipment rates shall include operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires and tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per Federal Acquisition Regulation (FAR) 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.
5. Estimate full rate for equipment only for duration that equipment will be utilized to accomplish work of the modification.
6. Standby unit rates used in accordance with paragraph 1.3, D, 2, above. If the U.S. Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then 1/2 of equipment costs minus any operating costs, major repair and overhaul will be accepted.
7. If equipment is in standby mode due solely to a documented NPS delay, established standby rate shall apply from the first day of the delay.
8. Equipment not used and on job site for up to five consecutive days may be classified at standby rates, provided the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work.
Equipment still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.
9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.
10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.
E. Establishment and Application of Overhead and Profit Percentages:
1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.
Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:
Overhead………………10% Profit………………...…10%
2. Total aggregate limit of markup (OH&P) for Contractor and Subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.
3. If Contractors form a partnership, partnership may only receive home office overhead and profit in same amount as an individual Contractor (refer to paragraph 1.3,E,1 above). It is the responsibility of the partners to decide on division of revenue.
4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, overhead and profit mark-ups are required on net increases and deducted on net decreases.
5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.
ACAD 151309B 01 26 01 - 6
PART 2 - PRODUCTS
PART 3 - EXECUTION
END OF SECTION 012601
ACAD 151309B 01 27 00 - 1
DEFINITION OF CONTRACT LINE ITEMS
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
PART 1 - GENERAL
1.1 SUMMARY
A. Section explains in general, what is and is not included in a contract line item, and limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of work, include costs in a related item.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. Contract Line Item Number 0001 - Sitework.
1. This item consists of all work associated with the new maintenance facility site, including but not limited to the following:
a. Construction of the new septic system
b. Construction of retaining walls
c. Regrading the site
d. Installation of new site utilities, including electric, sanitary, stormwater and tel/com.
e. Site improvements including paved areas and landscaping.
2. Measurement for payment will be on a lump sum basis.
3. Payment will be made at the contract lump sum price.
B. Contract Line Item Number 0002 –Relocation of Existing Structures
1. This item consists of all work associated with removing existing structures within the construction area, including:
a. Relocating the SARS and Fire Vehicle Garages and Trails Shed, including construction of new foundations and associated new utilities.
2. Measurement for payment will be on a lump sum basis.
3. Payment will be made at the contract lump sum price.
C. Contract Line Item Number 0003 – Maintenance Building
1. This item consists of all work associated with construction of the new maintenance building, including foundations, superstructure, exterior envelope, interior construction and finishes, and all associated mechanical, electrical, plumbing, fire protection, fire alarm and telecommunication systems
2. Measurement for payment will be on a lump sum basis.
3. Payment will be made at the contract lump sum price.
ACAD 151309B 01 27 00 - 2
DEFINITION OF CONTRACT LINE ITEMS
D. Contract Line Item Number 0004 – Maintenance Outbuildings
1. This item consists of all work associated with construction of new maintenance facility storage structures, including the following:
a. Covered snow plow storage
b. Battery storage
c. Hazardous materials storage
d. Trails storage
2. Measurement for payment will be on a lump sum basis
3. Payment will be made at the contract lump sum price
E. Contract Line Item Number 0005 – Fueling Station
1. This item consists of all work associated with relocating the existing fueling station, including the following:
a. Construction of a new canopy structure, including foundation and concrete pads, new lighting and fire protection systems
b. Relocation of the existing above grade fuel tank, including new foundation
c. Relocation of existing fuel pumps, including associated monitors and controls.
2. Measurement for payment will be on a lump sum basis
3. Payment will be made at the contract lump sum price.
F. Contract Line Item Number 0006 – Demolition of Existing Maintenance Buildings
1. This item consists of all work associated with demolition of the existing maintenance structures after completion of the new maintenance facility. It includes restoration of the site as indicated.
2. Measurement for payment will be on a lump sum basis
3. Payment will be made at the contract lump sum price.
G. Option A – Relocation of Existing Fueling Station Canopy
1. This item consists of relocation of the existing canopy structure in lieu of providing a new structure (included in CLIN 0005).
2. Measurement for payment will be on a lump sum basis
3. Payment will be made at the contract lump sum price.
END OF SECTION 01 27 00
ACAD 151309B 01 31 00 - 1
PROJECT MANAGEMENT AND COORDINATION
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Definitions
2. Construction Coordination
3. Submittals
4. Coordination Drawings
5. Requests for Information (RFIs)
6. NPS/DSC Project Website
7. Project Meetings
8. Environmental Coordination
9. Permits
B. Related Requirements:
1. Section 01 32 16 "Construction Schedule" for preparing and submitting Contractor’s construction schedule.
2. Section 01 73 40 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Section 01 77 00 "Closeout Procedures" for coordinating closeout of the Contract.
4. Section 01 91 14 "Total Building Commissioning" for coordinating the work with
Government’s Commissioning Authority.
1.2 DEFINITIONS
A. Agency with Jurisdiction B. Construction Permits – Contractor Provided C. Government Furnished Permits
1.3 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
http://www.nps.gov/dscw/definitionsdc_a.htm#awj http://www.nps.gov/dscw/definitionsdc_c.htm#cpcp http://www.nps.gov/dscw/definitionsdc_g.htm#gfperm
ACAD 151309B 01 31 00 - 2
1. Schedule construction operations in sequence required to obtain best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make provisions to accommodate items scheduled for later installation.
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of components, including mechanical and electrical.
5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to:
1. Preparation of Contractor's Construction Schedule
2. Preparation of the Schedule of Values
3. Installation and removal of temporary facilities and controls
4. Delivery and processing of submittals
5. Progress meetings
6. Permit requirements
7. Pre-installation conferences
8. Project closeout activities
9. Commissioning activities
1.4 SUBMITTALS
A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.
1. Content: Project-specific information, drawn accurately to scale. Do not base Coordination Drawings on reproductions of Contract Documents or standard printed data. Include following information, as applicable:
a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.
b. Indicate dimensions shown on Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to Contracting Officer (CO) for resolution of such conflicts.
c. Indicate space requirements for routine maintenance and anticipated replacement of components during the life of the installation.
ACAD 151309B 01 31 00 - 3
d. Show location and size of access doors required for access to concealed dampers, valves, and controls.
e. Indicate required installation sequences.
2. Sheet Size: At least 11 by 17 inches but no larger than 30 by 40 inches.
3. Number of Copies: Submit two opaque copies of each submittal. Contracting Officer will return one copy.
4. Refer to individual Sections for Coordination Drawing requirements for Work in those
Section
B. Coordination Drawing Organization: Organize coordination drawings as follows:
1. Floor Plans and Reflected Ceiling Plans: Show architectural, structural, mechanical, plumbing, fire-protection, fire-alarm, and electrical elements. Show locations of visible ceiling-mounted devices relative to acoustical ceiling grid. Supplement plan drawings with section drawings where required to adequately represent the Work.
2. Plenum Space: Indicate sub-framing for support of ceiling and wall systems, mechanical and electrical equipment, and related Work. Locate components within ceiling plenum to accommodate layout of light fixtures indicated on Drawings. Indicate areas of conflict between light fixtures and other components.
3. Mechanical Rooms: Provide coordination drawings for mechanical rooms showing plans and elevations of mechanical, plumbing, fire-protection, fire-alarm, and electrical equipment.
4. Structural Penetrations: Indicate penetrations and openings required for all disciplines.
5. Slab Edge and Embedded Items: Indicate slab edge locations and sizes and locations of embedded items for metal fabrications, sleeves, anchor bolts, bearing plates, angles, door floor closers, slab depressions for floor finishes, curbs and housekeeping pads, and similar items.
6. Mechanical and Plumbing Work:
a. Sizes and bottom elevations of ductwork, piping, and conduit runs, including insulation, bracing, flanges, and support systems.
b. Dimensions of major components, such as dampers, valves, diffusers, access doors, cleanouts and electrical distribution equipment.
c. Fire-rated enclosures around ductwork.
7. Electrical Work:
a. Runs of vertical and horizontal conduit 1-1/4 inches in diameter and larger.
b. Light fixture, exit light, emergency battery pack, smoke detector, and other fire-alarm locations.
c. Panel board, switch board, switchgear, transformer, busway, generator, and motor control center locations.
d. Location of pull boxes and junction boxes, dimensioned from column center lines.
8. Fire-Protection System:
a. Locations of standpipes, mains piping, branch lines, pipe drops, and sprinkler heads.
9. Review: Contracting Officer will review coordination drawings to confirm Work is being coordinated; details of coordination are Contractor's responsibility. If Contracting Officer
ACAD 151309B 01 31 00 - 4
determines coordination drawings are not prepared in scope or detail, or are otherwise deficient, Contracting Officer will inform Contractor, who shall make changes and resubmit.
10. Coordination Drawing Prints: Prepare coordination drawing prints according to requirements in Section 01 33 23 "Submittal Procedures."
C. Coordination Digital Data Files: Prepare coordination digital data files according to:
1. File Preparation Format: Same digital data software program, version, and operating system as original Drawings.
2. Contracting Officer will furnish Contractor one set of digital data files (Revit. RVT) of Drawings for use in preparing coordination digital data files.
a. Contracting Officer makes no representations as to accuracy or completeness of digital data files as they relate to Drawings.
b. Digital Data Software Program: Drawings are available in RVT.
D. Division 1 documents: The following items shall be submitted a minimum of one week prior to Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for Pre- Construction Conference.
1. Letter designating Project Superintendent
2. Construction Schedule
3. A Comprehensive Schedule of Values
4. Accident Prevention Plan
5. A List of Subcontractors for this project
6. Written statements from Subcontractors certifying compliance with applicable labor standard clauses.
7. Certificates of Insurance or SF1413 for Contactor and all Subcontractors
8. Waste Management Plan
9. Quality Control Plan
10. Temporary Storm Water Pollution Prevention Plan (SWPP or UPPP)
11. Indoor Air Quality (IAQ) Management Plan
12. Contractors Commissioning Plan
13. Historic Preservation Treatment Plan (HPTP)
14. List of Required Construction Permits. Include the following information for each permit:
a. Name of Permit
b. Agency(ies) with Jurisdiction issuing the permit
c. Information required from Government to complete permit application
E. Provide items listed to Contracting Officer before Pre-Construction Conference. If all documents have not been received one week prior to scheduled Pre-Construction Conference date, conference may be cancelled, Notice to Proceed may not be issued, and Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.
ACAD 151309B 01 31 00 - 5
1.5 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of Contract Documents, Contractor shall prepare and submit an RFI utilizing form created on NPS/DSC management software website.
1. Contracting Officer will not respond to RFIs submitted by other entities controlled by Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. Content of RFI: Include detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially
2. Date
3. RFI subject
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Field dimensions and conditions, as appropriate.
7. Contractor's suggested resolution: If Contractor's suggested resolution impacts Contract
Time or Contract Sum, Contractor shall state impact in RFI.
8. Contractor's signature
9. Requested date for response
10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .