CONFERENCE
RECORD
Purpose of
Contact
To Review Applicable Electrical Utility Requirements
Project Name
Scotts Bluff Visitor Center Remodel
Project # 3039.00
Prepared By Kit Davidson, Melina Moser
Date 3/27/2017
Present
Jennifer Heimbouch Office Supervisor Roosevelt Public Power District jheimbouch@rooseveltppd.com
(308) 635-2424
AE Design contacted the local electrical utility to review the requirements for the above referenced project. Following is a summary of the items that were discussed:
The following building characteristics were reviewed with the utility company:
Project Address 190276 Old Oregon Trail Rd Gering, NE 69341
Building Size 9,650 SF
Anticipated Building Use Visitors Center/Museum
Anticipated NEC Calculated Load 225kVA
Requested voltage and phase 208V/3-Phase
The following is a list of items provided by the utility company, confirmed via email 3/23/2017 from Jennifer.
1) We will provide the meter and everything on the primary side, you will need to provide secondary wiring out of the pad mount transformer.
2) We will be using the cement pad that is existing.
3) The transformer size will be the 3 phase, 208/120, 225kva that was in the quote that was sent to you, we can provide the fault current after we have purchased the transformer.
4) There are no forms that need to be submitted, but payment is due before we stake the job and purchase the material needed to complete the job.
5) The existing feeders will be fine for the new transformer; we will not have to pull anything new.
Quote is attached for reference.