PPT_Pre-Proposal_Slidessamples.ppt

PPT presentation 440 KB Posted

Attached to
Replace / Relocate Unsafe / Unhealthy / Unsustainable Visitor Center
Solicitation number
140P2018R0001
Issued by

About this file

Power Point Presentation

View the file

Other files

File Type Posted
Amendment_No._6_SF_30.pdf PDF
Final_Geotechnical_Design_Report4rev.pdf PDF
Amendment_No._6_-_Revised_Report.pdf PDF
Geotechnical_Investigation_Proposed_Trailhead_Visitor_Center_Timpanog_Jan_2011.pdf PDF
Timpanogos_Cave_National_Monument,_Rockfall_Mitigation_Measures_July_2013.pdf PDF
Amendment_No._5_-_Responses_to_Questions_Received.pdf PDF
Additional_Geotechnical_Investigation_Report,_Timpanogos_Aug_2016.pdf PDF
Amendment_No._5_SF_30.pdf PDF
Geotechnical_Design_Report_Rockfall_Mitigation_Project_Timpanogos_Feb_2016.pdf PDF
Amendment_No._4_SF_30.pdf PDF
Amendment_No._4_-_Responses_to_Questions_Received.pdf PDF
Amendment_3.pdf PDF
TICA_Prebid_Sign-in_Sheet.pdf PDF
Questions_Received_for_Timpanogos_Cave_1.pdf PDF
SF30_Amendment_2.pdf PDF
E09_Prebid_SignIn.doc DOC document
Amendment__1_TICA.pdf PDF
B08_Solit_PSP_Vol_I_PastPerf_REQD.docx DOCX document
B03_DOL_Wage_Deter_UT108.pdf PDF
TICA_152836_-_FINAL_ContractPriceSchedule_BLANK.xls XLS spreadsheet
A06_Specs-Dwgs_1._TICA_152836_04-27-17_Drawings_Combined_Part1.pdf PDF
A06_Specs-Dwgs_1._TICA_152836_04-27-17_Drawings_Combined_Part4.pdf PDF
RFP_VOL_1_pkg.pdf PDF
A06_Specs-Dwgs_1._TICA_152836_04-27-17_Drawings_Combined_Part2.pdf PDF
A06_Dwgs_Specs_2A._TICA_152836_-_Specifications_Volume_1_-_4-28-17.pdf PDF
A06_Dwgs_Specs_2B._TICA_152836_-_Specifications_Volume_2_-_4-28-17.pdf PDF
A06_Specs-Dwgs_1._TICA_152836_04-27-17_Drawings_Combined_Part3.pdf PDF
B03_DOL_Wage_Deter_UT68.pdf PDF
RFP_VOL_2.pdf PDF
B08_Solit_PSP_Vol_II_SBSubKCalc.xlsx XLSX spreadsheet
B08_Solit_SF_1442_and_clauses.pdf PDF
B03_DOL_Wage_Deter_UT30.pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REPLACE/RELOCATE UNSAFE/UNHEALTHY/

UNSUSTAINABLE VISITOR CENTER

TIMPANOGOS CAVE NATIONAL MONUMENT

Pre-Proposal Conference

APRIL 26TH, 2018

Timpanogos Cave National Monument

INTRODUCTION

Philip Lawrence – Project Manager Dane Johnson – Contracting Officer Daniel Fleming – Project Specialist Joy Ewalt – Contract Specialist

SYNOPSIS

Construct a 2400 SF Visitor Center
Utility Extensions and Site Work
A Federal Hwy’s Project realigning Utah Hwy 92
Rock Fall Hazard Mitigation
Visitor Center will be Energy Efficient – Will meet LEED Silver Design Goals
The contract will be awarded using Source Selection procedures
Evaluation factors - Price , Technical, &Past Performance

SOLICITATION, PLANS

& SPECIFICATIONS

SOLICITATION # 140P2018R0001
Are available for downloading on

FedBizOpps at fbo.gov

Solicitation
Plans & specifications

--Amendments

IFB VERSUS RFP

In the invitation for bid (IFB), FAR Part 14, process, a public bid opening occurs when the bids are due and the prices are read to the public
There can be no discussion
No correction of mistakes in most cases
Award is always to the low responsible bidder

IFB VERSUS RFP

In the Request for Proposal (RFP), FAR PART 15, process

After closing, the process is “closed” - information will be not be available until time of award
Only Awardee identity and price is disclosed-not other offerors or their prices
The Government will award based on best value criteria
There can be clarification, and/or discussions
Award may not always be to the lowest offered price

WHAT IS THE CONTRACT PERIOD?

Construction period is 270 calendar days after receiving the Notice to Proceed

DISCLAIMER

The following is a brief overview of the proposal requirements OFFERORS ARE STRONGLY CAUTIONED TO CAREFULLY READ THE REQUIREMENTS OF THE SOLICITATION AND COMPLY ACCORDINGLY

IMPORTANT REMINDER

THE GOVERNMENT INTENDS TO AWARD WITHOUT DISCUSSIONS, THUS THERE MAY NOT BE A CHANCE FOR DISCUSSIONS, CORRECTIONS, OR REVISED PROPOSALS!!

WHAT YOU MUST SUBMIT

Section L of the RFP details the required information and format for the proposal
3 Volumes are required plus 1 flash drive for a total of (4)
VOL 1 – Technical/Past Performance
VOL 2 – Business/Price

VOLUME 2

BUSINESS/PRICE

Offeror portion of SF1442
Section B – Insert all required pricing
Section K - Complete and insert representations and certifications (return those in Section K)
Complete Electronic Representations and Certifications in System Awards Management – website SAM.gov
Subcontracting Plan if required (large business only)
Include the Supplemental information form

VOLUME 1

TECHNICAL/PAST PERFORMANCE

NO PRICES/COSTS IN THIS VOLUME

Provide 3 to 5 Relevant Projects completed in the last five years
Past Performance Questionnaires for relevant contracts completed in the last five years. (Complete A PART B)
Send out questionnaires to your references for the Relevant projects.
DO this early – make sure they are sent to contracting officer prior to the closing date of the solicitation

VOLUME 1

TECHNICAL/PAST PERFORMANCE, CONT’D

Review Section L closely. Instructions on what to submit for evaluation.
Review Section M closely. How we’re going to evaluate what you submit.

PROPOSAL DUE DATES

Proposal Due Date is May 16, 2018. This date is firm, and will not be extended. This is due to construction season constraints
Proposal must be signed by officer of your company
No facsimile or electronic offers will be accepted.
Reference questionnaires are also due by this time and date
Send reference questionnaires out as soon as possible
These can be sent to us via mail or e-mail

PROPOSAL

EVALUATION

Process is detailed in RFP Section M
Carefully review Section M when preparing proposal
Comply with Section L requirements
Technical/Past Performance is approximately equal to Price
Failure to furnish a complete proposal may result in elimination from consideration !!

BEST VALUE AWARD DECISION

Best Value is defined as an award based on the greatest overall benefit in response to the requirement. Award is based on price and other non-price/cost related factors.

AWARD

The contractor whose proposal provides the BEST VALUE to the Government.

TECHNICAL/PAST PERFORMANCE IS APPROXIMATELY EQUAL TO PRICE

THE BEST VALUE MAY NOT BE THE LOWEST PRICE

IMPORTANT REMINDERS

Submit a complete proposal in accordance with Instructions Award without discussions is intended, so you may not have an opportunity to revise/correct Award in this process does not necessarily mean the lowest price wins

HELPFUL WEBSITES

http://www.fbo.gov
http://sam.gov
https://www.wdol.gov/dba.aspx

HOW QUESTIONS WILL BE HANDLED

Questions must be submitted in writing only via email to: joy_ewalt@nps.gov or dane_johnson@nps. gov
Submit questions NLT COB May 11, 2018
Questions received after May 11, 2018 may be held and addressed after RFP closing with those offerors determined to be in the competitive range if discussions are deemed necessary
DO NOT CALL TECHNICAL PERSONNEL OR A&E- THIS WILL DELAY GETTING AN ANSWER

ANSWERS TO QUESTIONS

All questions, should be in writing, and sent electronically to joy_ewalt@nps.gov or dane_johnson@nps.gov the official Government responses will be in an amendment to the solicitation on fbo.gov.
All addendums, issued by an amendment, will be posted to fbo.gov
Check web site regularly and don’t forget to refresh web page!!

Questions ???

Site Visit Follows This Briefing

File details come from the government source that posted it.