B08_Att12_140L0626R0003_-_Q_A_Partial_Response_0002.xlsx

XLSX spreadsheet 36 KB Posted

Attached to
NIFC Building 415 Replacement
Solicitation number
140L0626R0003
Issued by

About this file

This file is a Questions and Answers (Q&A) document for federal solicitation 140L0626R0003, the NIFC Building 415 Replacement project issued by the Department of the Interior Bureau of Land Management Idaho Region. The document addresses 105 inquiries from potential bidders regarding the scope, specifications, and technical requirements for the construction and demolition work.

The project involves the replacement of Building 415 at the National Interagency Fire Center (NIFC) with two phases: construction of new Building 320-SGE and subsequent demolition of Building 415-MNT with restoration to parking. Key scope items include structural steel framing, mechanical systems (HVAC, dust collection, fume hoods), plumbing and domestic hot water systems, fire protection and alarm systems, electrical distribution with metering integration into the campus Schneider Power Monitoring System, physical access control systems (AMAG panels and card readers), CCTV cabling infrastructure, communications and low-voltage systems, compressed air systems, and associated site work. Critical clarifications address delegated design requirements for metal storage shelving and dust collection systems; refrigerant recovery for existing HVAC equipment; salvage and waste management procedures during demolition; fire pump testing discharge locations; integration of new building systems into existing Johnson Controls Metasys and campus IT networks; utility connections including Veolia-approved water service contractors; temporary facility staging and laydown areas; and staffing expectations for superintendent, safety, and quality control personnel. The government confirmed that past performance questionnaires are no longer required, cameras and wireless access points are government-provided, and specification sections govern over named manufacturer references when equivalent products meet stated requirements.

View the file

Other files

File Type Posted
B08_Att22_NIFC_415_MNT_Bid_Clarification_Questions_-_B_0004.pdf PDF
Sol_140L0626R0003_Amd_0004.pdf PDF
B08_Att21_NIFC_415_MNT_Bid_Clarification_Questions_-_A_0004.pdf PDF
B08_Att16_NIFC_415_Revised_Drawings_0003.pdf PDF
B08_Att14_140L0626R0003_CP_REV_0003.pdf PDF
Sol_140L0626R0003_Amd_0003.pdf PDF
B08_Att15_NIFC_415_Amendment_Detailed_0003.pdf PDF
B08_Att20_NIFC_415_Q_A_0003.xlsx XLSX spreadsheet
B08_Att17_NIFC_415_Specifications_320_SGE_0003.pdf PDF
B08_Att19_NIFC_415_Furniture_Plan_0003.pdf PDF
B08_Att18_NIFC_415_Specifications_415_MNT_0003.pdf PDF
B08_Att13_SV_Sign-In_Sheet_140L0626R0003_0002.pdf PDF
Sol_140L0626R0003_Amd_0002.pdf PDF
Sol_140L0626R0003_Amd_0001.pdf PDF
JOFOC_Brand_Name_AMAG_Signed.pdf PDF
B08_Att6_26R0003_Wage_Determination_ID20260104.pdf PDF
JOFOC_Brand_Name_JCI_Signed.pdf PDF
B08_Att7_26R0003_RFI_Form.xlsx XLSX spreadsheet
B08_Att4_26R0003_NIFC_415-_Duane_Graves__IFC_Specifications_320_SGE.pdf PDF
B08_Att8_26R0003_-_Lim_on_SubK_Breakout.xlsx XLSX spreadsheet
Sol_140L0626R0003.pdf PDF
B08_Att9_26R0003_NIFC_Campus_Map.pdf PDF
B08_Att5_26R0003_NIFC_415-MNT_Replace_-_Bid_Schedule.pdf PDF
B08_Att2_26R0003_NIFC_415_Duane_Graves_NIFC_320-SGE_IFC_Drawings.pdf PDF
B08_Att1_26R0003_NIFC_415_Duane_Graves_IFC__Drawings_415_MNT.pdf PDF
B08_Att3_26R0003_NIFC_415_Duane_Graves__IFC_Specifications_415_MNT.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

United States Department of the Interior
Solicitation:140L0626R0003
Title:GAOA NIFC 415 Duane Graves Replacement
Questions and Answers
Inquiry numberSolicitation / Drawing / Spec / OtherSection/ Sheet/ PageQuestionGovernment ResponseFor LBYD?
1Are past performance questionnaires required for the Past Performance Factor Evaluation.NO, PPQ's are no longer required. Please see the revised continuation pages for additional detail on the requirements.
2102600Spec 102600 Calls out using CG1 Inpro corner guards and does not mention CG6. It also does not mention the sheet wall protection. On sheet IN-601 the Materials List calls out CG1/CG6 as Construction Specialties VA Series corner guards, and WP1 Construction Specialties Acrovyn sheet wall protection. Which information should we use in our bid for this projectY
3For a distributor of Larsen's/Amerex fire extinguisher cabinets and fire extinguishers. May we submit a substitution request for the equivalent FE Cabinets from Larsen's?No substitution request necessary. Per the applicable specification section, manufacturers are not limited to the names listed if meeting the requirements.
4101423.16Spec SECTION 101423.16 - ROOM-IDENTIFICATION PANEL SIGNAGE: Is the UFC Standards for 2025 acceptable for these items, as displayed in the attachment? If not please provide clarifying information and a rendering/picture to assist in quoting the correct design?Room signage will be based on Architectural Barriers Act Requirements, not UFC Standards. See Amendment for detail.
5Sheet CD101Existing 415-MNT water meter removal and capping limits. Sheet CD101 Keynote 13 states to remove the water meter on service, abandon service, and cap the line at both ends. Please clarify the exact limits of this work and whether the abandoned water service is to remain in place after capping or be removed where it conflicts with new paving, grading, or utilities.Y
6Sheet CD101Existing sanitary sewer service serving 410C and 420. Sheet CD101 Keynote 10 states to cut and cap the sanitary sewer service from the existing 415-MNT building while retaining sanitary sewer service from 410C and 420. Please clarify the exact cap location and whether any temporary bypass, rerouting, or utility protection is required to maintain service to 410C and 420 during demolition.Y
7Sheet CD101Existing electrical feed to transformer north of 410C. Sheet CD101 Keynote 9 states to cut and remove electrical feeds to the existing 415-MNT building, including the feed to the transformer north of the 410C building. Please clarify whether this transformer serves any active campus loads and whether temporary power, rerouting, or other coordination is required to keep adjacent buildings operational.Y
8Existing communication conduit and cable removal. The demolition drawings call for removing communication cables back to the nearest source or junction box and abandoning conduit below grade. Please identify which communications cabling is active, which source or junction boxes are to remain, and whether NIFC/BLM IT must disconnect or verify any cabling before removalY
9Sheet CD101, 102, 103Existing 415-MNT dust collection and welding fume systems. Sheets CD101, CD102, and CD103 note that the existing 415-MNT building includes dust collection and welding fume collection systems. Please clarify whether these systems are to be completely demolished and disposed of, salvaged for Government use, or handled with any special disposal or cleaning requirements before demolition.Y
1024116Salvage items in 415-MNT demolition
Specification Section 024116 states that salvaged items are to be inventoried, cleaned, packed/crated, stored, transported, and protected, and also states that items to be salvaged are indicated on the drawings. We did not identify a clear salvage list for the 415-MNT demolition. Please provide a list of all items to be salvaged and returned to the Government, including any equipment, doors, hardware, electrical components, mechanical equipment, or shop equipment.Y
11Refrigerant recovery for existing HVAC equipment
The 415-MNT demolition specifications require refrigerant removal from mechanical equipment before demolition. The drawings note split HVAC units and two rooftop package HVAC units. Please confirm whether refrigerant recovery is included in the Contractor’s demolition scope or will be completed by the Government before demolition starts.Follow demolition specification sections 017419 and 024116 for refrigerant recovery by the contractor.
12Hazardous Materials / Asbestos Survey Report

The demolition specifications state that hazardous materials are not expected and that hazardous materials will be removed by the Government before the work. Please confirm whether an asbestos/hazardous materials survey has been completed for the existing 415-MNT building and provide the report to bidders. If no report is available, please clarify how bidders should account for potential asbestos-containing materials or other hazardous materials encountered during demolition.

An asbestos survey report is not available for the building, since the building was not identified as having asbestos due to the building age. Follow the demolition specifications for bidding. A hazardous materials sign has been in place indicating that the insulation in the building includes Polyisocyanurate insulation. This is marked as a warning for occupants involved in spark generating operations since that insulation type is flammable.
13233500New dust collection system / Bid Item 44
The bid schedule includes a separate Bid Item 44 for Dust Collection, while the specifications include Section 233500 Dust Collection System and the mechanical drawings include dust collector controls. Please clarify whether Bid Item 44 is intended to include the complete dust collection system, including equipment, ductwork, controls, fire alarm shutdown interface, startup, testing, and connections to Government-furnished shop equipment.Bid Item 44 includes only the items included in specification section 233500.
14Architectural sheets state that shop equipment is Government-furnished and installed, with reference to Q-101. Q-101 lists several Government-furnished and installed equipment items, including metal bandsaw, belt sander, drill press, pipe threader, laser cutter, ice machine, and other shop equipment. Please clarify whether the Contractor should include final utility rough-ins, duct connections, electrical connections, dust collection connections, compressed air connections, or anchoring for Government-furnished equipment.Final utility rough-ins, duct connections, electrical connections, dust collection connections, compressed air connections are by government unless otherwise indicated in the construction set. Coordinate between Equipment, Plumbing, Mechanical, and Electrical sheets for connections.
15The mechanical controls sequence requires the dust collector fan and welding fume hood fan to shut down automatically upon fire alarm trigger/alarm. Please clarify the complete Contractor scope required for shutdown relays, control wiring, interface devices, programming, and final functional testing for these shutdown functions.Y
16233816The specifications include Section 233816 Fume Hoods, and the mechanical control notes include welding fume hood controls. Please clarify whether the welding fume hood system is intended to be included under HVAC, Dust Collection Bid Item 44, or another bid item, and confirm the required scope for equipment, ductwork, controls, startup, and fire alarm shutdown interface.Specifications 233816 is intended under bid item 23 for HVAC.
17The mechanical controls sequence requires a controls system with a Johnson Controls-compatible access point for remote monitoring and control of HVAC system status and temperature setpoints. Please clarify whether the Contractor should include full integration into the existing NIFC Johnson Controls system, including network connection, programming, graphics, trend logs, and final commissioning support.Follow specification 230900 and M-604 to M-606 which indicates full integration into the NIFC Johnson Controls system.
18262713Specification Section 262713 includes Government electricity meters, metering infrastructure components, metering software, network protocols, data communication paths, and compatibility with monitoring/control devices. Please clarify whether the Contractor should include integration of the new electrical metering into the existing NIFC monitoring system, including network cabling, programming, software setup, and Government system coordination.See 320-SGE plan sheet E-701 key note 1Y [Change spec to be contractor provided instead of utility provided]
19The telecommunications drawings call for new card reader AMAG panels in Comm Room 1010 and state that card-access-controlled doors must incorporate ISC requirements. Please clarify whether the Contractor should include furnishing, installing, programming, and commissioning the AMAG panels, card readers, power supplies, door contacts, request-to-exit devices, electrified hardware interfaces, and final tie-in to the existing campus access control system, or if any portion will be completed by NIFC security/IT.Y [Add PACS specification section]
20The telecommunications drawings state that overhead doors shall include safety sensors, operators with remote control functionality, and open/close sensors tied to the campus physical access control system. Please clarify the complete scope required for open/close sensors, operator interface, wiring, programming, and final tie-in to the campus physical access control systemSee spec 083613.2.3.NY [Add PACS specification section]
21The drawings state that UAV Storage Room 1603 shall have an additional open Wi-Fi network on a different system and clearly labeled. Please clarify whether the Contractor should include the access point, cabling, network equipment, labeling, programming, and coordination with NIFC IT, or only the rough-in/cabling.The government Wireless Access Point will be government provided.Y
22The electrical drawings state that the fire alarm contractor shall finalize locations, sizes, and specifications for notification devices. Please clarify whether the bid documents are intended to be performance-based for fire alarm notification device layout, and whether the bid should include final design, calculations, permitting, and any additional devices needed for code-compliant coverage.See E-105 and specification 2831000 for fire alarm design requirements.
23G-100Sheet G-100 lists 2021 IBC, 2021 IFC, 2022 NFPA 13, 2020 NEC, and 2022 NFPA 72 as governing codes. Please confirm that these are the code editions to be used for fire protection, fire alarm, electrical, and permitting. If any specification section references a different edition, please clarify which code edition governs for bidding.The newest and most stringent code editions listed in the plans and specifications governs the project.
24The fire pump specification requires the Contractor to furnish hoses for fire pump acceptance testing long enough to reach a storm drain or other acceptable discharge location. Please identify the approved discharge location for fire pump test water so bidders can include the correct hose length, routing, and water management requirements.See plan sheet V-101 for SSMH sanitary manhole locations that can be used as a discharge location.
25The fire pump specification requires fire pump controller connections to the building fire alarm system for motor running, loss of power, and phase reversal conditions. Please clarify the complete scope required for interface modules, monitoring points, control wiring, programming, and final fire alarm testing for the fire pump controller.Y
26113013Section 113013 includes residential appliances, including microwave and refrigeration appliances, with product data, warranty, and O&M requirements. Please confirm whether all appliances in this section are Contractor-furnished and Contractor-installed, and whether they should be carried under Bid Item 12 Furnishings.Correct. Group appliances under bid item 12 Furnishings.
27Architectural details show mechanical louvers with bird screens, flashing, air barrier tie-in, and sealant requirements, while the louvers are referenced back to the mechanical drawings. Please clarify the required furnishing, installation, flashing, sealant, and air-barrier tie-in scope for mechanical louvers.Coordinate between Architectural and Mechanical, see plan M-503.Y
28320-SGEThe 320-SGE specifications list Bid Item 6 as “Wood, Plastics, and Composites,” but the description states that it includes “all work related concrete.” Please confirm that Bid Item 6 is intended to include Division 06 Wood, Plastics, and Composites work, not concrete work.Correct, Bid Item 6 is for Wood Plastics and Composites, and concrete is included in Bid Item #3
29The demolition specification states to demolish foundation walls and below-grade construction within the footprint of new construction and extending 5 feet outside the footprint. The 415-MNT demolition scope appears to restore the footprint to a parking area, not construct a new building in that same footprint. Please clarify the required depth and extent of foundation, slab, footing, and below-grade construction removal for the 415-MNT demolition area.New construction and footprint in the 415-MNT demolition scope indicates the area of new asphalt parking surface.
30415-MNTThe 415-MNT demolition scope requires restoration of the building footprint to a usable parking area, with asphalt paving and striping. Please confirm the required pavement section for the full demolished building footprint and whether any unsuitable subgrade, existing foundation voids, or abandoned utilities below the paving area require removal/replacement beyond the typical asphalt detail.Y
31C-102Sheet C-102 for 415-MNT calls for replacing a solid lid with a grate at an existing catch basin. Please clarify the required grate type, loading rating, frame modification requirements, and whether any adjustment to rim elevation or drainage structure is required beyond replacing the lid.Y
32220593Specification Section 220593 requires an additional TAB within 90 days of completing TAB to verify balanced conditions are being maintained and correct unusual conditions. Please confirm whether the Contractor is required to include this 90-day return visit in the base bid and whether it applies to plumbing only, HVAC only, or both plumbing and HVAC systems.Specification 220593 is required and part of division 22 for HVAC, separate specification sections are listed for Plumbing TAB and HVAC TAB.
33E-106Sheet E-106 shows a Nexus RF receiver in Comm Room 1010, and the luminaire schedule lists emergency lights and exit signs with wireless Nexus RF reporting compatible with the existing Nexus wireless system in operation at NIFC. Please clarify whether the Contractor should include furnishing, programming, connecting, testing, and obtaining final acceptance of the Nexus RF receiver and wireless reporting through the existing NIFC Nexus system, including any required web application setup, access credentials, and coordination with NIFC staff.Yes per sheet E-106 and E-401.Y [Update spec with Nexus RF requirements]
34E-701Sheet E-701 Keynote 1 states that the Contractor shall provide a Square-D Power Logic PM5500 meter, provide Cat6 to the IT Room, commission and program the meter into the central campus Schneider Power Monitoring System, include the building electrical single-line image, and update the campus map to reflect the new building location. Section 262713 also requires metering software, data communication paths, network protocols, compatibility with monitoring/control systems, field testing, and software/firmware support. Please clarify whether NIFC/BLM will provide the required network port, IP information, Schneider system access, software credentials, existing campus map files, and programming support, or if the Contractor should include all items necessary for complete integration and final acceptance.Follow sheet E-701 keynote 1 and 262713. Provide network connection. Coordinate network port, IP information, schneider system access with NIFC campus IT.
35The plumbing/TAB requirements reference verifying hot-water circulating pump operation, but the control sequence for the domestic hot-water circulating pump is not clearly identified in the documents reviewed. Please clarify the intended control sequence for the domestic hot-water circulating pump, including whether it is to operate continuously, by aquastat, timer, BAS command, or another control method, and what control components should be included in the base bid.Y
36P-403Sheet P-403 shows domestic water equipment in the mechanical/fire pump area, including BFP-1 and WM-1, and notes the building riser is to be reduced to 2 inches after the riser to accommodate the 2-inch strainer, backflow preventer, and water meter. Please clarify whether the domestic water meter is Contractor-furnished or utility/Government-furnished, and identify the final installation and inspection requirements to be included in the bid.Utility provides a water meter at the connection point, contractor provides a water meter in the fire pump room.Y
37The fire protection drawings show an 8-inch fire service entrance, 8-inch double check backflow preventer assembly, fire pump, jockey pump, FDC, test header, main test and drain, and related valves/switches. We did not identify a separate fire-service water meter shown at the fire riser/fire pump room. Please confirm whether a fire-service water meter is required for this project, and if so, provide the required meter size, location, furnishing requirements, and utility/Government coordination requirements.Follow C-104, coordinate with water utility (Veolia) requirements. No fire service meter required.
38FP-302FP302 shows multiple tamper switches, flow switch, fire pump controller, jockey pump controller, and horn/strobe coordination. Please clarify the complete monitoring scope required for waterflow, tamper switches, fire pump running, loss of power, phase reversal, and related fire pump/riser supervisory points.Y
39211313Section 211313 requires pressure gauges at waterflow alarm switch locations, risers/feed mains, sprinkler test connections, backflow assemblies, and main drain connections, along with pressure relief valves and automatic air vents. Please confirm whether all listed devices are required even where not individually shown on the drawings, and whether any additional Government-required devices must be included beyond NFPA 13 minimum requirements.Provide devices per NFPA 13 minimum requirements or as shown on drawings, whichever is more stringent.
40233500The bid schedule includes a separate Bid Item 44 for Dust Collection, while the mechanical drawings and Section 233500 include dust collector equipment, ductwork, cyclone air lock, controls, blast gates, equipment connections, fire alarm shutdown, and compressed air connection requirements. Please clarify whether Bid Item 44 is intended to include the complete dust collection system, including all equipment, ductwork, air lock valve, blast gates, controls, electrical connections, compressed air connections, startup/testing, and fire alarm shutdown interface.Bid Item 44 includes only the items included in specification section 233500.
41The mechanical drawings state that the dust collection ducting system is sized based on the shop equipment layout shown on the architectural drawings, and that the Contractor must verify the installed shop equipment layout before ordering and installing the dust collection system. However, the architectural drawings state that shop equipment is Government-provided and installed. Please clarify when the final shop equipment layout will be available and whether the bid should include modifications to the dust collection ductwork if the Government-furnished equipment layout changes after bid.Shop equipment layout shown on sheet Q-101 and M-403 is the layout required for the dust collection system.
42The drawings indicate upper and lower dust collection connections for the table saw and bandsaw and require adapters for the indicated woodworking tool connection points. Please clarify whether the bid should include dust collection ductwork only to the equipment connection points, or whether all final adapters, flexible connections, blast gates, supports, and connection modifications required for the actual Government-furnished equipment should be included.Provide all necessary equipment connection points as shown in M-403.
43233500The mechanical drawings require an air lock butterfly valve in the dust collection ductwork and state it must be connected to a compressed air line branch in the room. Section 233500 specifies a duct air lock valve, dust accumulation sensor kit, air pulse cleaning, 120V electrical connection, controls, panels, and electrical boxes. Please clarify the complete scope to be included for the compressed air branch, 120V power, controls, panels, sensor wiring, and final startup of the air lock valve assembly.Coordinate between electrical and mechanical for all necessary connections, information is included in plans, compressed air, mechanical, and electrical sheets, and in specification 233500.
44233500Section 233500 requires delegated duct design and compliance with ACGIH, SMACNA, seismic bracing, and dust collection performance requirements. The drawings also state that DCS-1 is rated to operate from 1300 to 1500 CFM and that duct velocities must maintain minimum vertical and horizontal speeds for wood dust entrainment. Please clarify whether the Contractor is required to provide engineered/delegated design calculations confirming CFM, duct velocity, static pressure, and equipment performance for the final installed shop equipment layout.Follow specification 233500.
45233500Section 233500 specifies an air lock valve with a design basis of Fike Dual-Flap Explosion Isolation valve and NFPA 69 certification. Please clarify whether the dust collection system requires a complete combustible dust hazard analysis, explosion protection/isolation design, or additional NFPA 652/NFPA 664 compliance documentation beyond the listed air lock valve requirement.Section 233500 indicates the submittal requirements, system shall have a explosion protection design.
46233500Section 233500 describes a dust collector with motor/blower and HEPA filtration, while the drawings identify dust collection routing and equipment connections. Please clarify whether the dust collector discharge is intended to recirculate into the building, discharge outdoors, or connect to another exhaust path, and provide any required discharge location, clearances, filtration requirements, or make-up air requirements.See detail A1/M-301, M-403, and schedule M-602.
47E-104Sheets E-104, E-104A, and E-104B state to run new CCTV camera cabling to Comm Room 1010, including Cat6A PoE cabling to exterior-rated junction boxes for PTZ and fixed-focus cameras. Please clarify whether the cameras themselves are Contractor-furnished and installed, Government-furnished and Contractor-installed, or Government-furnished and Government-installed. Also clarify whether the bid should include final terminations, camera mounting, programming, aiming, labeling, and connection to the existing NIFC camera system.Cameras are government provided, installed, and connected at a future date. Contractor provides the junction box, covers, cabling, and labeling to future connection.
48E-104Sheets E-104, E-104A, and E-104B state that new card reader AMAG panels are to be located in Comm Room 1010, and that card-access-controlled doors are to incorporate ISC requirements. Please clarify whether the bid should include furnishing, installing, programming, and commissioning the AMAG panels, card readers, power supplies, door contacts, request-to-exit devices, electrified hardware interfaces, and final tie-in to the existing campus access control system, or if any portion will be completed by NIFC security/IT.Physical Access Control System (PACS) installed by contractor, coordinate programming with NIFC security.
49The hollow metal door specifications require coordination of door hardware, electrified door hardware, access control, and security systems, and require door/frame shop drawings to show electrical raceways and preparations for electrified hardware, access control systems, and security systems. Please clarify the required scope for final coordination drawings, raceways, power supplies, terminations, and functional testing for each access-controlled opening.Y
50Because the drawings require AMAG panels, CCTV cabling, card-reader-controlled doors, and overhead door open/close sensors tied into the campus physical access control system, please clarify whether the Government will provide system access, programming credentials, IP/network information, existing system standards, and NIFC security/IT support for final integration and acceptance.Y
51283100Section 283100 states that the fire alarm system is to unlock electric door locks in designated egress paths. Please clarify which access-controlled doors are designated to unlock on fire alarm, and identify the relays, wiring, programming, and final testing requirements that should be included in the bid.See designated egress on G-101, locks are operable on exit passage side.Y
52P-601Sheet P-601 lists P-1 as a domestic hot-water recirculation pump, 115V, 1 phase, 0.03 HP, 15A, and notes “provide with hot water control module.” Sheet P-403 shows P-1 in the mechanical/restroom domestic water area. Please clarify whether the bid should include electrical power, disconnecting means, control wiring, and the hot-water control module for P-1, and identify the intended circuit/panel if already assigned.
Y
53P-601Sheet P-601 lists WH-1 as a 208V, 1 phase heat pump water heater and WH-2 as a 120V, 1 phase electric water heater. Section 223300 also requires shop drawings to include power, signal, and control wiring diagrams. Please clarify the complete scope required for power wiring, disconnects, controls, and low-voltage/control wiring for WH-1 and WH-2, and identify the intended electrical circuit/panel locations if already assigned.See electrical plansY [Show recirc]
54P-601Sheet P-601 lists LAV-1 as requiring electricity and notes touchless automatic faucets. Please clarify whether the touchless lavatory faucets are battery-powered, hardwired, plug-in transformer powered, or provided with another power method, and identify the required power supplies/transformers to be included in the bid.See electrical plansY [Coordinate specs and plans for hardwired lav, manual flushometers]
55P-601Sheet P-601 lists DF-1 as requiring electricity, and Section 224716 requires power wiring information for pressure water coolers/bottle filling stations. Please clarify whether the electrical drawings include dedicated receptacles/circuits for both DF-1 units and confirm the required final power connection and startup scope.Y
56P-601Sheet P-601 lists ACT-1 as a 7.5 HP, 208V, 3 phase vertical air compressor. Section 221519 requires control panels, control voltage, power/signal/control wiring diagrams, startup, and an alarm signal device connection to an alarm system when the backup compressor is operating. Please clarify whether the electrical drawings include the required circuit/disconnect for ACT-1 and whether any alarm, BAS, or monitoring connection should be included in the bid.See M-601 for compressor room exhaust fan controls required, other monitoring or BAS not that is not indicated in the contract documents not required. See electrical plans E-401 and E-603 for electrical connections.
57221119Section 221119 states electrical connections and control wiring are required for domestic water piping specialties where applicable. The plumbing drawings show BFP-1 and WM-1 in the domestic water/mechanical room area. Please clarify whether WM-1 or any domestic water piping specialty requires power, signal wiring, communication wiring, or connection to the campus/BAS/metering system.Y
58230800Section 230800 includes automatic control valves, dampers, actuators, and control interface with fans, pumps, dampers, and other equipment as part of the commissioned HVAC controls scope. Section 230900 requires Johnson Controls Metasys integration through the existing supervisory controller. Please clarify whether HVAC damper/valve actuators are low-voltage BAS-powered devices, line-voltage devices, or a mix, and identify the required transformers, control wiring, programming, and functional testing to be included in the bid.Y [Add 24V dampers to the spec if allowed, only 120V dampers are indicated in 233300, and those dampers are not indicated on E sheets]
59233300Mechanical drawings show fire damper locations and details, and Section 233300 includes fire dampers and duct accessories. Please clarify whether any fire/smoke dampers require electrical power, monitoring, or fire alarm interface, and identify the required monitoring modules, wiring, and final testing to be included in the bid.Y [ Identify on the plans if it is a FD or a FD/SD combo, and include SD specs]
60230900Section 230900 states there is an existing Johnson Controls supervisory controller in Building 100 and that the controls contractor shall map available control points from FEC controllers and VRF interface into the existing Johnson Controls Metasys UI. Please clarify whether the Contractor should include full BAS graphics, point mapping, programming, network connection, credentials coordination, trend logs, final commissioning support, and acceptance with NIFC staff.Y [Change spec to not use building 100 controller]
61The specifications require a nameplate at each electrical connection indicating the electrical equipment designation and circuit number feeding the connection. Please confirm whether this requirement applies to all powered mechanical, plumbing, compressed air, domestic water, water heater, controls, and equipment connections, including P-1, WH-1, WH-2, ACT-1, DF-1, LAV-1 touchless faucets, and any BAS-controlled equipment.The specifications require a nameplate where listed, as outlined in the specific specification for each type of equipment.
62033000The drawings indicate use of a semi-rigid epoxy joint filler, while Specification Section 03 30 00 references a semi-rigid polyurea joint filler. Please confirm which material is required for the project and whether both products are considered acceptable.Y
63E-401Keyed Note 10 references OM4 multimode fiber; however, no destination or termination location is identified on the drawings or specifications. Please confirm the required homerun destination and extent of fiber installation.See ES101 for extent of fiber installation.
64E-401Keyed Note 9 references a cellular signal booster system; however, no associated cabling, device layout, or specification section has been identified. Please confirm whether the cellular booster system and associated cabling are contractor furnished and installed, owner furnished and contractor installed, or by others.Cellular booster system is identified on the sheet keynote, therefore is contractor furnished and installed.
65E-401Keyed Note 6 references procurement and installation of the UPS, battery modules, and 48-port PoE+ switches with redundant power supplies; however, quantities for these devices are not identified. Please confirm required quantities for each item.Y
66Electrical / Technology DrawingsPlease confirm whether cameras, wireless access points (WAPs), and associated technology equipment are contractor furnished and installed or owner furnished and contractor installed.Cameras and WAP are government provided, installed, and connected at a future date. Contractor provides the junction box, covers, cabling, and labeling to future connection.
67Technology Cabling RequirementsPlease confirm required cable color coding for data cabling and camera cabling. Specifically, confirm whether all cabling is required to be Cat6A blue cable or whether separate cable color identification is required by system type.Y [Update spec with NIFC campus network cable color standard]
68233300, 233400, 233500, 233713, 237219, 238219, 233400Please review attached mechanical equipment substitution requests and confirm acceptability of the proposed equivalent manufacturers and equipment.No substitution request necessary. Per the applicable specification section, manufacturers are not limited to the names listed if meeting the requirements.
6910 26 00
Sheet IN-601Specification Section 10 56 13 references delegated design requirements for seismic restraint of metal storage shelving. Please confirm whether compliance with the requirements identified on Sheet S-506 Detail B2 satisfies the delegated design requirement or whether additional engineered design and calculations are required.Sheet S-506 detail B2 and specification section 10 56 13 indicates rack design requirements, so a delegated design is still required.
70Division 10Please confirm whether equivalent Larsen’s fire extinguisher cabinets and Amerex fire extinguishers are acceptable substitutions for the specified products.See answer #68.
7110 56 13, Paragraph 1.4.CS-506Metal Storage Shelving - calls out "Delegated Design" for the seismic restraint of the metal storage shelving. Confirmation requested that requested bid can match the requirements in S-506 (B2) and any delegated design to be clarified.Sheet S-506 detail B2 and specification section 10 56 13 indicates rack design requirements, so a delegated design is still required.
72Architectural Drawings and Division 10 SpecificationsPlease confirm responsibility and specification requirements for the following items identified on the drawings as contractor furnished and installed but not clearly specified within Division 10:

Interior room signage FRP1 wall protection WP1/CG1/CG6 wall protection systems Toilet accessories Fire extinguishers and fire extinguisher cabinets Whiteboards Metal storage shelving

Exercise room mirrors (MI1)Y
73Architectural and Plumbing DrawingsRooms 1502, 1503, 1504, and 1505The shower assemblies for Rooms 1502 through 1505 are not clearly defined. Shower inserts are not identified on the plumbing fixture schedule. Please confirm whether the showers are to utilize prefabricated ADA shower inserts or conventionally framed and finished wall systems. Additionally, please confirm responsibility for grab bars and shower seats.Y
74E-501Sheet E-501 includes access control details; however, no associated specification section defining access control system requirements has been identified. Please provide the applicable specification section and clarify the intended access control scope.Y
75011000, 014000, and 015000Please confirm whether a dedicated Site Safety and Health Officer is required for this project and identify any minimum required qualifications or certifications for project safety personnel.Contractor is required to comply with OSHA requirements for General Construction. Also see solicitation item H-5, and answer #89.
76014000 and 019113The specifications require extensive coordination of testing, inspections, manufacturer representatives, commissioning activities, and startup procedures. Please confirm whether the Government anticipates dedicated onsite personnel specifically assigned to commissioning coordination and closeout management.Y [Reduce commissioning requirements in 019113 to basic startup phase]
7715000Specification Section 015000 references temporary field office requirements, temporary communication systems, and Government access to project communications. Please confirm whether the Contractor is required to maintain a continuously staffed onsite field office for the duration of active construction operations or does the phasing of the two buildings remove most of that requirement.See answer #89. Contractor to provide the temporary facilities as appropriate for the work per specification section 015000.
78024116, Paragraph 3.3.A.3Please confirm whether any utilities associated with Building 415-MNT currently serve adjacent facilities, campus infrastructure, or systems that are required to remain operational after demolition activities commence. If so, please identify any required temporary services, bypass connections, phased shutdown requirements, or utilities intended to remain active during demolition operations.Y [Previous review comment to reconnect the guard shack PACS and comm was not followed. Show reconnection]
79024116 – Structure Demolition, Paragraph 3.5.HSpecification Section 024116, Paragraph 3.5.H references abandonment of existing utilities and below-grade utility structures “within 5 feet outside the footprint indicated for new construction.” Since the 415-MNT scope consists of demolition and restoration of the area to parking, please clarify the intended limits for utility abandonment associated with the 415-MNT demolition work and confirm whether the reference to “new construction” is applicable to this phase of work.The new construction refers to the new work identified on the plans for new parking and site lighting.
80017419 and 024116Sheet Q-Series DrawingsThe Q-Series drawings identify specific equipment and materials intended to be reused or retained by the Government. Please clarify responsibility for miscellaneous remaining contents within Building 415-MNT that are not specifically identified for reuse or salvage, including but not limited to IT equipment, communications equipment, maintenance shop tools, loose equipment, shelving contents, and other owner materials remaining at time of demolition.
Please confirm whether the Government intends to remove these items prior to demolition or whether the Contractor is to include handling, storage, recycling, salvage coordination, or disposal of remaining miscellaneous contents as part of the demolition scope.See Amendment for additional clarification
81017419 – Construction Waste Management and DisposalPlease confirm whether the construction waste management, recycling, salvage, diversion, and reporting requirements identified in Section 017419 are fully contained within the contract documents or whether additional DOI, BLM, NIFC, sustainability, salvage, recycling, or waste diversion standards, policies, reporting requirements, or tracking procedures are intended to apply to this project.Any construction waste requirements not indicated in the clauses of the solicitation document are indicated in Specification section 017419 and CD101.
82017419 – Construction Waste Management and Disposal, Paragraph 3.3.BSpecification Section 017419, Paragraph 3.3.B states that “revenues, savings, rebates, tax credits, and other incentives received for recycling waste materials shall accrue to Government.” Please clarify which specific material streams this requirement applies to, including whether the requirement applies to all recyclable demolition materials generated by the project or only to materials specifically identified by the Government for salvage, recycling, or retention.
Please also confirm whether bidders are to assume that all recyclable material value associated with demolition activities is to be excluded from contractor salvage offsets and retained for the benefit of the GovernmentSee Amendment for revision to the specification
83415-MNT Demolition Drawings and Project Phasing RequirementsPlease confirm whether demolition of Building 415-MNT may commence immediately following substantial completion of Building 320-SGE or whether additional Government occupancy transition activities are anticipated prior to demolition authorization.See Amendment for additional clarification
84Section 024116 – Structure Demolition415-MNT Demolition DrawingsPlease clarify the required extent of below-grade demolition associated with Building 415-MNT within the limits of the future parking area, including whether existing foundations, slabs, grade beams, utility encasements, abandoned utility structures, manholes, vaults, and other below-grade concrete elements are to be fully removed or permitted to remain in place beneath the completed parking improvements.Y
85017419 and 024116415-MNT Demolition DocumentsSpecification Sections 017419 and 024116 include requirements associated with refrigerant recovery, universal waste handling, regulated material disposal, and demolition waste segregation. Please confirm whether hazardous material surveys or regulated material reports associated with Building 415-MNT are included within the contract documents, including any available asbestos, lead-containing material, PCB-containing equipment, refrigerant, or other regulated material assessments applicable to demolition activities.See answer #11 and #12.
86015000, Paragraph 3.5 and 017419 – Construction Waste ManagementOn the site walk the campus recognizes layout, and the phased construction approach for 320-SGE and 415-MNT, we anticipate space for contractor laydown, staging, parking, stockpile, salvage, and recycling operations will be limited.
To ensure consistent bidding assumptions and alignment with the Government’s intended site logistics approach, please provide the approximate area size and location for contractor staging, laydown, parking, stockpile, salvage, and recycling activities associated with both phases of work.See Attachment 9 NIFC Campus Map. Contractor parking areas are restricted to striped parking areas on the NIFC Campus identified on the map as "General Parking". The laydown, staging, stockpile, salvage, and recycling area shall be within the area identified on 320-SGE plan sheet CD101 linetype "Approximate Limits of Construction", and upon start of building demolition, within the area indicated on 415-MNT plan sheet CD101 line type "Approximate Limits of Construction". Partial usage of the parking lot east of 320-SGE will be available during Demolition.
87013200 – Construction Progress DocumentationSpecification Section 013200 requires preparation and maintenance of a detailed construction schedule using Microsoft Project, Primavera, or similar scheduling software. Please confirm whether the project schedule is required to include cost loading, resource loading, earned value tracking, or integration with the Schedule of Values beyond the requirements specifically identified in the contract documents.Schedule shall follow the requirements listed in the specifications
88015000 – Temporary Facilities and ControlsThe contract documents include requirements associated with temporary controls, environmental protection, traffic control, erosion control, dust control, public safety, and phased construction operations within an active campus environment. Please confirm the Government’s anticipated expectations regarding project safety administration and onsite safety staffing, including whether dedicated full-time onsite safety personnel are anticipated for the duration of the Work or whether safety oversight may be performed by qualified project supervision staff as part of their assigned duties.See answer #75.
89013200, 013300, and Quality Control RequirementsThe contract documents include requirements associated with construction scheduling, inspections, testing coordination, submittal management, phased construction operations, and ongoing project reporting. Please confirm the Government’s anticipated expectations regarding onsite quality control administration and staffing, including whether dedicated full-time onsite quality control personnel are anticipated for the duration of the Work or whether quality control responsibilities may be performed by qualified project supervision staff as part of their assigned duties.Offeror's staffing plans is a means and methods, though the Solicitation document adopts FAR requirements for on site work including 52.236-6 Superintendence by the Contractor: "At all times during performance of this contract and until the work is completed and accepted, the Contractor shall directly superintend the work or assign and have on the worksite a competent superintendent who is satisfactory to the Contracting Officer and has authority to act for the Contractor". Proposals will be evaluated per solicitation L-6 and M-5 and those with less risk will be rated more favorably.
90013200, 013300, and 015000Please confirm the Government’s anticipated staffing expectations for superintendent, safety, and quality control responsibilities associated with the Work, including whether qualified project personnel may perform combined superintendent, safety, and/or quality control duties (“dual hat” or “triple hat” roles) or whether the Government anticipates dedicated personnel assigned separately to these functions for the duration of the project.See answer #89
91Utility DrawingsThe contract documents indicate that work associated with the City of Boise domestic water system connection is required to be performed by a Veolia-approved contractor. Please clarify the anticipated extent of work to be performed under this requirement, including whether the Veolia-approved contractor is anticipated to perform only the final live connection/tie-in activities or whether the requirement also includes associated excavation, utility exposure, piping installation, shutdown coordination, service interruptions, testing, chlorination, and commissioning activities associated with the domestic water system work.The Veolia-approved contractor is identified in the locations listed in C-104 sheet keynotes where noted.
92017419 – Construction Waste Management and DisposalLandscape/Irrigation DrawingsThe contract documents include irrigation system modifications together with project salvage and recycling requirements. Please clarify whether the Government anticipates any specific coordination, salvage, reuse, stockpile, or return-to-Government expectations associated with removed irrigation and sprinkler system materials during construction activities.Coordination with government and reuse is identified on plan sheets LS001 and LS1002. No other additional specific salvage or stockpile requirements anticipated.
93Division 26 and 27 SpecificationsElectrical Site Utility Drawings
Low-Voltage DrawingsThe contract documents indicate utility trenching to the existing utility vault located within the parking area west of the proposed 320-SGE footprint and south of Building 300. Please clarify the intended division of responsibility associated with low-voltage and communications utility connections at this location, including which conduit runs, cabling, terminations, tie-ins, and system connections are to be provided by the Contractor and which are anticipated to be performed by the Government.
Please also clarify whether any contractor-performed low-voltage or communications work within Building 300 is anticipated as part of the required system connections.All connections identified on the drawings are contractor provided. Work within building 300 by the contractor is identified on 320-SGE ES101 keynote 2.
94Utility Vault DetailsElectrical Site Utility DrawingsPlease confirm whether the existing utility vault lid associated with the low-voltage utility connection work west of the proposed 320-SGE footprint is intended to remain in place or be replaced as part of the project. If replacement is required, please provide the anticipated vault lid type, loading requirements, and material expectations.Y
95Equipment / Relocation DrawingsDrawing S-506 – Storage Rack NotesDrawing S-506 requires the rack manufacturer to provide a complete rack system designed in accordance with RMI MH 16.1, including structural components, beams, columns, braces, base plates, and anchor bolts, with anchorage based on a 5,000 lb per shelf loading requirement and 15,000 lb total assembled rack load for a three-shelf configuration. Other contract documents appear to reference relocation of existing pallet racks from Building 415-MNT. Please clarify whether the storage racks are to be provided as new complete rack systems meeting S-506 requirements, or whether existing pallet racks are intended to be relocated and modified, supplemented, certified, and anchored to meet the S-506 requirements.Pallet racks identified on plan sheet Q-101 are to be a complete rack system meeting the plan sheet S-506 requirements. Also see answer #69.
96Temporary Facilities and ControlsSpecifications 15000Please confirm whether the Contractor is required to provide a dedicated full-time onsite Superintendent during all construction activities. The Contract Documents include requirements related to construction management, temporary facilities, coordination, and daily reporting; however, the specifications do not appear to specifically define minimum onsite superintendent staffing requirements or require a dedicated full-time Superintendent position. Clarification is requested to ensure proper staffing assumptions are included in the proposal.See answer #89.