This is a Specification Section (01 10 00 – Summary) for a construction contract under the Bureau of Land Management for flood damage repair work at the Glennallen Field Office in Glennallen, Alaska (MP 186.2, Glenn Highway). The work includes restoration of buildings and infrastructure damaged by flooding, specifically releveling a building, repairing a well house, improving electrical equipment, and altering site utilities. The project will be constructed under a single prime contract, and no geotechnical report is available; attachment and foundation methods are outlined in project drawings and specifications.

The contractor must coordinate with separate contractors performing concurrent work and comply with strict phased construction and sequencing requirements to support government operations during work execution. Key operational constraints include: (1) a 45-day government vacate period for the Headquarters Office Building with power maintained to communications equipment except during an 8-day main distribution panel replacement; (2) a full 8-day site vacation during which main distribution panel, well house repairs, and annex office building utility reconnection occur with no power or water service, with restoration required by day's end and water quality testing allowed thereafter; (3) an additional 8-day window for lift station control panel replacement; (4) utility service interruptions prohibited during regular office hours except with written government approval; and (5) maintenance of clear access to driveways, entrances, walkways, and corridors at all times. The contractor must submit a work plan at least 21 calendar days before the first facility or utility closure demonstrating measures to minimize impacts to government operations, and the plan requires government approval before work commences.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BUREAU OF LAND MANAGEMENT

GFO FLOOD DAMAGE REPAIR

GLENNALLEN, ALASKA

SECTION 01 10 00

SUMMARY

Design Alaska, Inc. 01 10 00 ‐ 1

PART 1 GENERAL

1.1 SCOPE: SECTION 01 10 00 ‐ SUMMARY

A. This Section includes the following:

1. Work covered by the Contract Documents.

2. Work under other contracts.

3. Use of premises.

4. Government occupancy requirements.

5. Specification formats and conventions.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Identification: Glennallen Field Office Flood Repairs

1. Project No. – To be confirmed by Government.

2. Project Location: MP 186.2, Glenn Hwy, Glennallen, AK

B. The Work consists of the following:

1. The Work includes restoration of buildings and other infrastructure as a result of flooding that occurred at the Glennallen Field Office site. Work includes releveling a building, repairing a Well House, improving electrical equipment, and altering site utilities.

C. Project will be constructed under a single prime contract.

1.3 GEOTECHNICAL DATA

A. Geotechnical Report: There is no geotechnical information available for this project. At‐ tachment and foundation methods for the canopies are outlined within the project draw‐ ings and specifications.

GLENNALLEN, ALASKA

Design Alaska, Inc. 01 10 00 ‐ 2

1.4 WORK UNDER OTHER CONTRACTS

A. Cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate the Work of this Contract with work performed under separate contracts.

1.5 USE OF PREMISES

A. Contractor shall have full use of premises for construction operations, including use of Project site, during construction period. Contractor's use of premises is limited only by Government right to perform work or to retain other contractors on portions of Project.

B. Phased Construction

1. This project requires phased construction and specific sequencing to support Government operations during the work. The stated phasing requirements have been approved by the Government as a basic plan while not knowing in advance the Contractor’s eventual ways, means, and methods. The Contractor shall sub‐ mit a work plan that demonstrates their intended approach to minimize impacts to Government operations. The plan shall be submitted no less than 21 calendar days in advance of the first facility or utility closure and must be approved by the Government before work can occur. The Contractor must meet the minimum stated requirements but can offer the Government a work plan that is considered more beneficial to the Government, pending Government concurrence and ap‐ proval.

2. Government will vacate the Headquarters Office Building for a period of 45 days while the releveling and repair work takes place in this facility. Site communica‐ tions are distributed from within this facility and, with the exception of an 8‐day period where the site’s Main Distribution Panel is replaced, power must remain on at this facility to power the communications equipment.

3. The Government will fully vacate the site for an 8‐day period wherein the Main Distribution Panel, repair work in the Well House, and reconnection of the exist‐ ing temporary AnnexLog Office Building utilities are to occur. During this time there will be no power or water distribution required to the site. By the end of the 8‐day period, power and water distribution shall be restored to the site. A few days allowance for laboratory testing of water distribution systems to con‐ firm water quality will be granted for restoration of water service to the AnnexLog Office Building. The 8‐day outage period for MDP and Well House work is deter‐ mined by the first 2‐day weekend, a 5‐day workweek, and the first day of a second 2‐day weekend. The second day of the second weekend is allocated for the Con‐ tractor to demonstrate to the Government that facilities are operational and that staff can return to work at the Site. The Contractor shall obtain all necessary work items and have them on hand before beginning the 8‐day closure so as to ensure work can be fully and successfully completed during this strict 8‐day closure

GLENNALLEN, ALASKA

Design Alaska, Inc. 01 10 00 ‐ 3 period. Any exceptions to this approach must be approved in advance in writing by the Government’s Representative.

4. Following this primary 8‐day closure, regular contract requirements will apply to any interruption to utilities or Government facilities such as when the new wa‐ terline for the AnnexLog Office Building is ready for connection or site electrical work that may require a utility outage for turn over.

5. Replacement of the Lift Station Control Panel must also be accomplished within an 8‐day closure that spans a first weekend, a full work week, and the first day of the second 2‐day weekend. This 8‐day window may align with the primary 8‐day window dedicated to the MDP and Well House work. If it does not align with the primary 8‐day window, the Contractor must ensure that portable latrines and handwashing stations are provided for Government use and that sewer facilities that utilize the Lift Station are locked out/tagged out from use by personnel.

6. A phasing matrix summarizing these requirements is included at Attachment 1 to Section 01 10 00 Summary.

C. Schedule and sequence operations necessary to complete the work, including coordina‐ tion with other crafts relative to the Contractor's requirements. Schedule Work in such manner as to avoid delays in overall construction and permit proper installation of work.

D. Use of Site: Limit use of premises to areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Limits: Confine constructions operations to areas indicated on drawings.

2. Government Occupancy: Allow for Government occupancy of Project site and use by the public. Government personnel will be continuously occupying areas of the building immediately adjacent to the work area, except as previously noted.

Conduct work in a manner that will minimize needs for disruption of normal Gov‐ ernment operations. Provide minimum 72 hours advance notice to Government of activities that will impact normal Government operations. Secure Govern‐ ment's written approval of activities that will impact normal Government opera‐ tions to avoid delays in overall construction and permit proper installation or work.

3. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government, Government employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

a. Schedule deliveries to minimize use of driveways and entrances.

b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on‐site.

E. Utilities: Service interruptions will not be allowed during regular office hours.

GLENNALLEN, ALASKA

Design Alaska, Inc. 01 10 00 ‐ 4

1.6 GOVERNMENT OCCUPANCY REQUIREMENTS

A. Partial Government Occupancy: Government will occupy the premises during entire con‐ struction period, with the exception of areas under construction. Cooperate with Gov‐ ernment during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government operations. Maintain existing exits, unless otherwise indicated.

1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Government and authorities hav‐ ing jurisdiction.

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION (NOT USED)

END OF SECTION