Attachment_8_Q_A_0001.pdf
PDF 94 KB Posted
- Attached to
- Glennallen Field Office Flood Repairs
- Solicitation number
- 140L0626B0005
About this file
This is a Questions and Answers document for Solicitation No. 140L0626B0005, GFO Flood Damage Repairs. The document addresses three substantive inquiries from potential bidders regarding the solicitation requirements.
The first question confirms that an attendance sheet for the prebid site tour is available as an attachment to the amendment. The second question addresses FM-200 fire suppression system disposal requirements, which have been revised on Drawing M100, Note 4. The revised requirements specify that FM-200 primer charge and FM-200 must be disposed of in accordance with EPA Regulations 608, with discharge to atmosphere prohibited. The FM-200 must be reclaimed, recycled, or returned to the manufacturer by a contractor certified and licensed to work on clean agent fire suppression systems. Contractors must submit an EPA Section 608 compliant certificate of disposal/recycling form and chain of custody form, with transportation of cylinders complying with DOT regulations per 49 CFR Parts 171, 172, and 173. The third question clarifies that references to the Annex Office Building in the specifications have been changed to the Log Office Building, with revisions included in specification sections 01 10 00 Summary Work, 01 10 00 Phasing matrix, and 01 50 00 Temporary Facilities and Controls.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers GFO Flood Damage Repairs
Solicitation No. 140L0626B0005
GFO Flood Damage Repairs
Questions and Answers
1. Question: Is the attendance sheet for the prebid site tour available?
Answer: Yes, it is attached to this amendment.
2. Question: Will there be a revision to the Halon system disposal requirements?
Answer: Yes, note 4 on Drawing M100 is revised to read:
4. DISPOSE OF FM-200 PRIMER CHARGE AND FM-200 IN ACCORDANCE WITH
EPA REGULATIONS 608. DISCHARGE TO ATMOSPHERE IS PROHIBITED. FM-
200 SHALL BE RECLAIMED, RECYLED, OR RETURN TO THE
MANUFACTURER. REMOVAL OF UNIT SHALL BE PERFORMED BY A
CONTRACTOR THAT IS CERTIFIED AND LICENSED TO WORK ON CLEAN
AGENT FIRE SUPPRESSION SYSTEMS. SUBMIT EPA SECTION 608
COMPLIANT CERTIFICATE OF DISPOSAL/RECYCLING FORM AND
CHAIN OF CUSTODY FORM. TRANSPORTATION OF CYLINDERS SHALL
COMPLY WITH ALL DOT REGULATIONS REGARDING COMPRESSED GAS
CYLINDERS PER 49 CFR PARTS 171, 172, & 173.
3. Question: The specifications mention the Annex Office Building, is there work related to that facility?
Answer: No. References are now changed to the Log Office Building. See revised specification section 01 10 00 Summary Work, 01 10 00 Phasing matrix, and 01 50 00
Temporary Facilities and Controls, attached to this amendment.