This is a Phasing Matrix document that outlines facility work requirements, occupancy constraints, and sequencing obligations for a federal construction or renovation project involving multiple buildings and site systems.
The project encompasses work across six primary facility areas: Site Main Distribution Panel, Well House, Annex Log Office Building, Headquarters Office Building, HBO and Lift Station Control Panel, and Other Site Electrical systems. Work activities include raising infrastructure above flood levels, reconfiguring electrical panels, releveling facilities, repairing damaged finishes, and reconnecting or installing water and sewer utilities. Critical scheduling constraints include an 8-day closure window during which the Site Main Distribution Panel must be powered down, reconfigured, and powered up, and the Well House must be repaired with water service restored. The Annex Log Office Building requires existing water/sewer connections during the 8-day closure with additional connections following standard contract procedures later in the project. The Headquarters Office Building work spans the project duration except for a 45-day period, with power remaining operational at the facility except during the 8-day outage window. The Annex Log Office Building requires temporary provisions of portable latrines, handwashing stations, and potable water during periods when permanent restroom and water systems are unavailable. Other Site Electrical work for HBO and Lift Station Control Panel improvements requires standard contractual outage notification procedures with no major operational impacts anticipated.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
01 10 00 Summary Attachment 1 - Phasing Matrix
Facility Work Summary Occupancy of Government Key Phasing / Sequencing Requirements Temporary Facility Requirements
Site Main Distribution Panel Raise above flood level. Reconfigure per requirements. N/A
Must be powered down, reconfigured, and powered up within the 8-day closure window. None
Well House Raise floor level. Reconfigure per requirements. N/A
Must be repaired and water service restored within the 8-day closure window. None
Annex Log Office Building Reconnect existing water/sewer. Install new water line.
Duration of project except for 8-day closure period.
Connect existing water/sewer utilities during 8-day closure window. Other connections required later in the project will follow normal contract requirements.
Portable latrines, handwashing stations, and potable water station for periods when restrooms and potable water are not available at this
Headquarters Office Building Relevel facility and repair damaged finishes.
Duration of project except for 45 day period.
With the exception of the 8-day power outage, power must remain on at this facility. None
Other Site Electrical
HBO and Lift Station Control Panel improvements. Reconfigure per requirements. N/A
No major impacts expected. Follow contractual requirements for outage notifications. None