This document is Section 01 50 00 (Temporary Facilities and Controls) of the specifications for the Bureau of Land Management's GFO Flood Damage Repair project in Glennallen, Alaska.

The section establishes comprehensive requirements for temporary construction facilities and controls. The contractor must provide temporary utilities including water and electric power service, with the government supplying these services without metering or use charges, except during periods when the Well House or Main Distribution Panel are under repair—at which times the contractor must provide their own water and power supplies. The contractor must submit a site plan showing temporary facilities, utility hookups, staging areas, and parking; an air quality permit five days before commencing covered activities; a landscape protection plan seven days before construction; and first aid plans before operations begin. Safety fencing must consist of orange plastic fencing minimum 4 feet high, and tarpaulins must be waterproof, fire-resistant, and UL-labeled with flame-spread ratings of 15 or less. The contractor must provide two portable latrines and two handwashing stations dedicated to government personnel use (one of each ADA-compliant), located adjacent to the AnnexLog Office Building, plus a potable water supply station dispensing 20-30 gallons daily for government personnel. Additional latrines and facilities for contractor use must be in a separate area. All portable facilities require daily cleaning and sanitation. The contractor must install temporary fire protection, security measures, barricades, warning signs, and lighting; provide waste disposal containers complying with NFPA 241; and remove all temporary structures, debris, and materials by Substantial Completion, restoring all areas to original or better condition including topsoil and seeding as necessary. Compliance with NFPA 241, NECA, NEMA, UL standards, and AASHTO MUTCD requirements is mandatory.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BUREAU OF LAND MANAGEMENT

GFO FLOOD DAMAGE REPAIR

GLENNALLEN, ALASKA

SECTION 01 50 00

TEMPORARY FACILITIES AND CONTROLS

Design Alaska, Inc. 01 50 00 ‐ 1

PART 1 GENERAL

1.1 SCOPE: SECTION 01 50 00 ‐ TEMPORARY FACILITIES AND CONTROLS

A. This Section includes requirements for temporary utilities, temporary field office, first aid, sanitary facilities, other support facilities, vehicular access, and security and protection facilities, temporary barriers and controls, and project identification.

B. See Divisions 2 through 50 Sections for temporary heat, ventilation, and humidity requirements for products in those Sections.

1.2 DEFINITIONS

A. Permanent Enclosure: As determined by Government, permanent or temporary roofing is complete, insulated, and weathertight; exterior walls are insulated and weathertight;

and all openings are closed with permanent construction or substantial temporary closures.

B. Landscape Preservation: The term “injury” as such relates to landscape preservation includes, without limitation, bruising, scarring, tearing, and breaking of roots, trunks, or branches. Injury also includes damage to root systems from contractor equipment leaking oil, hydraulic fluid, or other toxic chemicals.

C. Pesticides: Includes herbicides, insecticides, fungicides, rodenticides, piscicides, avicides, surface disinfectants, animal repellents, and insect repellents.

D. Restricted Area: An area where entry will not be allowed unless authorized by Government.

E. Security Measures: Measures contained in regulations or as may be established by Government and carried out by Federal guard system to provide continuous and effective security of restricted areas.

1.3 USE CHARGES

A. Water Service: Water from Government existing water system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations. This provision does not apply to the time period that the Well House is under repair. The Contractor shall provide their own water service requirements for the duration of time that the Well House is under repair and not providing water to the campus.

GLENNALLEN, ALASKA

Design Alaska, Inc. 01 50 00 ‐ 2

B. Electric Power Service: Electric power from Government existing system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations. This provision does not apply to the time period that the Main Distribution Panel is under replacement. The Contractor shall provide their own power supply for the duration of time that the Main Distribution Panel is being replaced and not providing electrical service to the campus.

1.4 SUBMITTALS

A. Site Plan: Show temporary facilities, utility hookups, staging areas, and parking areas for construction personnel.

B. Temporary Utilities: Submit implementation and termination schedule for each utility;

and tests, inspections, meter readings, and similar procedures performed on temporary utilities.

C. Air Quality: Submit Air Quality Permit, five days prior to commencing activity for which Air Quality Permit is required. Air Quality Permits will be required for certain construction‐related activities including earthmoving, sandblasting, aggregate processing, welding, spray‐coating operations, or other processes which discharge pollutants into open air.

D. Landscape Protection Plan: Submit description of protective barriers or other methods used to protect vegetation from damage or injury caused by construction operations seven days before commencing construction activities.

E. First Aid Plans: Submit plans for providing medical attention for injured or disabled employees, including onsite emergency facilities and ambulance service, before start of operations. Submit physician’s written report of inspection of first‐aid station facilities.

1.5 QUALITY ASSURANCE

A. Electric Service: Comply with NECA, NEMA, and UL standards and regulations for temporary electric service. Install service to comply with NFPA 70.

B. Tests and Inspections: Arrange for authorities having jurisdiction to test and inspect each temporary utility before use. Obtain required certifications and permits.

C. Standards: Comply with NFPA 241 "Standard for Safeguarding Construction, Alterations, and Demolition Operations," ANSI A10 Series standards for "Safety Requirements for Construction and Demolition," and NECA Electrical Design Library "Temporary Electrical Facilities."

D. Comply with AASHTO Manual on Uniform Traffic Control Devices (MUTCD), Part VI.

GLENNALLEN, ALASKA

Design Alaska, Inc. 01 50 00 ‐ 3

E. Inspections: Arrange for authorities having jurisdiction to inspect and test each temporary utility before use. Obtain required certifications and permits.

F. Horticulturist or Tree Surgeon: Employ services of experienced horticulturist or licensed tree surgeon to direct repair, treatment, and replacement of vegetation.

1.6 REGULATORY REQUIREMENTS

A. Comply with applicable local regulations for haul routes over public highways, roads, or bridges. Comply with industry standards and applicable laws and regulations of authorities having jurisdiction including following:

1. Building code requirements.

2. Health and safety regulations.

3. Utility company regulations.

4. Police, fire department, and rescue squad rules.

5. Environmental protection regulations.

6. Prevention and control of air pollution.

7. Prevention and control of water pollution.

1.7 PROJECT CONDITIONS

A. Temporary Use of Permanent Facilities: Installer of each permanent service shall assume responsibility for operation, maintenance, and protection of each permanent service during its use as a construction facility before Government acceptance, regardless of previously assigned responsibilities.

B. Explosives: Use will not be permitted.

PART 2 PRODUCTS

2.1 TEMPORARY FACILITIES

A. Safety Fencing: Orange plastic fencing, 4‐foot minimum height.

GLENNALLEN, ALASKA

Design Alaska, Inc. 01 50 00 ‐ 4

B. Tarpaulins: Waterproof, fire‐resistant, UL‐labeled tarpaulins with flame‐spread rating of 15 or less. Provide translucent, nylon‐reinforced, laminated polyethylene or polyvinyl chloride, fire‐retardant tarpaulins for temporary enclosures.

C. Water: Provide a potable water supply station that has the capacity to dispense 20‐30 gallons per day that is dedicated to the use of Government personnel. This station shall be available to Government personnel at all times when potable water is not available to Government personnel within the AnnexLog Office Building. Locate the potable water station adjacent to the AnnexLog Office Building at a spot approved by the Government’s Representative.

2.2 EQUIPMENT

A. Fire Extinguishers: Portable, UL rated; with class and extinguishing agent as required by locations and classes of fire exposures.

B. Toilet Units: Self‐contained, single‐occupant toilet units of chemical, aerated recirculation, or combustion type. Provide units properly vented and fully enclosed with glass‐fiber‐reinforced polyester shell or similar nonabsorbent material. Provide two (2) portable latrines and two (2) handwashing stations dedicated for use by Government personnel. One of each unit type shall meet ADA requirements. These facilities shall be available to Government personnel at all times when bathrooms are not available to Government personnel within the AnnexLog Office Building. Locate the facilities adjacent to the AnnexLog Office Building at a spot approved by the Government’s Representative. The Contractor shall provide portable latrines dedicated for their use in an area separated from those dedicated to Government use. All portable latrines and handwashing stations shall be cleaned daily by the Contractor and kept sanitary, tidy, and free of debris and garbage.

2.3 PROJECT IDENTIFICATION

A. Project Site Sign: Within 30 days after Notice to Proceed, provide project sign located at main construction entrance to site.

B. Construction Signs: Erect signs to expedite deliveries, maintain traffic flow, promote safety, and caution against danger, as necessary.

GLENNALLEN, ALASKA

Design Alaska, Inc. 01 50 00 ‐ 5

PART 3 EXECUTION

3.1 INSTALLATION, GENERAL

A. Locate facilities where they will serve Project adequately and result in minimum interference with performance of the Work. Relocate and modify facilities as required by progress of the Work.

B. Provide each facility ready for use when needed to avoid delay. Do not remove until facilities are no longer needed or are replaced by authorized use of completed permanent facilities.

3.2 TEMPORARY UTILITY INSTALLATION

A. General: Electrical power, Water are available on the site and will be provided by the Government to the Contractor. Install temporary service or connect to existing service.

1. Arrange with utility company, Government, and existing users for time when service can be interrupted, if necessary, to make connections for temporary services.

B. Water Service: Use of Government existing water service facilities will be permitted, as long as facilities are cleaned and maintained in a condition acceptable to Government.

At Substantial Completion, restore these facilities to condition existing before initial use.

1. Where installations below an outlet might be damaged by spillage or leakage, provide a drip pan of suitable size to minimize water damage. Drain accumulated water promptly from pans.

C. Sanitary Facilities: Provide temporary toilets, wash facilities, and drinking water for use of both Government and construction personnel. Comply with authorities having jurisdiction for type, number, location, operation, and maintenance of fixtures and facilities.

1. Install self‐contained toilet units, shield toilets to ensure privacy. Use of pit‐type privies will not be permitted.

2. Provide toilet tissue, paper towels, paper cups, and similar disposable materials for each facility. Provide covered waste containers for used material.

D. Electric Power Service: Use of Government existing electric power service will be permitted, as long as equipment is maintained in a condition acceptable to Government. No electrical materials which are part of the permanent electrical system may be used for temporary electrical installations unless approved in writing by Government. Provide weatherproof, grounded electric power service and distribution

GLENNALLEN, ALASKA

Design Alaska, Inc. 01 50 00 ‐ 6 system of sufficient size, capacity, and power characteristics during construction period.

Include meters, transformers, overload‐protected disconnects, automatic ground‐fault interrupters, and main distribution switch gear.

E. Lighting: Provide temporary lighting with local switching that provides adequate illumination for construction operations, observations, inspections, and traffic conditions.

1. Install and operate temporary lighting that fulfills security and protection requirements without operating entire system.

2. Provide temporary lighting that will provide adequate illumination for construction operations and traffic conditions.

3.3 SUPPORT FACILITIES INSTALLATION

A. General: Comply with the following:

1. Provide incombustible construction for offices, shops, and sheds located within construction area or within 30 feet of building lines. Comply with NFPA 241.

2. Maintain support facilities until near Substantial Completion. Remove before Substantial Completion. Personnel remaining after Substantial Completion will be permitted to use permanent facilities, under conditions acceptable to Government.

B. Parking: Use designated areas of Government existing parking areas for construction personnel. Provide additional offsite parking when site space is not adequate. Locate as approved by Government.

C. Project Identification and Temporary Signs: Provide Project identification and other signs. Install signs where indicated to inform public and individuals seeking entrance to Project. Unauthorized signs are not permitted.

1. Provide temporary, directional signs for construction personnel and visitors.

2. Maintain and touchup signs so they are legible at all times.

D. Waste Disposal Facilities: Provide waste‐collection containers in sizes adequate to handle waste from construction operations. Comply with requirements of authorities having jurisdiction. Comply with Division 1 Section "Execution Requirements" for progress cleaning requirements. Collect waste from construction areas and elsewhere daily. Comply with requirements of NFPA 241 for removal of combustible waste material and debris. Enforce requirements. Do not hold materials more than seven days during normal weather or three days when temperature is expected to rise above 80 degrees F.

Handle hazardous, dangerous, or unsanitary waste materials separately form other waste by containerizing properly. Dispose of material lawfully.

GLENNALLEN, ALASKA

Design Alaska, Inc. 01 50 00 ‐ 7

E. Lifts and Hoists: Provide facilities necessary for hoisting materials and personnel.

1. Truck cranes and similar devices used for hoisting materials are considered "tools and equipment" and not temporary facilities.

F. Existing Stair Usage: Use of Government existing stairs will be permitted, as long as stairs are cleaned and maintained in a condition acceptable to Government. At Substantial Completion, restore stairs to condition existing before initial use.

1. Provide protective coverings, barriers, devices, signs, or other procedures to protect stairs and to maintain means of egress. If, despite such protection, stairs become damaged, restore damaged areas so no evidence remains of correction work.

G. Individual Project circumstances may require use of other construction aids and miscellaneous facilities, such as scaffolds, platforms, swing stages, ramps and bridges, incidental sheeting and shoring, and demolition waste chutes. Add requirements to suit Project. See Evaluations.

H. Safety Facilities: Provide safety showers, eyewash fountains, and similar facilities for safety and sanitation of personnel.

I. First‐Aid Facilities: Make first‐aid facilities and services obvious and available for providing emergency aid to personnel on the site.

3.4 STORAGE/STAGING AREAS

A. Storage/Staging Areas: Construct temporary area for trailers, equipment, and materials, located as approved by Government. Fencing of materials or equipment shall be required at this site. Trailers, materials, or equipment shall not be placed or stored outside fenced area unless trailers, materials, or equipment are assigned separate and distinct storage area by Government away from vicinity of construction site but within Government property boundaries.

3.5 SECURITY AND PROTECTION FACILITIES INSTALLATION

A. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.

B. Security Enclosure and Lockup:

1. Protect site, materials, and operations from theft, vandalism, and unauthorized entry.

GLENNALLEN, ALASKA

Design Alaska, Inc. 01 50 00 ‐ 8

2. Provide lockable entrances to prevent unauthorized entrance, vandalism, theft, and similar violations of security.

C. Barricades, Warning Signs, and Lights: Comply with requirements of authorities having jurisdiction for erecting structurally adequate barricades, including warning signs and lighting.

1. Construct fence, barricade, or otherwise block off immediate work area to prevent unauthorized entry.

2. Illuminate barricades and obstructions at night; keep safety lights burning from sunset to sunrise.

3. Adequately barricade and post open cuts in or adjacent to thoroughfares.

4. Protect pedestrian traffic with guardrails or fences.

5. When pedestrian traffic is detoured onto a roadway, provide temporary covered walkways. Provide ramps at changes in elevation of walkways.

6. Cover pipes, hoses, and power lines crossing sidewalks and walkways with troughs using beveled edge boards.

D. Temporary Enclosures: Provide temporary enclosures for protection of construction, in progress and completed, from exposure, foul weather, other construction operations, and similar activities. Provide temporary weathertight enclosure for building exterior.

1. Where heating or cooling is needed and permanent enclosure is not complete, insulate temporary enclosures.

E. Temporary Fire Protection: Install and maintain temporary fire‐protection facilities of types needed to protect against reasonably predictable and controllable fire losses.

Comply with NFPA 241.

1. Prohibit smoking in construction areas.

2. Supervise welding operations, combustion‐type temporary heating units, and similar sources of fire ignition according to requirements of authorities having jurisdiction.

3. Develop and supervise an overall fire‐prevention and ‐protection program for personnel at Project site. Review needs with local fire department and establish procedures to be followed. Instruct personnel in methods and procedures. Post warnings and information.

4. Provide temporary standpipes and hoses for fire protection. Hang hoses with a warning sign stating that hoses are for fire‐protection purposes only and are not to be removed. Match hose size with outlet size and equip with suitable nozzles.

GLENNALLEN, ALASKA

Design Alaska, Inc. 01 50 00 ‐ 9

3.6 OPERATION, TERMINATION, AND REMOVAL

A. Supervision: Enforce strict discipline in use of temporary facilities. To minimize waste and abuse, limit availability of temporary facilities to essential and intended uses.

B. Maintenance: Maintain temporary structures, facilities, and controls in good operating condition as required for safe and proper completion of Work and as directed by Government, until removal.

1. Maintain operation of temporary enclosures, heating, cooling, humidity control, ventilation, and similar facilities on a 24‐hour basis where required to achieve indicated results and to avoid possibility of damage.

C. Temporary Facility Changeover: Do not change over from using temporary security and protection facilities to permanent facilities until Substantial Completion.

D. Termination and Removal: Remove temporary structures, facilities, and controls when need for its service has ended, when it has been replaced by authorized use of a permanent facility, or no later than Substantial Completion. Complete or, if necessary, restore permanent construction that may have been delayed because of interference with temporary facility. Repair damaged Work, clean exposed surfaces, and replace construction that cannot be satisfactorily repaired.

1. Materials and facilities that constitute temporary facilities are property of Contractor. Government reserves right to take possession of Project identification signs.

2. Remove construction debris, waste materials, and packaging material from work site daily. Clean dirt or mud tracked onto paved or surfaced roadways. Store salvageable materials, resulting from demolition activities, within fenced storage area. Stack stored material not in trailers, whether new or salvaged.

3. Upon completion of project and after removal of trailers, materials, and equipment from within fenced area, remove fence. Restore areas used by Contractor for storage of equipment or material, or other use, to original or better condition.

Restore area to original condition, including top soil and seeding as necessary.

4. At Substantial Completion, clean and renovate permanent facilities used during construction period. Comply with final cleaning requirements specified in Division 1 Section "Closeout Procedures."

END OF SECTION

GLENNALLEN, ALASKA

Design Alaska, Inc. 01 50 00 ‐ 10

THIS PAGE INTENTIONALLY LEFT BLANK