Sol_140A1626B0001_Amd_0005.pdf
PDF 263 KB Posted
- Attached to
- Bannock Pumping Plant Rehabilitation Federal contract opportunity
- Solicitation number
- 140A1626B0001
About this file
This is Amendment 0005 to Solicitation 140A1626B0001 for the Bannock Pumping Plant Rehabilitation project, issued by BIA Central (Contracting Office at 12201 Sunrise Valley Drive, Reston, VA 20192) with an effective date of May 7, 2026. The amendment is not extending the offer receipt deadline, which remains 12:00 PM Eastern on July 14, 2026. Contractors must acknowledge receipt of this amendment prior to the deadline by completing items 8 and 15 of Standard Form 30, or by separate letter or electronic communication referencing the solicitation and amendment numbers. Failure to acknowledge receipt at the designated location by the specified hour and date may result in rejection of the offer.
The amendment makes three substantive changes to the solicitation: (1) inclusion of additional answers to previously submitted questions in the Questions and Answers Log; (2) addition of Attachment 14 (As Constructed Crane Rail Supports) to the solicitation documents; and (3) clarification that a prefilled form mistakenly selected in Amendment 0004 indicating an extended offer receipt date does not apply, with offers still due at the original deadline. The Questions and Answers Log addresses six contractor inquiries (Questions 58-64) regarding crane specifications, including the new hoist capacity (5 tons), bridge span dimensions, hook height requirements, travel speeds, bridge drive configuration, and existing crane documentation. Answers consistently indicate that the contractor must field verify all interface dimensions and that no existing drawings of the crane are available, directing contractors to Attachment 14 for as-constructed crane rail support information.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B08_Attachment_14_As_Constructed_Crane_Rail_Supports_0005.pdf | ||
| Sol_140A1626B0001_Amd_0004.pdf | ||
| B08_Attachment_13_Steel_Pipes_Memo_0004.pdf | ||
| B08_Attachment_12_Electrical_Service_Revision_0004.pdf | ||
| B08_Attachment_11_WD_ID20260072-02_05182026_0004.pdf | ||
| Sol_140A1626B0001_Amd_0003.pdf | ||
| Sol_140A1626B0001_Amd_0002.pdf | ||
| Sol_140A1626B0001_Amd_0001.pdf | ||
| Sol_140A1626B0001.pdf | ||
| Geotechnical_Report.pdf | ||
| Attachment_10_Pre_Bid_Site_Visit_Agenda.pdf | ||
| SF-25_Performance_Bond_Form.pdf | ||
| SF-25A_Payment_Bond_Form.pdf | ||
| Wage_Determination_ID20260072-01_01302026.pdf | ||
| Drawings.pdf | ||
| SF-24_Bid_Bond_Form.pdf | ||
| Technical_Specifications.pdf | ||
| IEE_Reps.pdf | ||
| SF-1413_Statement_and_Acknowledgement_Form_(Subcontracting).pdf | ||
| Scope_of_Work.pdf |
Show all 20
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: is not is required copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7.ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
PAGESOF
Contractor
The hour and date specified for receipt of Offers to sign this document and return
See continuation page
BIA CENTRAL 00016
12201 Sunrise Valley Drive Contracting Office Mail Stop-244 Reston VA 20192
A16
140A1626B0001
05/07/2026
05/07/2026
1 4
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
140A1626B0001/0005
1. 140A1626B0001 is amended to include additional answers to submitted questions.
Please see the question-and-answer sheet attached to this amendment.
2. Attachment 14 (As Constructed Crane Rail
Supports) has been added.
3. A prefilled form stating that "the hour and date for receipt of offers has been extended" was mistakenly selected in Amendment 0004. As stated elsewhere in amendment 0004, offers are still due at 12:00 PM Eastern on 14 July 2026.
Number Question Answer
What is the confirmed rated capacity of the crane (in tons)?
Section 1.1.B.4 references a possible actual load of "up to 5 tons". Is this the rated hook capacity, or an anticipated operating load below the rated capacity? The capacity of the new hoist is to be 5T.
What is the required bridge span (rail centerline to rail centerline)? The architectural drawings show an overall building width of approximately 24', but the crane rail span isn't explicitly dimensioned in the architectural set.
Contractor to field verify all interface dimensions. See Attachment 14 (As Constructed Crane Rail Supports) for more information.
What is the existing crane's hook height / lift distance, so we can confirm the new "+6 inches" requirement against a baseline? Is there a minimum hook height above finished floor required?
No drawings of the hoist or trolley exist. Contractor to field verify all dimensions.
What are the required bridge travel speed, trolley travel speed, and hoist lift speed? These are referenced as "shown on the drawings" but weren't in the documents provided.
The bridge and trolley travel are to be manually driven with no defined speed. Any references to the travel and lift speeds in Section 41 22 13 are related to the design of the new equipment, not the existing.
Section 2.3.A.1 and 2.3.D.5 describe the bridge as manually operated and controllable from the floor, but Section 2.3.D.9 describes "dual drives, with one drive connected to one wheel of each end truck," which typically implies a motorized bridge. Can you confirm whether the bridge drive is intended to be hand-geared (push) or motor-driven?
Per Section 41 22 13 (2.3) the bridge is to be manually operated and one wheel on each side of the trolley should be driven.
Could you provide the structural drawing set (or the specific crane general arrangement drawing) referenced throughout Section 41 22 13? This should contain the capacity, span, and speed data called out above, plus existing runway rail size/condition information relevant to our rail alignment/replacement scope.
No drawings of the existing crane are available. Any references to the crane capacity, span, speed, rail size in Section 41 22 13 are related to the design of the new equipment, not the existing. See Attachment 14 (As Constructed Crane Rail Supports) for more information.
Questions and Answers Log for IFB 140A1626B0001 Bannock Pumping Plant Rehab
Do you have any existing documentation (cut sheets, as-builts, or a nameplate photo) on the current crane being replaced? This would help us confirm rail size, wheel gauge, and existing hook travel.
No drawings or design data for the existing bridge or trolly exist. All rail size, wheel gage and hook travel are to be field verified by the Contractor. See Attachment 14 (As Constructed Crane Rail Supports) for more information.
| Amendment of solicitation/modification of contract |
| Contract ID code |
| Amendment/modification number |
| Effective date |
| Requisition/purchase requisition number |
| Project number |
| Issued by |
| Code |
| Administered by |
| Code |
| Name and address of contractor |
| Code |
| Facility code |
| Amendment of solicitation number |
| Dated |
| Modification of contract/order number |
| Dated |
| This item only applies to amendments of solicitations |
| Accounting and appropriation data |
| This item applies only to modifications of contracts/orders. |
| This change order is issued pursuant to: |
| The above numbered contract/order is modified to reflect the administrative changes |
| This supplemental agreement is entered into pursuant to authority of: |
| Other |
| Important: |
| Description of amendment/modification |
| Name and title of signer |
| Contractor/offeror |
| Date signed |
| Name and title of contracting officer |
| Signature of Contracting Officer |
| Date signed |
| Previous edition unusable |
| Standard form 30 (rev. 11/2016) |
| Continuation sheet |
| Reference Number |
| Name of Offeror or Contractor |
| OPTIONAL FORM 336 (4-86)) |
Sponsored by GSA FAR (48 CFR) 53.110
Sheet1
File details come from the government source that posted it. Updated .