This document is installation instructions for Roxtec R transit components, including Roxtec R 50 - R 200 frame sizes. It provides details on disassembly, reinstallation, tools required, and recommended torque values for the various frame sizes. The instructions cover how to install the frames around pre-routed cables/pipes, with guidance on cutting the rubber and reassembling the frame. The document also includes a disclaimer from Roxtec regarding certification, liability, and proper use of their system.

The related federal contract opportunity is for the Oscar Dyson FSV Midlife Extension Program, solicitation number 1305M224R0018, issued by the Department of Commerce National Oceanic and Atmospheric Administration. The contract involves providing products and services for the midlife extension of the Oscar Dyson Fishery Survey Vessel. Interested parties can request reference drawings and technical manuals from the Contract Specialist Shawn Griscom.

View the file

Other files

File Type Posted
J.1 NOAA Ship Oscar Dyson FSV Midlife Extension Program Work Specification_Revision-005.pdf PDF
J.7 Government Furnished Material-0001.pdf PDF
1305M224R0018-0006.pdf PDF
1305M224R0018-0005.pdf PDF
Amendment 0005 Tech Manuals - Drawings.zip ZIP file
J.1 NOAA Ship Oscar Dyson FSV Midlife Extension Program Work Specification_Revision-004.pdf PDF
1305M224R0018-0004.pdf PDF
J.1 NOAA Ship Oscar Dyson FSV Midlife Extension Program Work Specification_Revision-003.pdf PDF
J.1 NOAA Ship Oscar Dyson FSV Midlife Extension Program Work Specification-0002.pdf PDF
1305M224R0018-0003.pdf PDF
1305M224R0018-0002.pdf PDF
ROXTEC S Frame - Installation Instructions.pdf PDF
J.1 NOAA Ship Oscar Dyson FSV Midlife Extension Program Work Specification-0001.pdf PDF
1305M224R0018-0001.pdf PDF
J.1 NOAA Ship Oscar Dyson FSV Midlife Extension Program Work Specification.pdf PDF
J.3 NOAA Standard Specifications.pdf PDF
J.10 Schedule of Items and Prices.xlsx XLSX spreadsheet
J.11 Past Performance Information Form.xlsx XLSX spreadsheet
J.15 SF 1418 Performance Bond.pdf PDF
J.14 SF 1416 Payment Bond.pdf PDF
J.4 List of Technical Publications.pdf PDF
J.6 List of Ship Drawings.pdf PDF
J.7 Government Furnished Material.pdf PDF
J.8 Propulsion System Technical Specification.pdf PDF
J.12 Past Performance Questionnaire.docx DOCX document
1305M224R0018.pdf PDF
J.2 Specific Contract Definitions and Work Requirements.pdf PDF
J.5 List of Industry Standards & Public Documents.pdf PDF
J.9 List of Deliverables.pdf PDF
J.13 AIRs Process Document.docx DOCX document
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Installation instructions Roxtec R transit

Components

Roxtec R 50 - R 75 frame Roxtec R 100 - R 200 frame Roxtec Lubricant Roxtec RM sealing modules (not included)

Technical data The amount of torque needed to compress the seal depends on several things, e.g cable or pipe size, amount of used lubricant, aperture size or material in the cable sheath, etc.

Name Aperture dimension Ø (mm) Packing space (mm) Torque (Nm) Tool size (mm)

R 50 50 - 52 30 x 30 4 - 5 3

R 70 70 - 72 40 x 40 6 - 7 10

R 75 75 - 77 40 x 40 6 - 7 10

R 100 100 - 102 60 x 60 6 - 7 10

R 125 125 - 127 80 x 80 6 - 7 10

R 127 127 - 129 80 x 80 6 - 7 10

R 150 150 - 152 90 x 90 9 - 11 13

R 200 200 - 202 120 x 120 9 - 11 13

Disassembly and reinstallation

Untighten the nuts crosswise in small steps. Make sure the nuts are completely loose. Push the front fittings to the sides.

Remove the modules by using a flat tool. Replace any damaged modules.

Clean the inside surfaces of the exposed packing space.

Lubricate the inside surfaces all around with Roxtec Lubricant, es-pecially into the corners. Continue the reinstallation.

4 Tools o Spanner (not included) o Allen key (not included) o Caliper (not included)

To be installed in o Welded sleeves o Bolted sleeves o Cast-in sleeves o Core drilled holes

Pre-routed cables/pipes

R 70 - 75: Disassemble the seal and orientate the fittings making the frame openable.

R 70 - 75: Install the frame around the cables.

R 100: Remove fittings and cut the rubber between screw hole and corner.

R 125 - R 200: Remove fittings and cut the rubber between screw holes.

R 100 - R 200: Wrap the frame around the cables.

R 100 - R 200: Reassemble the frame around the cables.

A rt N o: A

SS20

1 D oc N o: A

SS20

1 rev. I R oxtec ® and M ultidiam eter ® are registered tradem arks of R oxtec in Sw eden and/or other countries.

Disclaimer ”The Roxtec cable entry sealing system (”the Roxtec system”) is a modular-based system of sealing products consisting of different components. Each and every one of the components is necessary for the best performance of the Roxtec system. The Roxtec system has been certified to resist a number of different hazards. Any such certification, and the ability of the Roxtec system to resist such hazards, is dependent on all components that are installed as a part of the Roxtec system. Thus, the certification is not valid and does not apply unless all components installed as part of the Roxtec system are manufactured by or under license from Roxtec (“authorized manufacturer”).

Roxtec gives no performance guarantee with respect to the Roxtec system, unless (I) all components installed as part of the Roxtec system are manufac-tured by an authorized manufacturer and (II) the purchaser is in compliance with (a), and (b), below.

(a) During storage, the Roxtec system or part thereof, shall be kept indoors in its original packaging at room temperature.

(b) Installation shall be carried out in accordance with Roxtec installation instructions in effect from time to time.

The product information provided by Roxtec does not release the purchaser of the Roxtec system, or part thereof, from the obligation to independently determine the suitability of the products for the intended process, installa-tion and/or use.

Roxtec gives no guarantee for the Roxtec system or any part thereof and assumes no liability for any loss or damage whatsoever, whether direct, in-direct, consequential, loss of profit or otherwise, occurred or caused by the Roxtec systems or installations containing components not manufactured by an authorized manufacturer and/or occurred or caused by the use of the Roxtec system in a manner or for an application other than for which the Roxtec system was designed or intended.

Roxtec expressly excludes any implied warranties of merchantability and fitness for a particular purpose and all other express or implied representa-tions and warranties provided by statute or common law. User determines suitability of the Roxtec system for intended use and assumes all risk and liability in connection therewith. In no event shall Roxtec be liable for indirect, consequential, punitive, special, exemplary or incidental damages or losses.”

Note o For optimum reliability, wait 24 hours or longer after installation before exposing the cables/pipes to strain or pressure.

o To be used with: RM modules.

o Cables/pipes shall be parallel to the sleeve/aperture.

o Cable/pipe with a considerable weight needs to be supported to prevent damage or subsidence to the seal.

o Approvals or certificates may include amendments or limitations related to this application.

o The latest version of this and related documents are found at roxtec.com.

Installation R transit

Make or verify an aperture.

Clean the aperture.

Lubricate the frame sparsely on the outside with Roxtec Lubricant.

Insert the frame into the aperture.

Push the front fittings to the sides.

Lubricate the inside of the frame thoroughly, especially into the corners.

Perforate the net prior to routing cables/pipes if applicable.

The net will simplify horizontal installations.

Route the cables/pipes through.

Achieve a 0.1-1.0 mm (A) gap be-tween the two halves when held against the cable/pipe.

A

Adapt the modules by peeling off layers.

The number of layers may not dif-fer (A) by more than one between the corresponding module halves.

A

Lubricate all sealing surfaces on the modules.

Lubricate the sealing surfaces of the spare modules. Do not remove the core.

Insert the modules according to your packing plan. The cables/ pipes shall be parallel to the sleeve.

Push the front fittings back to-wards the center.

Tighten the nuts crosswise in small steps.

7 8

Rubber surfaces bulging and protruding excess lubricant indicate a final-ized transit.

Check additional documentation, if applicable.