J.13 AIRs Process Document.docx
DOCX document 19 KB Posted
- Attached to
- Oscar Dyson FSV Midlife Extension Program
- Solicitation number
- 1305M224R0018
About this file
This document outlines the Additional Item Requirements (AIR) process to be used throughout the performance of the NOAA Ship Oscar Dyson FSV Midlife Extension Program contract, solicitation number 1305M224R0018. The process describes the steps for the contractor to submit a Condition Found Report (CFR) to the Contracting Officer's Representative (COR), the COR's response, and the issuance of an AIR form by the COR to the Contracting Officer. The contractor is then required to provide a quotation for the additional work within 3 days, including an analysis of the impact to the production schedule. The contracting team will review the quote, negotiate if necessary, and issue a Notice to Proceed once agreed upon. To reduce contract modifications, a consolidated modification will be issued to memorialize the agreed-upon AIRs.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
J.13 AIRs Process Document
NOAA EASTERN ACQUISITION DIVISION (EAD)
Additional Item Requirements (AIR) Process for the NOAA Ship Oscar Dyson FSV Midlife Extension Program:
Pursuant to CAR 1352.271-72 ADDITIONAL ITEM REQUIREMENTS (AIR) - GROWTH WORK (APR 2010), the following process shall be used throughout the performance of the contract to execute AIRs. Exceptions to this process are expected throughout the period of performance (PoP) and will be addressed on a case by case basis.
1. Contractor submits Condition Found Report (CFR) to the Contracting Officer’s Representative (COR) and copies the Contracting Team (Contracting). For this contract, Contracting includes Contract Specialist (CS) Shawn Griscom and Contracting Officer (CO) Ashley Perry.
2. COR issues Condition Report Response (CRR) and sends it back to the Contractor and copies Contracting. The response will include:
| a) Acknowledgment of receipt of the Condition Report. |
| b) Additional information and/or comments from the Government, if needed. |
| c) Notice that an AIR will be issued, if needed. |
3. If an AIR is required the COR will send the AIR form to Contracting ONLY. The AIR is an internal document from the COR to the Contracting Officer requesting to add an item to the requirement (contract). Not every AIR will have a related CFR as some represent additional requirements identified by the COR.
4. Unless Contracting has additional questions for the COR, the Contracting Team will issue a Request for Pricing (RFP) to the Contractor.
5. The Contractor shall respond to the AIR with a quotation for the additional work requested within three (3) days of receipt of the AIR. Contractors shall provide proposal to Contracting ONLY. Contractor response to AIR shall include an analysis of the requirements against the production chart and shall include the following additional information:
a. A firm statement concerning impacts to the production chart: This statement shall either confirm that the additional work can be accomplished within the current PoP, or it shall state that the additional work will affect the PoP completion date. In case of the latter, the quote shall note the primary and any secondary work items that would be affected, including an excerpt of the contractor’s planning production chart showing the impact to the project.
b. The contractor shall also provide an analysis and alternative proposal to maintain existing PoP, including such things as alternative procedures, accelerated and/or premium labor efforts, or any other solutions contractor may present to avoid contract PoP extensions.
6. Upon receipt of the quote from the Contractor, the quote will be reviewed by Contracting who will consult with the COR if necessary.
7. Negotiations may take place prior to accepting the pricing to address any issues/concerns that the Government has with the quote (omissions, justification of materials/hours, etc).
8. Once all aspects of the AIR have been negotiated, if necessary, and agreed by both the Contractor and Contracting, the Contracting Officer signs a Notice to Proceed (NTP).
9. Contracting distributes NTP, this AIR is now considered a part of the contract and work can start.
10. To reduce the amount of modifications to the contract, once a number of AIRs have been authorized through an NTP a consolidated modification will be issued memorializing the agreed to AIRs.
1305M224R0018
File details come from the government source that posted it. Updated .