This document is an amendment to a solicitation for drydock repairs to the NOAA ship OKEANOS EXPLORER. The amendment provides responses to vendor questions to clarify the scope of work. Repairs and services include removal and replacement of piping, inspection and repair or replacement of steel plates, radar replacement, electrical breaker maintenance, bunk bed replacement, gauge replacement, and inspection of switchboards, breakers and transformers. The amendment specifies dimensions, clarifies allowable repair methods and locations, and provides additional references and photographs. The solicitation was issued by NOAA's Eastern Region Acquisition office and is for fiscal year 2021 repairs to ready the NOAA ship for future operations.
View the file
Other files
Show 40 more
Latest 50 of 70 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Except as provided herein, all terms and conditions of the document referenced in item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. Name and Title of Signer (Type or Print) 16A. Name and title of Contracting Officer (Type or Print)
15B. Contractor/Offeror 15C. Date Signed 16B. United States of America
(Signature of Contracting Officer)
16C. Date Signed
(Signature of person authorized to sign)
NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV. 10-83)
PREVIOUS EDITIONS UNUSABLE Prescribed by GSA FAR (48 CFR) 53.243
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. Contract ID Code Page of Pages 1 7
5. Project No. (if applicable) 2. Amendment/Modification No.
3. Effective Date 07/17/2020
4. Requisition/Purchase Req. No.
NMAN7200-20-01111
Code AJ930073 7. Administered By (If other than Item 6)
SEE BLOCK 6
6. Issued By
NOAA/EASTERN REGION ACQUISITION
200 GRANBY STREET
SUITE 405
NORFOLK, VA 23510
8. Name and Address of Contractor (No., Street, County, and Zip Code) (X)
X
9A. Amendment of Solicitation No.
1305M220QNMAN0202
9B. Date (See Item 11) July 2, 2020 10A. Modification of Contract/Order No.
10B. Date (See Item 13)
Code Facility Code
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDG- MENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. Accounting and Appropriation Data (if required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACT/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
(x) A. This change order is issued pursuant to: (Specify authority) The changes set forth in item 14 are made in the Contract Order No. in item 9A.
B. The above numbered Contract/Order is modified to reflect the administrative changes (such as changes in paying office, appropriation date, etc.)
Set fourth item 14, pursuant to the authority of FAR 43.103 (b)
C. This supplemental agreement is entered into pursuant to authority of:
D. Other (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. Description of Amendment/Modification (Organized by UCF section headings, including solicitation/contract subject matter where feasible.
X The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended
DRYDOCK REPAIRS TO NOAA SHIP OKEANOS EXPLORER
This amendment is being issued to answer questions in regards to Attachment D1: OKEANOS EXPLORER FY21 DRYOCK REPAIR SPECIFICATION and include additional references.
X
The purpose of this Amendment is as follows:
1. Address questions submitted by vendors.
Q1: Please provide interior pictures of all spaces named in paragraph 3.5.4.1 and the exact pipe sizes and amount to be removed in paragraph 3.5.4.5.
Also indicate the amount of ceiling panels, insulation, interferences in way of all work.
A1: This additional reference has been therefore added to the RFQ. Reference
15 is attached.
Q2: Please provide interior pictures of all spaces to be affected in item 3.8 and indicate the amount of ceiling panels, insulation, interferences. Paragraph
3.8.4.3 has no interferences? Paragraph 3.8.4.4 has no interferences?
A2: Contractor should anticipate no interference for 3.8.4.3 other than getting stell into and out of the tank. For 3.8.4.4, contractor should anticipate no
"hot work" interferences, but will need to get the steel plates into and out of the from under Engine Room grating. This additional reference has been therefore added to the RFQ. Reference 16 is attached.
Q3. Paragraph 3.19.4.7.4 indicate potable water tanks to be addressed but do not give any dimensions. The accompanying sketch indicates several inserts and the paragraph 3.19.4.7 identifies several interferences that are not depicted on the sketch. See below. Paragraph 3.19.4.8 indicates there are 15 inserts not 2, as in 3.19.4.3. Paragraph 3.19.4.2 identifies the large inserts but provides no dimensions. Please clarify the interferences, need for staging, gas freeing requirements and provide pictures of all intended areas for inserts to be installed.
A3. The two large rectangles are approximately 10 feet by 16 feet. This additional reference has been therefore added to the RFQ. Reference 17 is attached.
Q4: Item- 3.27 Radar Replacement.
In regards to 3.27.4.2.7 -- Please provide more info in the nature of the informal training during sea trial.
A4: The Training shall be up to 12 hours (as specified in 3.27.4.2.7) for up to
8 crew. The training shall be operational in nature and show the crew how to use the new radars and highlight any notable operational difference between the new and old units.
Q5: Para- 5.24.4.4---- Rack out, remove arc chutes, inspect contacts, clean, lubricate and adjust the following circuit breakers, (breakers are needing to be removed from ship and serviced in an authorized breaker shop.)
Question- Is your intent in this work scope to be removed to an authorized breaker shop?
A5: Not necessarily, if work can be done by a field engineer who has experience with similar GE plant components, that field engineer can be used. The name and contact info of an acceptable source can be provided if needed.
Q6: Para- 5.24.5.2---- All switchboard, breakers, panels and transformers will be jointly inspected by the contractor and COR prior to acceptance.
Question- Please describe what panels in this item-5.24 that are required to be inspected prior to acceptance?
A6: A joint inspection will be of the equipment affected by this item (Listed in
5.24.4.1, 5.24.4.4 and 5.24.4.5)
Q7: 5.22 Bunk Replacements
42” (is this outside dim?) wide double bunks to match the existing bunks on onboard the Okeanos Explorer.
A7: Yes, outside dimensions (an inch or two either way is acceptable)
Q8: What are the other dimensions of berth (total height, length, height of tubs, space between tubs, drawer base dims, sub base dims)?
A8: This additional reference has been therefore added to the RFQ. Reference
18 is attached.
Q9: New beds shall have 3 drawers under bottom bunk and a single ladder.
New beds shall be installed in same location as existing with final location approval provided by COR. What are desired drawer width, height and depth? Do they need to be lockable?
A9: Drawers do not need to be lockable. Drawers should be approximately
18.5"L, 25"wide and 4.5"tall.
Q10: 5.22.4.4 Bed color shall be same as existing. We can get close but probably not exact. Do you have paint info.?
A10: A paint color that is close is acceptable.
Q11: 5.22.4.5 Repair all affective base trim, flooring, paint and insulation.
What are the amounts expected to need repairing? Will the bulkheads need repairing? Are the bases bolted or welded? Are there any existing drawings?
A11: Beds are bolted to welded studs on the deck.
Q12: New bunk beds shall be the same approximate height as existing. What is the height?
A12: Approximately 54 inches.
Q13: Please provide missing reference listed below. Base Item- 3.21, Reference-3.21.2.1 Technical Manual T9568-AC-MMO-010---- Main
Propulsion Motors, Bow Thruster Motors, Ship Service Transformers.
A13: The additional reference has been therefore added to the RFQ. Reference
OE_235_01_Manual is attached.
Q14: What is the required Pressure scale, Pressure/Vacuum scale, Gauge/Sensor scale, Thermo-gauge scale for all gauges list?
A14: Use the below list (and the size in the 4th column should supersede the spec)
SERIAL
NUMBER
LOCATION RANGE SIZE
T-116 Winch Room SW 0-250F 3" Face every angel
T-112 U/L air cooler 0-250F 3" Face every angel
T-93 Thruster HPU 0-250F 3" Face every angel
T-94 Thruster HPU 0-250F 3" Face every angel
M-124 Geny room 0-160psi 2.5"
M-209 Geny room 0-160psi 2.5"
T-43 AC Flat neg 40 to 120F 3" Face every angel
M-144 Geny room 0-200psi 2"
M-145 Geny room 0-200psi 2"
M-119 Distiller 30-0-60psi 2.5"
M-40 geny 4 30-0-30psi 4.5"
M-43 geny 2 30-0-30psi 4.5"
M-46 geny 3 30-0-30psi 4.5"
M-204 0-30psi 2.5"
M-229 0-200psi 4"
M-235 0-160psi 2.5"
M-23 0-150F 3" face Back
E-10 SSDG 1 amps 0-1000AC Amps 0-1mA DC input
E-121 Fire main eos 0-120psi 0-10VDC input
M-219 EDG 0-100psi 2"
T-10 SSDG 2 jw 50-300F 3" Face every angel
T-56 SSDG 1 JW 50-300F 3" Face every angel
T-67 SSDG 2 CAT 4W2683
T-66 SSDG 1 CAT 4W2683
T-81 SSDG 3 CAT 4W2683
E-122 TLI 0-200 Micro DC amps 4-72-3
E-48 TLI 0-200 Micro DC amps 4-80-2
M-41 Geny room 0-160psi 2.5"
M-129 gen room 0-200psi 2.5"
M-250 U/L air cooler 0-400psi 2.5" m-157 fan tail 0-400psi 2.5" m-238 frb deck 0-5000psi 2.5" m-158 frb deck 0-5000psi 2.5" m-236 frb deck 0-6000psi 2.5" m-237 frb deck 0-6000psi 2.5"
M-202 Winch Room 0-6000psi 2.5" m-35 scullury 0-100psi 2.5" m-19 prop room 30-0-30psi 2.5" m-179 prop room 30-0-60psi 2.5" m-177 prop room 30-0-60psi 2.5"
M-246 prop room 0-100psi 2.5"
M-247 prop room 0-60psi 2.5" m-248 prop room 30-0-30psi 2.5" m-130 gen room 0-400psi 4"
M-206 winch rm 0-6000psi 2.5"
T-95 prop room 0-200F 3" Face every angel
M-253 winch room 0-100psi 30-0-100psi
M-233 geny 30-0-60psi 2.5" m-112 gen 0-160psi 2.5" m-240 l/l 0-30psi 2.5" m-241 l/l 30-0-30psi 2.5" m-25 l/l 30-0-30psi 2.5" m-217 bow thruster 0-5000psi 2.5" m-93 bow thruster 0-4000psi 2.5" m-94 bow thruster 0-4000psi 2.5" m-193 winch room 0-5000psi 2.5" m-252 winch room 0-6000psi 2.5" m-254 winch room 0-6000psi 2.5" m-197 winch room 0-5000psi 2.5" m-204 winch room 0-600psi 2.5" m-151 Geny room CAT 4W510 m-222 Geny room 0-60psi 2.5" m-142 Geny room 0-100psi 2.5" m-13 Geny room 0-60psi 2.5" m-148 Geny room 0-30psi 2.5" m-152 Geny room 0-400psi 4" m-47 Geny room 0-160psi 2.5"
M-232 Geny room 0-100psi 2.5"
M-212 AC Flat 30-0-300psI 2.5
M-39 Geny room 0-400psi 4"
Q15: WI 5.22 Bunk Bed Replacement. Do the bunk beds need to satisfy the
Buy American Act? Could you provide a source to get a quote? Possible sources
A15: Yes; Possible sources - Jamestown, U.S. Joiner
Q16: Please provide interior pictures of all spaces to be affected in item 3.19.
Also indicate the amount of ceiling panels, insulation, interferences involved.
A16: This additional reference has been therefore added to the RFQ.
Reference 17 is attached.