AMC-505-1B, Valve Overhaul and Test

PDF 29 KB Posted

Attached to
FY20 DRYDOCK REPAIRS TO NOAA SHIP GORDON GUNTER
Solicitation number
1305M219QNMAN0345
Issued by

About this file

ATTACHMENT D: REFERENCE DOCUMENT

View the file

Other files

File Type Posted
SBE38_mounted_at_Sea_Chest_2396.jpg JPG image
5987226_B_Bulwark_Misc_Structure_Dets.pdf PDF
SBE38_mounted_at_Sea_Chest_2395.jpg JPG image
6233545_C_Scantlings_FSCLE___above.pdf PDF
6233544_D_Scantlings_MN_DK___Below.pdf PDF
67071A-PN50244-SBE38-External-Temp-Mount-Kit.pdf PDF
aft_stbd_chock.JPG JPG image
Amendment_0003.pdf PDF
GU_FY20_Drydock_Spec_August_Ch-2.pdf PDF
chock_foundation_steel_thickness.JPG JPG image
TLI_Sys_ISO_EWD.pdf PDF
GU_342_6629785_MN_Engine_FW_Cooling_System_Diagram_MARK_UP.pdf PDF
Amendment_2-1305M219QNMAN0345.pdf PDF
6233772_C_Carpet_AD.pdf PDF
6630021_A_Plumb_Drains_Sewage_Sys_Dia.pdf PDF
winch_control_base.JPG JPG image
6233974_D_NBC_Washdown_Sys_Arr.pdf PDF
GU_FY20_Drydock_Spec_August_Ch-1.pdf PDF
6233663_P_One_Line_Diagram.pdf PDF
6233845_F_Overflow_Vent_Sounding_Tubes_T-13_Class.pdf PDF
6629795_-_Overflow_Vents_Sounding_Tube_Diagram.pdf PDF
Life_Raft_Certs_2018.pdf PDF
AMENDMENT_0001.pdf PDF
6233773_E_Storerooms_Lockers.pdf PDF
6629807_-_One_Line_T-18.pdf PDF
6233816_E_Fuel_Fill_and_XFR_Sys_Dia.pdf PDF
6233779_C_Modular_Bath_Arr_Det.pdf PDF
6629791_-_Weather_Deck_Drain_Diagram.pdf PDF
GU_Immersion_Suit_Inspection_2019.pdf PDF
Foc'sl_chair_stand.JPG JPG image
Gordon_Gunter_Updated_FF_Inspection.pdf PDF
6233754_E_Joiner_Arr_Upper_Dk.pdf PDF
winch_control_boxes_1.JPG JPG image
Price_Schedule.xlsx XLSX spreadsheet
GU-555-001--.pdf PDF
512-6233800.pdf PDF
drw_DCU-housing-200x200x120.pdf PDF
573-2, Overhaul-Repair of Hydraulic Cylinders.pdf PDF
s1205.pdf PDF
GU_342_6629792 Diesel Engine SW Cooling Sys Diagram.pdf PDF
6233582_B Zinc Arr _ Details.pdf PDF
GU_FY20_Drydock_Spec_AUG_2019.pdf PDF
GU-512-003 Revision B.pdf PDF
GU-512-004 Revision A.pdf PDF
533-1.pdf PDF
528-6233893 Plumbing Drains Above Main Deck.pdf PDF
085-6233567 General Arrangement Fcsle Dk _ Above - Copy.pdf PDF
GU-801-001.pdf PDF
520-001 Science SW System Revision A.pdf PDF
ATTACHMENT_D.5_SUBCONTRACTING_PLAN_AS_WORD_DOC.doc DOC document
Show 40 more

Latest 50 of 104 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMC-505-1B

AUGUST 1995

SUPERSEDING

AMC-505-1A

SEPTEMBER 1990

NATIONAL OCEANIC AND ATMOSPHERIC ADMINISTRATION (NOAA)

ATLANTIC MARINE CENTER

STANDARD SPECIFICATION AMC-505-1B

VALVE OVERHAUL AND TEST

1. SCOPE. This specification contains the general requirements for overhaul and test of valves on and for NOAA ships and boats.

2. REFERENCES.

None

3. REQUIREMENTS.

3.1 Standard Overhaul. Overhaul all specified valves as

follows:

3.1.1 Except for valves which have welded ends preventing

removal without cutting the welds, or unless otherwise specified in the detail specification or other applicable procurement document, remove all specified valves from the ship or boat to a suitable machine shop for overhaul and tests. Specified valves which are not removed from the ship or boat shall be overhauled in place. See paragraph 3.2 for special requirements for sea valve removals.

3.1.2 Tag each valve prior to removing from the ship or

boat.

3.1.3 Completely disassemble each valve. Matchmark valve

parts. Thoroughly clean bonnets, stems, discs, gates, globes, seats, bodies, and other metal parts to bright metal.

3.1.4 Deleted.

3.1.5 Clean and chase all valve stem threads. Check stems

for straightness. Straighten stems to within 0.002 inch total indicator runout (TIR). Polish stems to a 32 Root-Mean-Square (RMS) finish in way of packing surface and remove all raised edges.

3.1.6 Visually inspect all parts, including all fasteners, for deterioration and other defects. Clean, dress, and true gasket mating surfaces.

3.1.7 Check the disc-to-seat, globe-to-seat, and plug-to-

bore contact fits using the bluing transfer method. Machine, grind, lap, spot-in, and recheck contact fits as necessary to obtain the following contacts:

a. Globe, globe angle, and globe stop-check valves shall have a 360-degree continuous globe-to-seat contact with a bluing transfer line not exceeding 1/16-inch width.

b. Gate valves shall have a 360-degree continuous gate-to-seat contact with a bluing transfer line which does not exceed 3/16-inch width. The transfer line shall appear within the lower 50-percent of the gate seating surface at the top and bottom of the gate.

c. Plug valves shall have a minimum 80-percent plug-to-bore surface contact, evenly distributed over 100-percent of the area.

d. Swing-check valves shall have a 360-degree continuous disc-to-seat contact.

3.1.8 If unable to obtain the above specified contact fits

by machining, grinding, and lapping, renew the globes, plugs, discs, gates, and renewable seats. Contractor may, at their option and at no additional cost to the Government, renew globes, plugs, discs, gates, and renewable seats after initial inspections and before machining, grinding, or lapping the existing parts to obtain the required contact fits.

3.1.9 (Modified and relocated to section 3.2)

3.1.10 Reassemble each valve. Insure that discs, gates, and plugs are in the half-open position during reassembly to avoid damaging seats or bending stems. Renew all gaskets, fasteners, rubber seals, and non-metallic seats. In butterfly valves, renew boots, o-rings, o-ring fasteners, and teflon bushings. Renew valve stem packing in feed water, condensate, and steam valves with packing conforming to MIL-P-24503 and DOD- P-24583. Renew valve stem packing in all other valves with packing conforming to MIL-P-24396, Type B.

3.1.11 Prior to disassembling and overhauling a valve, the

Contractor may, at their option and at no additional cost to the Government, renew the valve with an identical valve. If this option is exercised, the new valve must be tested and meet the same acceptance criteria as prescribed herein for overhauled valves. If a valve is determined after disassembly to be nonrepairable, the Government will negotiate an equitable cost adjustment, limited to the difference between the cost of the new valve and the costs which would have been incurred had the valve been overhauled. For valves of 3-inch IPS size and below, the cost adjustment will be limited to the costs incurred associated with disassembling the valves.

3.2 Additional Sea Valve Requirements.

3.2.1 Inspect all studs, bolts, and nuts in line and bonnet

flanges of non-ferrous sea valves to determine the material. If the fasteners are not nickel-copper (Monel), submit a Condition Report giving the actual material, condition, and recommendations.

3.2.2 Coat the interior of each steel valve, excluding

seating and polished surfaces, with the same epoxy primer used on the underwater body.

3.2.3 Remove all waster pieces and spool pieces installed

between the sea valves and the ship's hull. Thoroughly clean the waster and spool pieces, and inspect for deterioration or other defective conditions. Inspect all fasteners and submit a Condition Report same as specified above for sea valves.

3.2.4 Whenever a transducer sea chest valve is required to

be removed for overhaul, extreme care must be taken to prevent damaging the transducer assembly. Remove and reinstall the transducer assembly in accordance with the transducer manufacturer's technical manual, a copy of which will be provided by the COTR within 48 hours after requested.

3.3 Tests. After reassembling or renewing, conduct hydrostatic tests of each valve as follows:

3.3.1 All tests shall be performed using clean water as the

test medium. Unless otherwise specified, the test pressure shall be 150-percent of the maximum operating pressure of the system from which the valve was removed, but not less than 50 pounds-per-square-inch-gage (psig).

3.3.2 With the valve in the open position, test each valve

body for 10 minutes. No leakage is allowed.

3.3.3 Seat each plug and butterfly valve with hand force.

Seat all other valves using the torque values listed in the following table as the maximum allowable seating force applied to the handwheel.

Total Tangential Force Handwheel Diameter (pounds) on Rim of Handwheel

2 inches and below 90 3 inches 98 4 inches 106 5 inches 112 6 inches and greater 118 plus 3 pounds for each inch above 6, not to exceed 150 pounds.

3.3.4 Test each globe, angle globe, and globe stop-check

valve by applying test pressure in the direction tending to open the valve. Test each butterfly, gate, and plug valve by applying test pressure alternately on both sides of the disc, gate, or plug. Hold test pressure for a minimum of 3 minutes if there is no evidence of leakage. If there is evidence of leakage, hold the test pressure and measure the leakage rate.

3.3.5 Test each globe stop-check valve and swing-check

valve by applying test pressure in direction tending to close the valve (back pressure) for a minimum of 5 minutes. If leakage occurs, hold the test pressure and measure the leakage rate.

Globe stop-check valves shall be tested with stems in the open position. The test back pressure for valves having a pressure rating of 150 psig and below shall be 50 psig, and for valves having a pressure rating over 150 psig shall be 100 psig.

3.3.6 The seat leakage shall not exceed the following:

a. Check valve back pressure tests -- For valves up to and including 2 inches, the leakage rate shall not exceed 25 cc/hour/inch diameter. For valves 2-1/2 to 10 inches, the leakage rate shall not exceed 50 cc/hour/inch diameter. For valves over 10 inches, the leakage rate shall not exceed 100 cc/hour/inch diameter.

b. Soft-seated valves -- No leakage shall be permitted.

c. Metal-to-metal seated valves -- For valves less than 1 inch, the leakage rate shall not exceed 10 cc/hour. For larger valves, the leakage rate shall not exceed 10 cc/hour/inch of nominal pipe size.

3.3.7 Any valve which fails a seat leakage test shall be

renewed or overhauled and retested until an acceptable test is performed.

3.4 Reinstallation. After tests have been accepted by the COTR, reinstall each valve, using new flange gaskets.

4. QUALITY ASSURANCE.

4.1 Prior to requesting the COTR to witness the final bluing

contact inspection or the final acceptance hydrostatic tests of a valve, the Contractor shall perform preliminary inspections and tests which meet the acceptance criteria stated above.

4.2 After acceptable preliminary inspections and tests have been conducted, the Contractor shall notify the COTR and conduct final acceptance bluing contact inspection and final acceptance hydrostatic tests of each valve in the COTR's presence.

END OF SPECIFICATION