Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
1 2
2. AMENDMENT/MODIFICATION NUMBER
A0011
3. EFFECTIVE DATE
04/17/2019
4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
USDA FOREST SERVICE
PACIFIC SOUTHWEST REGION
1323 CLUB DRIVE
VALLEJO, CA 94592-1110
SAME AS ITEM 6.
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER
1291S819R4002
9B. DATED (SEE ITEM 11)
02/22/2019
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return 1 copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Amendment A0011 is for the purpose of providing technical response to RFI 12.
The offer due date/time is unchanged. Offers are due NLT Thursday, April 18, 2019, 2pm/1400 PST.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
Jeremy Bedner, Contracting Officer
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
04/17/2019 (Signature of person authorized to sign)
Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
Amendment A0011
04/17/2019
RFP 1291S819R4002
LOS PRIETOS FIRE ENGINE GARAGE CONSTRUCTION
SANTA BARBARA RANGER DISTRICT, LOS PADRES NATIONAL FOREST
US FOREST SERVICE
The following is the revised technical answer to RFI 12. General answer provided via prior amendment 10 A0010.
12. Floor Plans on A1 show two different rooms numbered 110: "Cache 110" and "Workstation 110." On the interior finish schedule (A5), only "Workstation 110" is shown. Concrete flatwork plan 1/A4 shows only "Cache 110." When the finish schedule refers to acoustical ceiling tile and cedar base in the Dayroom, please clarify whether this refers to the entire "Dayroom/Workstation" area (as it is referenced in B/A7) or rather to only the portion between gridlines 2 and 3 (as suggested by the floor plan).
ANSWER VIA AMENDMENT 9.
This information to be provided following proposal receipt if necessary IAW FAR 15.306 – Exchanges with offerors after receipt of proposals.
REVISED TECHNICAL ANSWER.
Acoustic ceiling tile and cedar base is to be provided for the entire “Dayroom/Workstation” area between gridlines 1 and 3.
| SF-30 A11 |
| 11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS |
| 13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14. |
| Amendment A0011 is for the purpose of providing technical response to RFI 12. |
A11 CONTINUATION