J-2 FrankLakeRoad213RxSummary.pdf

PDF 133 KB Posted

Attached to
USFS Region One/Region Four Mechanical Thinning IDIQ
Solicitation number
1284LM22R0006
Issued by

About this file

This document provides details for a silviculture prescription and excavator piling task order to be conducted on 69 acres in Unit 213 of the Frank Lake Road unit in Montana. The task order is part of the Region One/Region Four Mechanical Thinning IDIQ, which will solicit offers for mechanical tree thinning, slash treatment, and other fuels reduction activities on National Forest lands. Work under the IDIQ will primarily involve heavy machinery but may include some manual labor. For the task order, thinning will reduce smaller diameter Douglas fir and other trees to retain larger, well-spaced ponderosa pine and western larch. Cut material will be bucked into lengths under 10 feet. Post-thinning, an excavator will pile slash concentrations over 8 feet in height and 12 feet in diameter, leaving 5-10 tons of coarse woody debris per acre, with larger pieces preferred. Piles must avoid leave tree areas and unit boundaries.

View the file

Other files

File Type Posted
Correct Call in number .pdf PDF
J- 2 FrankLakeAlkaliLostLake_UnitMap.pdf PDF
J-3 LittleSnowy HLF 08 Mechanical vicinity map.pdf PDF
J-11 WD 1977-0030 Rev 62 03152022 UT.pdf PDF
J-2 KootenaiFoodStorageOrder.pdf PDF
J- 2 RabbitTracksVicinityMap.pdf PDF
J- 1 Crestline QASP.pdf PDF
J-2 Item2_3_4_5_VicinityMap.pdf PDF
J- 2 QRCodes_RabbitTracks_Maps.pdf PDF
J-2 AlkaliFuelsRxSummary.pdf PDF
J-3 Food Storage Order.pdf PDF
J-3 MAP.pdf PDF
J-12 WD 77-0727 (Rev 66 03_15_2022 CA.pdf PDF
J- 3 Seed TO 3 Little Snowies.pdf PDF
J-4 Thinning Inspection Plot Form.pdf PDF
J-2 HagadoreFrassRxSummary.pdf PDF
J-5 Sample Thinning Inspection Plot Form.pdf PDF
J- 2 RabbitTracksUnitMap.pdf PDF
J-13 WD 1976-1342 Rev 69 03_15_2022 MT.pdf PDF
J-7 Equipment Evaluation Form.pdf PDF
J- 2 Summary_Info_Chart.pdf PDF
J- 3 Little Snowy HLF-08 Mechanical Treatment Units.pdf PDF
J-2 HagadoreFrassUnitMap.pdf PDF
J-10 WD 1969-0113 Rev 67 03152022 NV.pdf PDF
J- 2 Rabbit Tracks RxSummary.pdf PDF
J-6 Sample Forest Camping Permit.pdf PDF
J-3 Summary Information Chart.pdf PDF
J- 3 LittleSnowiesRx_Summary.pdf PDF
J-8 WD 1995-0228 Rev 53 03152022 ID.pdf PDF
J- 2 Seed TO 2 Kootenai NF.pdf PDF
1284LM22R0006 Final.pdf PDF
J-1 Seed TO 1 Crestline.pdf PDF
J-9 WD 1979-0948 Rev 61 03152022 WY.pdf PDF
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SILVICULTURE SUMMARY PRESCRIPTION Item No. 3 Acres: 69 Acres Excavator Piling Seed Task Order Number 2 Task Order Name: Kootenai Fuels Project Unit Name: Frank Lake Road Unit 213

Location – Approx. 2.5 miles south of Eureka, MT.

Legal –T36N R27W Southwest Corner of Section 25 Average Stand Age – 60-120 years Average Slope – 5-20% Average Tree Height - 80 feet Average Aspect – Variable

THINNING WORK IS NOT PART OF THIS ITEM NUMBER. Thinning work conducted by Forest Service employees may not be completed at the time this Task Order is issued. Silvicultural Prescriptions are given in order for perspective bidders to more accurately estimate post thin fuels loads that will be excavator piled under this Task Order. THINNING WORK IS NOT PART OF THIS ITEM NUMBER.

THINNING PRESCRIPTION: Intermediate – Thin from below.

• Cut nearly all 7” and smaller DBH Douglas fir

• Cut Douglas fir up to 10” dbh where the are growing within 20-30’ of large overstory PP or WL.

o Trees 7” dbh or less to retain are rare but may include:

Well-formed Ponderosa Pine and Western Larch and occassional high quality Douglas fir (long and broad crowns, pointy tops) where not acting as ladder fuels or directly competing with a neighboring higher quality tree.

If multiple nice small trees are present in an area, thin to 5-15’ spacing.

• Trees designated for removal shall be cut below the lowest live limb, except when prevented by natural obstacles. All live limbs below the cutting point shall be removed. Trees shall be completely severed from the stump. Stumps shall be cut at or below 6 inches above ground level on the uphill side and shall be cut horizontally, not slanted.

• Designated cut trees shall be felled away from unit boundaries or roads. Any trees falling on such areas shall be removed. All thinning slash shall be placed on or near the ground surface, so that it is not leaning against or suspended by an uncut tree, stump, log, or any obstacle.

• Do not cut snags. Snags shall be defined as all standing dead trees of any species greater than

10” DBH and 20’ tall or taller.

• Buck fuels created through thinning activities into lengths less than 10 feet, and buck the top from the remainder of the tree at a 4 inch diameter. Buck pre-existing downed fuels into lengths less than 10 feet, up to a diameter of 7 inches, and leave the remainder of the tree larger than 7 inches diameter unbucked.

EXCAVATOR PILE: Excavator piling shall be completed on Item 3-1 in accordance with the specifications from the R1R4 Mechanical Fuels Treatment IDIQ. Acceptable equipment for slash piling is an excavator equipped with a bucket and a thumb approved by the Contracting Officer. Other equipment may be approved in writing by the Forest Service. Unit boundaries are marked it pink flagging.

• Excavator Piling shall include piling of all fuel concentrations generated by slashing and natural accumulations of fuels within the unit boundary. A slash concentration is defined as an area where the amount of slash in a 50-foot radius area or smaller, is sufficient to build a pile that meets contract specifications. Piles shall be constructed to facilitate full consumption when they are burned.

• Leave an average of 5-10 tons per acre of down coarse woody debris. The most desirable coarse woody debris shall consist of logs >10” diameter and greater than 10’ in length where they exist. In areas where larger diameter logs are not present, acceptable coarse woody debris will be material greater than 4 inches diameter on the small end and longer than 3 feet in length. In all areas, the larger diameter pieces are more desirable than smaller diameter pieces needed to meet this requirement.

• Piles shall be located outside of live residual/leave tree driplines, in openings or areas of low tree densities. Piles shall be kept as far away from designated leave trees as feasible--a minimum of 15 feet where possible, or as mutually agreed to by the Contractor and the Government, to minimize damage to residual trees when the piles are burned. Piles shall be located at least 10 feet from unit boundaries.

• Piles shall be constructed no more than 12 feet in diameter, and no less than 8 feet in height (tall and compact, not sprawling is desired), shall be constructed compact and free of dirt and duff, shall have a good base to prevent the pile from toppling and shall not be made on down logs, rotten stumps or rocks.

Material shall be piled in a parallel configuration, similar to pencils in a box. Once a pile meets the maximum diameter and minimum height; slash may be added vertically on the edge of a pile to prevent the pile from toppling. All objects which extend more than 2 feet in any direction from the pile profile shall be cut off and returned to the pile. No stumps shall be placed in piles.

• All excavator piling shall be conducted in such a manner as to allow operations without damaging residual live trees. All standing trees shall be retained in an undamaged condition. At the discretion of the Contracting Officer, concentrations of fuels may be left un-piled if it is deemed that piling operations will damage the remaining live trees. Placement of piles shall be in such a manner to not damage road surfaces or road drainage structures. No slash shall be left within 5 feet of culverts, nor on trails, roads or fill-slope after piling.

All Other Considerations

(1) Minimize damage to the leave tree boles.

(2) Any tree designated for retention that poses a safety hazard may be felled by the contractor without prior approval of the Forest Service. All such hazard trees felled to provide for safe work conditions will remain adjacent to the stump.

(3) Excavator piling operations shall be conducted when soil moisture is 18% or less or on frozen ground.

(4) Prior to project implementation any off-road equipment used shall be weed washed and inspected.

(5) No timber products may be hauled from contract area under this Task Order.

(6) Protect all survey monuments.

(7) Road damage as a result of the Contractors operations shall be repaired by the contractor at no expense to the government.

(8) Slash shall not be left on the roadways or in ditches. All woody debris shall be removed from the road surface and ditch immediately to prevent the disruption of traffic or the blocking of water flow.