This solicitation seeks proposals for a center pivot irrigation system installation project. Contractors must attend a mandatory site visit on either February 21st or 22nd to be eligible to bid. The work includes installing new center pivot irrigation systems on four existing fields, upgrading an existing river pump site including installing a new pump and manifold, and modifying irrigation piping. Proposals are due by March 7th, 2024. The federal agency issuing this solicitation is the USDA Agricultural Research Service Plains Area Field Research Implementation and Information Delivery office.

The document also includes questions and answers related to amendment 0003 of the solicitation. Key clarifications provided include specifying a larger pump model for the river pump site, confirming GPS positioning is required for all center pivots, and stating the contractor is responsible for obtaining any required railroad right-of-way permits.

View the file

Other files for this federal contract opportunity

Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

12805B24R0009 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

ARS-12805B

FORT COLLINS CO 80526

BLDG D, SUITE 300

2150 CENTRE AVENUE

USDA ARS PA AAO ACQ/PER PROP

03/05/20240003

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

02/07/2024

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return _______1___________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The purpose for this amendment is to provide questions and answers for amendment 0003. All other aspects remain unchanged.

Attachment titled "Amendment 0003 Questions and Answers" is hereby incorporated into the

RFP.

Q1: Based on the contract documents posted on the SAMS site the new river pump has been specified to be a "Cornell - 8NHTR-VC18DB with 300 HP".

During the site visit I had originally had some concerns about utilizing a centrifugal pump for this project because of the amount of suction lift. Currently all three existing pumps

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

KELLY D. WRIGHT

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 5

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

12805B24R0009/0003 are vertical turbine self priming style pumps.

Based on the quote received today from Cornell

Pump Company the specified pump will not be able to be mounted on the existing I beam pump mount.

The manufacturer stated this pump will only provide 2 to 2.5' of suction lift allowed. The original email from the manufacturer is attached.

A field measurement was taken at the site visit from the existing mounting surface to the water level of 12' 7". If the pump was mounted on the existing pump platform it would not function at the current river level based on the suction requirements.

It is possible to use this pump by building a lower mount inside the pump structure however it will be subject to flooding with river fluctuations.

A1: Due to the observed historical river gage height fluctuations, and in consideration of additional field measurement information presented by industry following required site visits, a larger pump is now specified.

Contractor¿s shall build proposals to install

Cornell Pump Size 10NNT-F18DB 350 HP, in lieu of the previously specified 8NHTR-VC18DB.

Q2: Its it possible of an alternative pump may be accepted as we do not expect that the specified pump will work properly for this application?

A2: : Contractor¿s shall build proposals to install Cornell Pump Size 10NNT-F18DB 350 HP, in lieu of the previously specified 8NHTR-VC18DB.

Q3: The quantities for the River Manifold material list do not match the quantities specified in the spec section.

A3: For bid purposes, contractors shall utilize the design criteria provided in the River Pump

Site Equipment Specifications section 1.02, section G & H for specifics on manifold requirements.

Q4: There is no information on the modifications needed to the existing Pump House. The manifold and Pump House work is a significant portion of

Option 1 without additional information it is impossible to estimate this cost.

A4: Contractors shall reference River Pump Site

Equipment Specifications section 1.02, section L and provide bids commensurate with

Continued ...

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

3 5

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

12805B24R0009/0003 perceived/evaluated necessary modifications to provide a fully functional system.

Q5: The wiring in the existing pump house will need to be updated but there is no information what is currently there.

A5 : Contractors shall reference River Pump Site

Equipment Specifications section 1.02, section K and provide bids commensurate with observed up-grades needed to the existing wiring layout/platform in order to facilitate a fully functional system specified in the Government¿s solicitation.

Q6: Another item I do not see addressed is working within the railroad right of way. From past experience getting the proper permit can be a very long process which would affect the 180 day completion time frame.

A6: Based on the project scoping and locations of proposed systems, USDA, ARS does not anticipate a

BNSF Right of Way to be required for the North

Line pipeline, however, if permitting is required, the construction contractor shall be responsible for obtaining required permits. USDA will allow for contract time extensions as required for procurement/obtaining any required permit for Right of Way.

Q7: 2024 Season Flood Operation- Per site visit it was stated that construction may impede this season's irrigation operations. Will it be acceptable to stop irrigation operations for the entire contract period?

A7: In consideration of the climate at the Miles

City site, construction performance will need to occur during irrigation periods, and thus, irrigation operations will not occur during the performance period of the awarded contract.

Q8: Yaskawa 300HP VFD - Is the river pump drive required to be in an enclosure with Main Circuit

Breaker?

A8: Yes.

Q9: BNSF Right of Way - Per Q/A Amendment, ROW was stated to be 200' from the centerline of

Railroad tracks. If a permit is required for the

North Line pipeline will USDA obtain ? Will contract time be extended to allow for

Continued ...

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

4 5

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

12805B24R0009/0003 procurement of BNSF permitting process?

A9: Based on the project scoping and locations of proposed systems, USDA, ARS does not anticipate a BNSF Right of Way to be required for the North Line pipeline, however, if permitting is required, the construction contractor shall be responsible for obtaining required permits. USDA will allow for contract time extensions as required for procurement/obtaining any required permit for Right of Way.

Q10: Remote Pump Control - Is the River pump vfd required to be controlled directly by ALL center pivot control panels ? Option II does not show any Pivot radios to pump site. Is buried wire control acceptable?

A10: Yes, the pump vfd installed shall have the ability to be controlled by all center pivot panels. Radio, cellular modem, buried wire are all acceptable forms of telemetry.

Q11: River Manifold - Per River Pump Site Spec -

G. - It is stated that both flood and pivot irrigation must be able to take place at the same time. Does the manifold have to feed the existing

15" and 24" lines simultaneously for flood operation while also feeding the new North line option #1 with pivot pressure?

A11: Yes. Both aforementioned lines will require simultaneous operation and contractors shall bid for the manifold to feed both lines at the same time.

Q12: Screen System - Per River Pump Site Spec -

N. - "Screen will need to be self cleaning" What flow rating is required for the screen system?

Is modification to the existing trash rack acceptable? Or is a new screen system required?

A12: The scope concept was for modifications to occur to the existing system, however contractors are allowed to install a new system if deemed necessary. The final system shall be self cleaning. Flow rating is not required.

Q13: Materials List - Option I (Clin 0002) -

Irrigation Ditch Shut Off Valve - Per the site visit, a 20" Buried Valve will be required to isolate the existing 21" pipeline to operate the new pivot # 10 . This is not on the materials

Continued ...

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

5 5

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

12805B24R0009/0003 list. If not installed water will backfeed the canal system.

A13: It is permissible for the contractor to build proposals for capping of the 21" pipeline at the end of the run, or install a new appropriately sized valve. Either is acceptable.

Q14: Materials List - Option II (Clin 0003) -

Irrigation Ditch Shut Off Valve - Per the site visit, a 24" Buried Valve will be required to isolate the existing canal. This is not on the materials list.

A14: Contractor shall include installation of a new 24" valve to be installed on the south line to isolate the existing canal.

Q15: Materials List - Option II (Clin 0003)

-Center Pivots # 1,2,3,4 - Materials list shows

11.2 24 Non Directional Tires as where

Specification sheet shows in section 1.06 E. - "

Tires will be 11.2 x 38""

A15: All tires shall conform to the 11.2 x 38¿ non directional.

Q16: Center Pivot Specifications - 1.07 - Control

Panel - "Telemetry has to be built into the panel" - Is cellular modem telemetry acceptable?

A16: Yes.

Q17: Center Pivot Specifications - 1.07 - Control

Panel - # 18 "GPS ready" - Is GPS positioning required? Materials list shows Pivot #10 with gps positioning but not #1,2,3,4.

A17: GPS positioning is required for all pivots.