About this file

This document contains questions and answers regarding solicitation number 12805B24R0009 for a center pivot irrigation system installation. The solicitation requires contractors to install a new river pump, manifold, and pipeline to supply four center pivot irrigation systems. Modifications are also needed to an existing pump house and electrical system. Attendance at a mandatory site visit on February 21st or 22nd is required to submit a proposal. The selected contractor must complete the work within 180 days but time extensions will be allowed for any required railroad right-of-way permits. The contractor will also be responsible for obtaining any other necessary permits. Irrigation operations may be stopped during construction to accommodate the project schedule.

View the file

Other files for this federal contract opportunity

Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

12805B24R0009 - Ques�ons and Answers Amendment 0003

Q1: Based on the contract documents posted on the SAMS site the new river pump has been specified to be a "Cornell - 8NHTR-VC18DB with 300 HP".

During the site visit I had originally had some concerns about u�lizing a centrifugal pump for this project because of the amount of suc�on li�. Currently all three exis�ng pumps are ver�cal turbine self priming style pumps. Based on the quote received today from Cornell Pump Company the specified pump will not be able to be mounted on the exis�ng I beam pump mount. The manufacturer stated this pump will only provide 2 to 2.5' of suc�on li� allowed. The original email from the manufacturer is atached. A field measurement was taken at the site visit from the exis�ng moun�ng surface to the water level of 12' 7". If the pump was mounted on the exis�ng pump pla�orm it would not func�on at the current river level based on the suc�on requirements.

It is possible to use this pump by building a lower mount inside the pump structure however it will be subject to flooding with river fluctua�ons.

A1: Due to the observed historical river gage height fluctua�ons, and in considera�on of addi�onal field measurement informa�on presented by industry following required site visits, a larger pump is now specified. Contractor’s shall build proposals to install Cornell Pump Size 10NNT-F18DB 350 HP, in lieu of the previously specified 8NHTR-VC18DB.

Q2: Its it possible of an alterna�ve pump may be accepted as we do not expect that the specified pump will work properly for this applica�on?

A2: : Contractor’s shall build proposals to install Cornell Pump Size 10NNT-F18DB 350 HP, in lieu of the previously specified 8NHTR-VC18DB.

Q3: The quan��es for the River Manifold material list do not match the quan��es specified in the spec sec�on.

A3: For bid purposes, contractors shall u�lize the design criteria provided in the River Pump Site Equipment Specifica�ons sec�on 1.02, sec�on G & H for specifics on manifold requirements.

Q4: There is no informa�on on the modifica�ons needed to the exis�ng Pump House. The manifold and Pump House work is a significant por�on of Op�on 1 without addi�onal informa�on it is impossible to es�mate this cost.

A4: Contractors shall reference River Pump Site Equipment Specifica�ons sec�on 1.02, sec�on L and provide bids commensurate with perceived/evaluated necessary modifica�ons to provide a fully func�onal system.

Q5: The wiring in the exis�ng pump house will need to be updated but there is no informa�on what is currently there.

A5 : Contractors shall reference River Pump Site Equipment Specifica�ons sec�on 1.02, sec�on K and provide bids commensurate with observed up-grades needed to the exis�ng wiring layout/pla�orm in order to facilitate a fully func�onal system specified in the Government’s solicita�on.

Q6: Another item I do not see addressed is working within the railroad right of way. From past experience ge�ng the proper permit can be a very long process which would affect the 180 day comple�on �me frame.

A6: Based on the project scoping and loca�ons of proposed systems, USDA, ARS does not an�cipate a BNSF Right of Way to be required for the North Line pipeline, however, if permi�ng is required, the construc�on contractor shall be responsible for obtaining required permits. USDA will allow for contract �me extensions as required for procurement/obtaining any required permit for Right of Way.

Q7: 2024 Season Flood Opera�on- Per site visit it was stated that construc�on may impede this season's irriga�on opera�ons. Will it be acceptable to stop irriga�on opera�ons for the en�re contract period?

A7: In considera�on of the climate at the Miles City site, construc�on performance will need to occur during irriga�on periods, and thus, irriga�on opera�ons will not occur during the performance period of the awarded contract.

Q8: Yaskawa 300HP VFD - Is the river pump drive required to be in an enclosure with Main Circuit Breaker?

A8: Yes.

Q9: BNSF Right of Way - Per Q/A Amendment, ROW was stated to be 200' from the centerline of Railroad tracks. If a permit is required for the North Line pipeline will USDA obtain ? Will contract �me be extended to allow for procurement of BNSF permi�ng process?

A9: Based on the project scoping and loca�ons of proposed systems, USDA, ARS does not an�cipate a BNSF Right of Way to be required for the North Line pipeline, however, if permi�ng is required, the construc�on contractor shall be responsible for obtaining required permits. USDA will allow for contract �me extensions as required for procurement/obtaining any required permit for Right of Way.

Q10: Remote Pump Control - Is the River pump vfd required to be controlled directly by ALL center pivot control panels ? Op�on II does not show any Pivot radios to pump site. Is buried wire control acceptable?

A10: Yes, the pump vfd installed shall have the ability to be controlled by all center pivot panels. Radio, cellular modem, buried wire are all acceptable forms of telemetry.

Q11: River Manifold - Per River Pump Site Spec - G. - It is stated that both flood and pivot irriga�on must be able to take place at the same �me. Does the manifold have to feed the exis�ng 15" and 24" lines simultaneously for flood opera�on while also feeding the new North line op�on #1 with pivot pressure?

A11: Yes. Both aforemen�oned lines will require simultaneous opera�on and contractors shall bid for the manifold to feed both lines at the same �me.

Q12: Screen System - Per River Pump Site Spec - N. - "Screen will need to be self cleaning" What flow ra�ng is required for the screen system?

Is modifica�on to the exis�ng trash rack acceptable? Or is a new screen system required?

A12: The scope concept was for modifica�ons to occur to the exis�ng system, however contractors are allowed to install a new system if deemed necessary. The final system shall be self cleaning. Flow ra�ng is not required.

Q13: Materials List - Op�on I (Clin 0002) - Irriga�on Ditch Shut Off Valve - Per the site visit, a 20" Buried Valve will be required to isolate the exis�ng 21" pipeline to operate the new pivot # 10 . This is not on the materials list. If not installed water will backfeed the canal system.

A13: It is permissible for the contractor to build proposals for capping of the 21” pipeline at the end of the run, or install a new appropriately sized valve. Either is acceptable.

Q14: Materials List - Op�on II (Clin 0003) - Irriga�on Ditch Shut Off Valve - Per the site visit, a 24" Buried Valve will be required to isolate the exis�ng canal. This is not on the materials list.

A14: Contractor shall include installa�on of a new 24” valve to be installed on the south line to isolate the exis�ng canal.

Q15: Materials List - Op�on II (Clin 0003) -Center Pivots # 1,2,3,4 - Materials list shows 11.2 24 Non Direc�onal Tires as where Specifica�on sheet shows in sec�on 1.06 E. - " Tires will be 11.2 x 38""

A15: All �res shall conform to the 11.2 x 38” non direc�onal.

Q16: Center Pivot Specifica�ons - 1.07 - Control Panel - "Telemetry has to be built into the panel" - Is cellular modem telemetry acceptable?

A16: Yes.

Q17: Center Pivot Specifica�ons - 1.07 - Control Panel - # 18 "GPS ready" - Is GPS posi�oning required?

Materials list shows Pivot #10 with gps posi�oning but not #1,2,3,4.

A17: GPS posi�oning is required for all pivots.