USDA Building 6403 RFI Log.xlsx

XLSX spreadsheet 110 KB Posted

Attached to
Renovate Building 6403 Containment Lab
Solicitation number
12639526Q0184
Issued by

About this file

This is an RFI Log documenting 55 questions and clarifications submitted by contractors during the pre-bid phase for the USDA/APHIS Building 6403 renovation project located at Moore Air Base in Edinburg, Texas. The project, based on specifications dated October 17, 2025, and an 83-sheet drawing set, involves major renovation of the Arthropod Quarantine Facility including mechanical, electrical, and plumbing system upgrades and interior finish refreshes. The contract duration is 450 calendar days (approximately 15 months) from Notice to Proceed, and the building will remain unoccupied during construction. All RFIs were closed by August 20, 2026, with responses provided through two addenda.

Key clarifications addressed in the RFI log include: hazardous materials testing responsibility, with an asbestos survey underway; roof work assuming 20% sheathing and framing replacement with 50 linear feet of blocking and R-20 minimum insulation; laboratory pressure relationships and HVAC sequence of operations requirements; environmental growth chamber repairs (EGC 4, 5, 6, 10, 11, 12) as a deferred alternate with delegated design responsibility; fume hood installation by contractor with owner-provided equipment and APHIS-contracted certification; access control and security system installation by owner's contractor with GC responsible for rough-in; structural assessment completed for roof loads with delegated design for guardrail anchorage; and comprehensive commissioning requirements per new Specification Section 019113. Additional critical scope items include temporary fencing requirement, designated door removal authorization during construction, laboratory casework coordination with plumbing and electrical penetrations, point-of-use water heater electrical requirements, and owner responsibility for equipment removal and sensitive materials handling. RFIs were submitted by multiple contractors (Covington, McKenzie, Trevino, Truinco, and AR6 CE) with priority levels distributed as 36 high-priority and 19 medium-priority items.

View the file

Other files

Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Covington

USDA/APHIS MAB Building 6403 Renovation – Pre-Bid RFI Log
Moore Air Base, Edinburg, Texas | Based on Specifications dated 10/17/2025 and 83-sheet Drawing Set
RFI No.DisciplineSubjectReferencesQuestion / ClarificationPriorityStatusResponseDate SubmittedDate Answered
RFI-001ArchitecturalPlease confirm if there is a Hazardous Material report on the facility.

a. If not, is the contractor responsible for performing any hazardous material testing? and or if the contractor should intend on performing a test to document this?

b. If the contractor is responsible for performing hazardous material testing, are they then responsible for performing hazardous material abatement as well? This will be difficult to price abatement, as quantity would not be known until after the report is developed.

c. If contractor is responsible for performing hazardous material testing and abatement, would the government please specify an allowance to be carried out for HAZMAT abatement?

d. If hazardous material is known, please specify what it is, locations, quantities, and if the contractor

is responsible for appropriate abatement.ClosedWe're getting a survey performed in the next day or two.08.17.202608/20/2026
RFI-002ArchitecturalWithout further inspection, the contractor cannot quantify damaged roof sheathing that may need to be

replaced as noted on drawing A-301 wall sections.

Would the USDA be willing to specify a percentage of roof sheathing to be replaced and reconcile this upon further evaluation of the sheathing conditions? This would keep all bidders on equal

footing for pricing, as some may price more or less sheathing replacement than others.ClosedSee direction provided in Addendum 1. No allowance. Assume replacement of 20% of sheathing and framing with 50 linear feet of blocking.08.17.202608/19/2026
RFI-003ArchitecturalCan the USDA confirm the slab profile or provide a detail for patching back the slab removed on drawing
PD101?ClosedExact existing slab provide for the original portion of the building is not available. Contractor to assume 4" concrete slab (4000 psi) with #3 bars at 13" o.c. each way. Dowel new slab infil into existing slab edge with #3 dowels, 8" long, embedded 4" into existing slab at 13" o.c. on all sides of the new infil.08.17.202608/19/2026
RFI-004General ConditionsWill the contractor be required to install temporary fencing around the job site, or will this not be required?ClosedYes for when work is occuring outside the building. See Addendum 2.08.17.202608/19/2026
RFI-005ArchitecturalSheetrock is currently installed at the underside of roof joists at the lower roof area and possibly the higher

roof areas; with the new roofing being installed, it is our understanding the roof system R Value will be in the new TPO roof assembly. Please advise if the sheetrock installed tight to the roof joist needs to be re-installed or can be removed or compromised without being repaired during the installation of new hangers, etc. Please advise on the finished product of the roof joist drywall.

a. What is the construction intent of the drywall on the underside of the roof deck?

i. Is it for firewall/fire rating purposes?

ii. To help achieve insulation R-value?

b. Additionally, for the installation of MEP hangers, does additional blocking have to be installed to prevent hangers from penetrating the TPO roof assembly? See the attached picture of the drywall

on the underside of the roof deck. Please advise if blocking will need to be installed for hangers.ClosedSection 03/A-301 existing gypsum board ceiling is to remain as noted. This is a part of the insect containment construction. Install blocking as required to support ductwork.08.17.202608/19/2026
RFI-006General ConditionsReferencing past performance to be submitted with proposals, please indicate how many prior projects are
to be submitted with the contractor’s proposals.ClosedThat's up to you.08.17.202608/20/2026
RFI-007General ConditionsWill the entire building be vacated during construction?ClosedYes.08.17.202608/19/2026
RFI-008General ConditionsWill there be any equipment left in the building that is sensitive and needs protection? Or will the government be responsible for removing all sensitive equipment?ClosedAll sensitive equipment will be removed by FMS and IMMDL. The only equipment that will stay fixed is to the building and will be secured by FMS.08.17.202608/19/2026
RFI-009General ConditionsWill the government leave any scientific research, reagents, materials, etc. that are temperature sensitive in
the lab spaces in freezers or refrigerators that must remain on and protected during construction?ClosedNo. All will be removed. The only equipment that will stay is fixed to the buidling and will be secured by FMS.08.17.202608/19/2026
RFI-010General ConditionsIs the contractor responsible for removing any bio-safety cabinets, centrifuges, microscopes, etc.?

a. If so, is the contractor responsible for re-certifying these devices once placed back in the labs?

b. If the contractor is responsible for moving and recertifying, we will need to know quantities, equipment description (brand, model #, serial #), and if they need to be recertified or balanced upon relocation. Closed No existing biosafety cabients to demolish. Owner will remove bench equipment. The new fume hood installation and TAB by the contractor. APHIS will have the fume hood certified. 08.17.2026 08/19/2026

McKenzie

USDA/APHIS MAB Building 6403 Renovation – Pre-Bid RFI Log
Moore Air Base, Edinburg, Texas | Based on Specifications dated 10/17/2025 and 83-sheet Drawing Set
RFI No.DisciplineSubjectReferencesQuestion / ClarificationPriorityStatusResponseDate SubmittedDate Answered
RFI-001MechanicalNo specification can be found for the environmental growth chambers; can one be provided?ClosedThe work done on the environmental growth champers is part of a delegated design. We have added a specification to Addendum 2 to provide additional clarity.08.17.202608.19.2026
RFI-002ArchitecturalKeynote E36 in multiple areas is shown as dashed, please confirm if this scope is covered by the owner or is to be provided by the contractor.ClosedStainless steel tables as noted by keynote E36 are to be provided by owner.08.17.202608.19.2026
RFI-003ArchitecturalPlease confirm if OnePointe Solutions is an approved alternate metal laboratory casework manufacturer.ClosedOnePointe Solutions is an acceptable substitution for the basis of design provided the stainless steel option meets the specifications.08.17.202608.19.2026
RFI-004ArchitecturalThe Lab Casework is specified as BMC, Inc. casework, which would be epoxy-coated steel. However, the drawings label the Lab Casework as being Stainless Steel; please confirm.ClosedLab casework is Stainless Steel.08.17.202608.19.2026
RFI-005ArchitecturalThe existing building entrance and interior door openings appear to significantly restrict the movement of materials and equipment; please confirm whether designated doors may be temporarily removed during construction to facilitate material deliveries and equipment installation. If permitted, please identify which door locations may be removed and any requirements for temporary security or weather protection during construction.ClosedSee Addendum 1. The building will be unoccupied.08.17.202608.19.2026
RFI-006GeneralThe above-ceiling spaces observed during the site visit appear to provide limited working room for new installations; please confirm whether the design team has evaluated the available ceiling space for constructability and coordination of the HVAC, electrical, plumbing, and fire protection systems. Additionally, advise if any modifications to the ceiling systems or existing utilities are anticipated to provide adequate installation clearances.ClosedThe above-ceiling space was evaluated. Demolition scope will specifically address several known conduits and pipes that are in conflict with the new ceilings, however, some re-working of existing to remain electrical and plumbing is anticipated as noted in the contract drawings. (Example: ED121 KN#9). The tight conditions above-ceiling will require careful planning and coordination by contractor and subs prior to rough-in. All mechanical ductwork/piping is new and has been coordinated with the new ceiling or moved to the roof.08.17.202608.19.2026
RFI-007ArchitecturalPlease provide bidding quantities for deteriorated underlayment or confirm repairs due to discovery of deteroriated underlayment during demolition will be treated as differing site conditions under FAR 52.236 2 or addressed as a change under FAR 52.243 4.ClosedSee direction provided in Addendum 1. No allowance. Assume replacement of 20% of sheathing and framing with 50 linear feet of blocking.08.17.202608.19.2026
RFI-008ArchitecturalPlease confirm the manufacturer of the existing roofing system and who carries the current warranty of the roofing system.ClosedSee Addendum 1. In Specification 075423 delete 1.6, B. This is a full roof replacement.08.17.202608.19.2026
RFI-009General ConditionsAre third party inspections required?ClosedSee previously answered RFI in the RFI log.08.17.202608.19.2026
RFI-010General ConditionsIs permitting required?ClosedNo08.17.202608/20/2026
RFI-011MechanicalAre partitioning, dust containment, and/or negative air machines required for this project?ClosedNo. Unoccupied during construction.08.17.202608.19.2026
RFI-012MechanicalDoes the government have a preferred Direct Digital Control for HVAC company? If so please provide the contact information.ClosedSee Instrumentation and Controls specification edits in addendum 1. An additional firm has been added in Addendum 2.08.17.202608.19.2026

Trevino

USDA/APHIS MAB Building 6403 Renovation – Pre-Bid RFI Log
Moore Air Base, Edinburg, Texas | Based on Specifications dated 10/17/2025 and 83-sheet Drawing Set
RFI No.DisciplineSubjectReferencesQuestion / ClarificationPriorityStatusResponseDate SubmittedDate Answered
RFI-001ArchitecturalPlease confirm if all SUF-4 areas will be available to install at one time or if it will need to be phased out.ClosedSee Addendum 1.08.17.202608.19.2026
RFI-002ArchitecturalPlease confirm who holds the roof warranty for this building.ClosedSee Addendum 1. In Specification 075423 delete 1.6, B. This is a full roof replacement. Provide Warranty per Specification 075423 1.10 WARRANTY, A and B.08.17.202608.19.2026
RFI-003General ConditionsPlease confirm if there is a preferred Fire Alarm vendor and/or contractor for this building.ClosedWork shall be performed by a contractor certified by the existing fire alarm manufacturer and all new equipment / devices to be compatible with existing system.08.17.202608.19.2026
RFI-004ArchitecturalPlease Confirm If Fireproofing is a required scope for this building. If so, please confirm which areas will require fireproofing.ClosedSealants will be required for smoke partitions as shown on Life Safety drawings08.17.202608.19.2026
RFI-005ArchitecturalPlease provide a list of any OFOI/OFCI items not listed in the project documents.ClosedNot applicable. Fume hood is OFCI and is in the documents.08.17.202608.19.2026
RFI-006ElectricalPer RFI-031 in the RFI log, please confirm access control scope will be completed by owner.ClosedConfirmed. Owner's security contractor to provide and install access control and GC is responsible for rough-in and coordination of access control installation as specified in Addendum 1.08.17.202608.19.2026

Truinco

USDA/APHIS MAB Building 6403 Renovation – Pre-Bid RFI Log
Moore Air Base, Edinburg, Texas | Based on Specifications dated 10/17/2025 and 83-sheet Drawing Set
RFI No.DisciplineSubjectReferencesQuestion / ClarificationPriorityStatusResponseDate SubmittedDate Answered
RFI-001General ConditionsThe solicitation indicates that the Contractor is to complete the work within 450 calendar days, or approximately 15 months, after Notice to Proceed.
Please confirm the contractual construction duration that bidders are to use for pricing and scheduling purposes, and advise whether any other duration referenced in the project documents is applicable.ClosedThere is no other reference to duration that's applicable.08.17.202608/20/2026
RFI-002General ConditionsSection 011000 indicates that the Owner will occupy the existing building throughout the construction period and requires coordination of outages and disruptive work.
Please confirm whether Building 6403 will remain occupied during construction or whether the facility will be vacated for the duration of the work. If partial occupancy is anticipated, please identify the areas that will remain occupied and any required phasing restrictions.ClosedSee Addendum 1.08.17.202608.19.2026
RFI-003MechanicalSection 236400 references Division 28 Section 283500, “Refrigerant Detection and Alarm,” for refrigerant monitors, alarms, ventilation equipment interlocks, and related controls. Section 283500 does not appear to be included in the issued specifications.
Please provide the applicable specification and clarify the complete refrigerant detection and alarm scope required for the project.ClosedThe chillers are located outside the building. Refrigerant detation/alarming is not required for this project.08.17.202608.19.2026
RFI-004ElectricalThe door hardware schedules identify various card readers and security devices as being provided by the Security Integrator.
Please identify the existing access-control system manufacturer and platform, as well as any Owner-required or incumbent security integrator. Please also clarify responsibility for card readers, emergency push buttons, door-position switches, request-to-exit devices, programming, final terminations, system integration, and testing.ClosedSee Addendum 1.08.17.202608.19.2026
RFI-005MechanicalSection 115313 identifies the Labconco laboratory fume hood as an Owner-provided product.
Please confirm the exact components that will be furnished by the Owner and clarify the Contractor’s responsibilities for unloading, storage, rigging, setting, base cabinet or stand, work surface, accessories, anchorage, startup, testing, and warranty coordination.ClosedThe fume hood is owner provided. The fume hood is located on site and the contractor is responsible for its complete installation. The ductwork, exhaust fan, and all accessories associated with this system are to be provided by the contractor to provide complete system installation.08.17.202608.19.2026
RFI-006General ConditionsThe project documents indicate coordination with existing fire-suppression components; however, no dedicated Division 21 drawings or specifications were identified.
Please confirm whether modifications to the existing fire-sprinkler system are required as part of the project. If modifications are required, please provide the extent of work, applicable design criteria, and responsibility for sprinkler-head relocations, piping modifications, testing, inspections, and permitting.ClosedThe existing building is not sprinklered.08.17.202608.19.2026
RFI-007MechanicalAlternate 03 requires repair of six chilled-water environmental growth chambers, including new controls, pumps, stands, and connections to the chilled-water and steam systems.
Please provide the existing chamber manufacturer and model information, current condition, required extent of repairs, control requirements, electrical requirements, and any manufacturer-specific service requirements. Please also clarify whether internal refrigeration or mechanical components of the chambers are included in the repair scope.ClosedThe repairs to the existing EGCs are to be part of a delegated design, and therefore the full extent to the work to completed in this scope of work will be determined by the EGC manufacturer. Additional information on the EGCs was included in sheet M-504 of addendum 1. See specificaiton in Addendum 2.08.17.202608.19.2026
RFI-008ArchitecturalThe project includes substantial rooftop mechanical work and references roof curbs, equipment supports, structural anchorage, and roof penetrations across multiple specification divisions.
Please clarify trade responsibility for furnishing and installing roof curbs, structural framing, support steel, blocking, equipment rails, and associated anchorage for each new rooftop mechanical unit and penetration.ClosedThis is a fixed fee, single-prime contract. Responsibility for ALL work lies with the General Contractor. Distribution of work to sub-contractors is the General Contractor's responsibility.08.17.202608.19.2026
RFI-009General ConditionsPlease confirm whether an asbestos-containing materials survey or other hazardous-material survey has been performed for Building 6403.

If a survey has been completed, please provide the report and identify all known asbestos-containing materials or other hazardous materials that may be disturbed by the work.

If no survey has been performed, please clarify whether the Owner will provide testing prior to construction and how bidders should account for potential asbestos-containing materials encountered during demolition and renovation activities. Closed A survey is being conducted today or tomorrow 08.17.2026 08/20/2026

AR6 CE

USDA/APHIS MAB Building 6403 Renovation – Pre-Bid RFI Log
Moore Air Base, Edinburg, Texas | Based on Specifications dated 10/17/2025 and 83-sheet Drawing Set
RFI No.DisciplineSubjectReferencesQuestion / ClarificationPriorityStatusResponseDate SubmittedDate Answered
RFI-001ArchitecturalIs the St Stl lab table OFCI? A401 E36ClosedStainless Steel table is provided by owner.08.17.202608/19/2026
RFI-002MechanicalIs there a preferred controls contractor USDA wants General Contractors to request pricing from? A Metasys panel was witnessed at the site walk.ClosedSee Addendum 1.08.17.202608.19.2026
RFI-003ArchitecturalPlease quantify amount of batt insulation to be replaced per A301ClosedQuantity depends on related work. The note in question requires the contractor to replace batt insulation where impacted by work to the existing materials to remain.08.17.202608.19.2026
RFI-004ArchitecturalThe current design and details of the roof mounted guardrail system provide an issue with finding a warrantable roof flashing. Can a non-penetrating or wall mounted guardrail be provided in lieu of the design shown in the plans?ClosedProvide roof flashing per new roof manufacturers standard details. Wall mounted system would not be applicable for all existing roof conditions.08.17.202608.19.2026
RFI-005ElectricalThere are multiple keynotes that say “provided and install by owners security contractor.” Is it the governments intention to separate this scope out, or will be included as apart of the base bid? If excluded, please clarify the work to be included by the awarded contractor.ClosedSee Addendum 1.08.17.202608.19.2026
RFI-006General ConditionsIs a temporary construction fence required around the building?ClosedYes for when work is occuring outside the building. See Addendum 2.08.17.202608.19.2026
RFI-007ArchitecturalIs the existing deck wood sheathing?ClosedExisting deck is wood sheathing. See Details A-56508.17.202608.19.2026
RFI-008ArchitecturalIs a vapor barrier to be installed over the need wood deck?ClosedVapor barrier is to be installed. See Details A-565.08.17.202608.19.2026
RFI-009ArchitecturalFM does not provide a Roof Nav # for wood decks as mentioned in spec section 075423-5 3.3.A. Is this just mentioned to be an installation guide more than a requirement?ClosedNotation is for standards for roof design.08.17.202608.19.2026
RFI-010ArchitecturalWill an adhered membrane be allowed in lieu of a self-adhered?ClosedBid per Specifications. Other options will be a substitution08.17.202608.19.2026

RFI Log

USDA/APHIS MAB Building 6403 Renovation – Pre-Bid RFI Log
Moore Air Base, Edinburg, Texas | Based on Specifications dated 10/17/2025 and 83-sheet Drawing Set
RFI No.DisciplineSubjectReferencesQuestion / ClarificationPriorityStatusResponseDate SubmittedDate Answered
RFI-001General ConditionsInterior Work Versus Limits on Contractor’s UseSpec 011000 §1.4.A.1; Drawings A-101, A-111 and MEP sheetsSpecification 011000 states that construction operations are to be confined to the building exterior unless otherwise requested for approval. However, the contract documents include extensive interior demolition and renovation throughout laboratories, restrooms, dressing rooms, corridors, mechanical rooms, the headhouse, and other occupied spaces. Please confirm that interior construction shown in the drawings is authorized contract work and provide the required process for obtaining access to each interior work area. Also provide any room-by-room access restrictions or required advance notice.HighClosedAs stated during the prebid meeting, the building will be unoccupied during construction.08.06.202608.12.2026
RFI-002General ConditionsRequired Construction Phasing PlanSpec 011000 §1.5; Project scope narrativeThe Owner will occupy the building throughout construction, while the project requires replacement of the chilled-water system, air-handling units, exhaust systems, ductwork, controls, boiler system, ceilings, lighting, doors, plumbing fixtures, and laboratory systems. Please provide the required construction phasing sequence, including areas that may be taken out of service simultaneously, maximum allowable duration of each phase, required temporary laboratory relocations, rooms or systems that must remain continuously operational, and turnover criteria before proceeding to the next phase.HighClosedBuilding will be unoccupied during construction, no phasing requirements.08.06.202608.12.2026
RFI-003General ConditionsMaintaining Arthropod ContainmentSpec 011000; Drawing G-001; Mechanical plansPlease provide the specific USDA/APHIS containment requirements that must remain in effect during demolition and construction, including temporary pressure relationships, temporary barriers and airlocks, pest-proof construction, sealing of penetrations, negative- or positive-pressure requirements, HEPA filtration requirements, and inspection and approval procedures before barriers are removed.HighClosedNot required as the building will be unoccupied during construction.08.06.202608.12.2026
RFI-004General ConditionsTemporary HVAC and Environmental ControlSpec 011000 utility interruption requirements; Division 23The work requires replacement of essentially the entire HVAC, chilled-water, exhaust, boiler, and controls systems while the Owner remains in occupancy. The documents identify temporary power requirements but do not clearly define temporary cooling, heating, exhaust, pressure-control, or humidity-control requirements. Please confirm whether temporary HVAC and laboratory exhaust systems are required. If required, provide required temperatures, humidity ranges, room-pressure relationships, air-change rates, filtration levels, and anticipated duration.HighClosedBuilding will be unoccupied during construction.08.06.202608.12.2026
RFI-005General ConditionsUtility Shutdown DurationsSpec 011000 §1.6Please provide the maximum allowable outage duration for normal and emergency electrical power, chilled water, heating water or steam, domestic water, sanitary service, laboratory exhaust, building controls, access control and security systems, and fire alarm systems. Please also confirm whether temporary services other than electrical power are required when shutdowns exceed the approved duration.HighClosedBuilding will be unoccupied during construction.08.06.202608.12.2026
RFI-006General ConditionsWork Hours and Weekend WorkSpec 011000Please identify normal permissible work hours, restrictions on noisy or disruptive work, available weekend work periods, holiday restrictions, and whether premium-time work required to accommodate Owner operations is to be included in the base bid.MediumClosedCovered in the prebid meeting. Building will be unoccupied during construction.08.06.202608.12.2026
RFI-007General ConditionsHazardous Materials SurveySpec 024119; Demolition drawingsPlease confirm whether asbestos, lead-based paint, PCB, mercury, mold, or other hazardous-material surveys have been completed and provide all available reports. If hazardous materials are encountered but are not identified in the contract documents, please confirm that investigation, abatement, disposal, schedule impact, and associated costs will be handled by contract modification.HighClosedAPHIS is working on getting a survey completed.08.06.2026
RFI-008General ConditionsSite Security and Personnel RequirementsSpec 011000; Drawing G-001Please provide requirements for background checks, security badges, escorts, vehicle inspections, restricted tools or electronic devices, photography restrictions, worker access hours, material delivery procedures, secure storage, and access to occupied laboratory areas. Please confirm whether costs and lead time for these requirements must be included in the base bid.MediumClosedRequirements for site access were covered in the prebid meeting. All costs need to be included in the contractors bid proposal.08.06.202608.12.2026
RFI-009General ConditionsContract Document IdentificationSpecification cover and drawing title blocksThe specification manual identifies CEI Project No. 212431, while several architectural sheets identify CEI Project No. 8050.07. Please confirm that both project numbers refer to the same contract and identify the controlling project number for submittals, RFIs, pay applications, correspondence, and record documents.MediumClosedProject No. 212431 is Coffman internal project number, Project No. 8050.07 is KZF internal project number. APHIS will have their own contract number for this work.08.06.2026
RFI-010AlternatesAlternate 02 Scope ConflictSpecification scope narrative, Alternate 02; Drawing A-101The specification narrative states that Alternate 02 includes demolition of the exterior electrical panelboard by the greenhouses and repainting the entire building exterior. Drawing A-101 appears to state “Demo exterior greenhouse panel bd,” which could be interpreted as greenhouse panel board rather than electrical panelboard. Please confirm that Alternate 02 requires demolition of the exterior electrical panelboard, identify the exact panel designation and location, and clarify all associated feeder removal, branch-circuit rerouting, equipment reconnection, patching, and disposal.HighClosedAlternate 02 scope is to demolish the exterior electrical panelboard identified as "Greenhouse Panel" and the adjacent panel meter. Equipment locations and demolition requirements are noted in the electrical demolition drawings. Refer to Addendum #1 for additional clarification.08.06.202608.12.2026
RFI-011AlternatesAlternate 02 Electrical Panel LoadsElectrical drawings; Alternate 02Please provide a list of all circuits and equipment presently served by the exterior panelboard included in Alternate 02. Confirm whether the loads are to be abandoned, reconnected to another panel, temporarily powered, or replaced under another scope item. Please provide revised panel schedules and feeder information where required.HighClosedThe only active branch circuit load in panelboard "greenhouse" is an exterior light fixture noted to be re-circuited on ED111 as part of the base bid. Alternate 02 scope is demoltion only as noted in the electrical demolition drawings. Refer to Addendum #1 for additional clarification.08.06.202608.12.2026
RFI-012AlternatesAlternate 03 Growth Chamber IdentificationSpecification scope narrative, Alternate 03; Drawing A-101; Mechanical drawingsAlternate 03 requires repairs to six environmental growth chambers, but the architectural plan identifies twelve chambers, EGC-1 through EGC-12. Please identify by equipment number the six chambers included in Alternate 03.HighClosedEGC 4, 5, 6, 10, 11, 12 are in-scope for the alternate. Other EGC are existing to remain.08.06.2026
RFI-013AlternatesAlternate 03 Existing Equipment InformationAlternate 03; Division 23 drawings and specificationsPlease provide existing manufacturer, model, serial number, capacity, electrical characteristics, control diagrams, pump information, and current operating condition for each environmental growth chamber included in Alternate 03. Also provide final performance criteria including temperature and humidity range and tolerance, steam requirements, chilled-water flow and pressure, alarm functions, controls integration, and testing and commissioning requirements.HighClosedContact equipment manufacturer for equipment data.08.06.2026
RFI-014AlternatesAlternate 03 Controls ResponsibilityAlternate 03; Spec 230900Please clarify whether growth-chamber controls are to be standalone, connected to the building DDC system, or connected to an existing proprietary control platform. Identify the required controls manufacturer and responsibility for programming, graphics, trend logs, alarms, licensing, and network connections.HighClosedConnect to the new DDC being installed as a part of this project. Also maintain existing connection to the existing MAB Niagra system that monitors select items in this building.08.06.2026
RFI-015AlternatesAlternate 04 Drawing IdentificationSpecification scope narrative, Alternate 04; Drawings A-101 and A-201The specification identifies Alternate 04 as relocating the Maintenance Room 105 doorway, including removal and infill of the existing opening and installation of a new north-wall opening. Portions of this work appear on architectural plans and elevations without a clear Alternate 04 boundary. Please identify every drawing note, detail, door, wall infill, electrical relocation, finish repair, and mechanical modification included in Alternate 04, and confirm that none of this work is included in the base bid.HighClosedRefer to Addendum #1 for clarification. See architectural drawing note D40 added to Sheet AD101 and see additional door schedule remark for Door 105.08.06.202608.12.2026
RFI-016AlternatesAlternates Pricing and AwardSpec 012300Please confirm whether alternates are additive or deductive, the required order of acceptance, whether overhead, profit, bond, insurance, mobilization, commissioning, and closeout costs are to be included in each alternate, how long alternate prices must remain valid, and whether an accepted alternate may be added after Notice to Proceed.MediumClosed-08.06.2026
RFI-017RoofingExisting Roof Deck ReplacementDrawings A-301, A-302 and A-567; Specs 070150.19 and 075423The drawings require damaged roof panels, sheathing, blocking, and framing to be replaced as needed, but no quantity or allowance is provided. Please provide anticipated quantities or establish unit prices for roof sheathing or plank replacement, wood blocking, wood joist or framing repair, metal deck repair where applicable, and deteriorated fascia blocking. Please confirm how concealed deterioration beyond the bid quantity will be measured and compensated.HighClosedNo allowance. Assume replacement of 20% of sheathing and framing with 50 linear feet of blocking.08.06.2026
RFI-018RoofingRoof Insulation Material ConflictDrawings A-301, A-302 and A-567; Spec 075423Some drawing notes call for XPS roof insulation, while typical roof details reference polyiso/XPS and identify an R-20 minimum. Please confirm the required insulation material for each roof area, including base insulation type, tapered insulation type, required total R-value, minimum thickness, number of layers, attachment method, and cover-board type and thickness.HighClosedR-20 is minium requirement. Tapered insulation by contractor will be required for existing flat roofs as shown on Sheet A-110.08.06.2026
RFI-019RoofingExisting Roof Warranty RequirementSpec 075423 Closeout SubmittalsSpecification 075423 requires a certified statement from the existing roof membrane manufacturer confirming that the existing roof warranty has not been affected. The project scope calls for complete roof replacement. Please confirm whether this requirement applies. If it does, provide the existing roof manufacturer, warranty number, expiration date, and areas of roofing intended to remain.MediumClosedSee Addendum 1. In Specification 075423 delete 1.6, B. This is a full roof replacement.08.06.2026
RFI-020RoofingNew Roofing Warranty PeriodSpec 075423 §1.10 and installer warranty formPlease confirm the required manufacturer’s warranty and installer’s warranty periods. Also confirm required wind-speed coverage, hail coverage, puncture coverage, and whether a no-dollar-limit warranty is required.MediumClosedProvide Warranty per Specification 075423 1.10 WARRANTY, A and B. This does not include wind and hail.08.06.2026
RFI-021RoofingRoofing Specification Cross-ReferencesSpec 075423Specification 075423 references sections including 053100 Steel Decking, 061600 Sheathing, and 078443 Roof Accessories. These sections do not appear in the project table of contents as listed; Section 078443 is identified elsewhere as Joint Firestopping, while Roof Accessories appears as Section 077200. Please confirm the intended specification sections and issue corrected cross-references.MediumClosedSee Addendum 1. Specification Section 075423 Section 1.1C Related requirements. Section 061000 is an added Specification Section. Section Roof Accessories which should read 077220. Metal deck is not a Releated Requirment.08.06.2026
RFI-022RoofingRoof Drainage ConfigurationDrawing A-110 and roof detailsThe roof plan identifies gutters, existing downspouts, open scuppers, roof slopes, and existing roof cants. Please provide design drainage calculations, required gutter slopes, new gutter and downspout sizes, scupper dimensions and elevations, overflow drainage requirements, locations requiring new downspouts, and confirmation that existing underground or surface drainage can accept the revised flow.HighClosedThe scope of the project is one for one replacement of the existing roof system including new gutters and existing downspouts as noted.08.06.2026
RFI-023RoofingRoof-Mounted Piping SupportsDrawing A-110; Mechanical roof plans; Specs 232100, 232213 and 075423Please provide complete support details for chilled-water, steam, condensate, electrical, and control systems routed across the new roof, including support spacing, support manufacturer or basis of design, maximum point loading, walk pads, thermal expansion provisions, anchorage, flashing, required clearance above the roof, and coordination with tapered insulation and drainage paths.HighClosedProvided specifications and drawings together cover support requirements. Not every support required is detailed. Not all items listed in RFI-023 are routed on the roof. Some supports require a delegated design and are contractor’s responsibility.08.06.2026
RFI-024StructuralStructural Capacity for New Roof LoadsMechanical plans and roof detailsPlease confirm that the existing roof framing has been evaluated for all new equipment, piping, fluid weight, guardrails, ductwork, supports, and construction loads. Provide structural details for any required reinforcement.HighClosedStructural assessment of mechancial equipment and piping on the roof was completed with some updates in Addendum 1. Mechanical bid drawings show notes and shaded areas for support reinforcement. Contractor is responsible for delegated design where noted, such as the guardrails. Construction loads are contractor's responsibility.08.06.202608.12.2026
RFI-025StructuralRoof Guardrail AnchorageDrawing A-110 Note R07; Drawing A-201 Note E37The drawings require new utility safety guardrails mounted to the top of exterior CMU walls. Please provide engineered anchorage details, post spacing, design loads, reinforcing requirements, corrosion protection, and required testing. Please also confirm whether existing CMU bond beams have been investigated and are adequate for the proposed anchorage.HighClosedRailings are delegated design. See new Specification Section 055213 in Addendum 1.08.06.2026
RFI-026Exterior EnvelopeGreenhouse-to-Building Sealant WorkDrawing A-101 Notes A12 and A13; Spec 079200Please identify the full limits and approximate linear footage of greenhouse perimeter and expansion-joint sealant replacement. Confirm required sealant type, joint preparation, backer rod, primer, color, and whether existing sealant must be tested for hazardous constituents before removal.MediumClosedReplace per existing condition and noted on Sheet A-101. Coded Note 13 is an existing vertical joint. Coded Note 63 added to Sheet A-201, Elevation 03 in Addendum 1. See also Response RFI-007.08.06.2026
RFI-027Exterior EnvelopeExterior Painting LimitsAlternate 02; Drawing A-201; Spec 099113Please confirm whether Alternate 02 exterior painting includes brick veneer, CMU, decorative brick, existing and new hollow-metal doors and frames, existing gutters and downspouts, existing metal fascia and trim, new guardrails, louvers, conduit and exterior electrical equipment, greenhouse support framing, and previously coated and uncoated masonry. Please provide final color selections or basis-of-bid colors and required coating systems for each substrate.MediumClosedSee Sheet A-201, Note ALTERNATE #2. See Specification Section 099113 - Exterior Painting. See Sheet A-604 for selected colors.08.06.2026
RFI-028ArchitecturalFloor Preparation and LevelingArchitectural demolition plans, wall sections and finish plans; Specs 096516 and 096519The drawings indicate lightweight concrete infill or leveling in certain areas but do not clearly define the full limits, depth, or required substrate remediation. Please identify all areas requiring lightweight concrete fill, self-leveling underlayment, crack repair, moisture mitigation, adhesive removal, slab grinding, and patching of abandoned penetrations. Please provide acceptable floor-flatness and moisture limits for each flooring system.HighClosedSee Sheet G-001, Demolition General Notes F, G and H. Level/patch floors as required for new floor finishes.08.06.2026
RFI-029ArchitecturalExisting Flooring Hazardous-Material TestingFinish demolition drawings; Specs 024119, 096516 and 096519Please confirm whether existing flooring, adhesive, wall base, mastics, or leveling materials have been tested for asbestos or other regulated materials. Provide reports before bid.HighClosedSee RFI-007 response above08.06.202608.12.2026
RFI-030ArchitecturalFinish TransitionsFinish plans and finish specificationsPlease provide transition details between new flooring and existing flooring at the limits of construction, including reducer strips, thresholds, expansion-joint covers, termination locations, and responsibility for repair where adjacent existing finishes are damaged during demolition.MediumClosedSee Floor Transitions Details 01,02,03 Sheet A-603.08.06.2026
RFI-031Doors/SecurityDoor Hardware and Access-Control Scope SplitSpec 087100; Drawings E-131 and E-132Please provide a complete responsibility matrix identifying who furnishes, installs, wires, programs, tests, and commissions card readers, electric locks, door-position switches, request-to-exit devices, interlock controllers, access-control panel, power supplies, signal strobes, emergency override pushbutton, fire-alarm interface, security software, cabling and conduit, and final programming and credentialing.HighClosedOwner's security contractor to provide and install access control system including all device and equipment listed in RFI-031. Security contractor scope includes wiring and terminations, programming, and commissioning of the access control system. GC is responsible for rough-in and raceway as noted in the contract drawings. GC is additionally responsible for coordination of scheduling with security contractor activities and for coordination of commissioning activities and training. Secuirty contractor scope of work and system commissioning must be completed as part of overall commissioning agent approval and prior to Owner acceptance of project completion.08.06.202608.12.2026
RFI-032Doors/SecurityDoor Interlock OperationDrawings E-131 and E-132The drawings indicate that interlocked doors fail secure upon power loss or fire alarm while allowing free egress. Please provide the approved sequence of operations for each door group, including normal operation, fire alarm, loss of normal power, loss of access-control power, emergency override, egress from each side, door release timing, audible or visual indication, and reset procedures. Please confirm compliance with applicable egress and life-safety requirements.HighClosedNo response, not relevant to project scope.08.06.2026
RFI-033Fire AlarmFire Alarm ScopeElectrical systems drawings; Specification table of contentsThe drawings require interfaces between door controls and the existing fire alarm, but a dedicated fire-alarm specification section is not listed. Please clarify the fire-alarm scope, required manufacturer, existing system model, required devices, programming, testing, permits, certification, and responsibility for coordination with the Owner’s fire-alarm vendor.HighClosedGC is responsible for identifying existing fire alarm controller and fire alarm system modificaitons required to provide the noted access control system interconnections. Acess control interconnection requirements to be specified by Security Contractor.08.06.202608.12.2026
RFI-034SecuritySecurity CameraDrawing A-201 Note E62The drawings identify a new security camera to be coordinated with APHIS, but camera specifications and system requirements are not clearly provided. Please confirm whether the camera is Contractor-furnished or Owner-furnished and provide manufacturer and model, mounting height and location, power requirements, data cabling, network connection, recording-system interface, licensing, programming, and testing responsibility.MediumClosedCamera is existing. A-201 revised in addendum #1.08.06.202608.12.2026
RFI-035LaboratoryLaboratory Fume Hood ResponsibilitySpec 115313; Laboratory and mechanical drawingsPlease confirm whether the new fume hood is Contractor-furnished and Contractor-installed. Provide the final basis-of-design manufacturer and model, sash configuration, liner material, service fixtures, controls, alarm, airflow-monitoring requirements, exhaust volume, duct connection size, electrical requirements, and testing standard.HighClosedFume hood is owner provided and to be contractor installed. See keynote 3 on sheet M-101 and electrical equipment schedule E-711 for requirements.08.06.202608.12.2026
RFI-036LaboratoryFume Hood CertificationSpec 115313; Division 23 commissioning requirementsPlease confirm the required field-certification standard and party responsible for testing the new fume hood. Identify required face velocity, containment test method, alarm setpoints, reporting requirements, and whether ASHRAE 110 testing is required.HighClosedThe local APHIS program will directly contract for the fume hood certification. GC needs to coordinate with the overall schedule.08.06.2026
RFI-037LaboratoryLaboratory Casework CoordinationSpecs 123553.13 and 123661.16; Architectural, plumbing and electrical drawingsPlease provide coordinated casework shop-drawing requirements showing all plumbing, electrical, data, equipment, sink, eyewash, water-heater, and countertop penetrations. Please confirm whether removal and temporary storage of existing laboratory contents are by the Owner or Contractor.MediumClosedSee Addendum 1. Section 123661.16, 1.2, B. to read "B. Shop Drawings: For countertops. Show materials, finishes, edge and backsplash profiles, methods of joining, and cutouts for plumbing fixtures, and equipment". Temp storage not required - unoccupied during construction.08.06.2026
RFI-038Plumbing/ElectricalPoint-of-Use Water Heater Electrical RequirementsSpec 223000; Plumbing and electrical drawingsPlease confirm voltage, phase, wattage, circuit size, disconnect requirements, and exact quantity for all point-of-use water heaters. Where electrical plans and plumbing equipment schedules differ, identify the governing requirement.HighClosedSee Sheets P-701 and E-711 for equipment specifications and electrical requirements. Equipment information is consistent between mechanical and electrical drawings. Any discrepancies in specified equipment shall be reviewed and approved by engineer.08.06.202608.12.2026
RFI-039PlumbingHead House RO Water ConnectionProject scope narrative; Plumbing drawingsPlease identify the source and connection point for the new RO piping serving the Head House sink. Confirm available pressure and flow, pipe material and size, required backflow protection, water-quality requirements, sanitization requirements, whether the existing RO system has sufficient capacity, and responsibility for modifications to the existing RO system.HighClosedRO piping connects to existing, relocated, RO system in the boiler room. New piping is shown on P-102 to include routing and pipes sizes.08.06.2026
RFI-040PlumbingEmergency Shower and Drench Hose DrainageLaboratory 114 and Head House plumbing scopePlease confirm drainage requirements for the new emergency shower and detachable drench hose, including floor slope, floor-drain capacity, trap-primer requirements, waterproofing, containment, and whether discharge testing may be performed at full flow.MediumClosedDrainage is provided for the emergency shower on sheets P-101/P-102. No drainage is required for the drench hose. Floor sloping will be added to architectural sheets in addendum 1.08.06.202608.12.2026
RFI-041HVACRequired Laboratory Pressure RelationshipsSpec 011000 project background; Division 23 drawingsThe project background states that the existing HVAC system does not provide pressure zones required to meet ARS standards. Please provide the required room-by-room pressure relationship schedule, acceptable pressure differential, airflow direction, alarm thresholds, monitoring requirements, and applicable ARS or USDA criteria.HighClosedAir balance schedule added to drawings for Addendum #1.08.06.202608.12.2026
RFI-042ControlsHVAC Sequence of OperationsSpec 230900; Mechanical control drawingsPlease provide a complete final sequence of operations covering chillers, primary and secondary pumps, boilers, feedwater system, air-handling units, energy-recovery unit, exhaust fans, air curtains, terminal units, reheat coils, growth chambers, laboratory pressure control, emergency modes, freeze protection, alarms, and trend logs. Please identify any controls narrative that supersedes the drawings.HighClosedDrawings have sequences. Some modifications were made in Addendum 1.08.06.2026
RFI-043ControlsExisting DDC System InterfaceSpec 230900Please identify the existing DDC manufacturer, software version, communication protocol, server location, and available network infrastructure. Confirm whether the new system must be an extension of an existing campus standard or may be provided by any approved manufacturer. Please identify responsibility for licensing, graphics, integration, cybersecurity review, user accounts, and remote access.HighClosedSome updates to the spec were made in Addendum 1.08.06.2026
RFI-044ControlsTemporary Controls During PhasingDivision 23; Occupied-building requirementsPlease confirm whether temporary controls, sensors, actuators, or standalone operation are required to keep existing systems functional while new DDC controls are installed. Provide required transition and cutover procedures.HighClosedBuilding will be unoccupied during construction.08.06.202608.12.2026
RFI-045HVACTAB Acceptance CriteriaSpec 230590Please provide final acceptance tolerances for supply airflow, exhaust airflow, outside air, room pressurization, hydronic flow, steam flow, equipment capacity, noise, and vibration. Please confirm whether TAB must be completed by phase and approved before each area is returned to the Owner.MediumClosedTolerances are per AABC or NEEB except where specified in 230590 or on the drawings. Phased TAB is not required because the buidling will be unoccupied during construction.08.06.202608.12.2026
RFI-046CommissioningCommissioning Specification ConflictSpecs 230800, 260923, 260943 and other equipment sectionsSeveral technical sections refer to a Commissioning Agent and reference Section 019113, but Section 019113 does not appear in the project table of contents. Section 230800 is included. Please provide the complete governing commissioning requirements and identify the Commissioning Authority, systems to be commissioned, contractor testing responsibilities, required prefunctional checklists, functional test scripts, seasonal testing, deferred testing, training requirements, required documentation, and costs to be included in the bid.HighClosedSpecification section 019113 has been added in Addendum 1 that supplements 220800, 230816, 260816, 270816, and 280816.08.06.2026