This document is a guidance document from the Forest Southern Research Station (USDA) establishing the 6% fee limitation for architect/engineer (A/E) design services under Solicitation Number 12445124R0001, in accordance with Federal Acquisition Regulation (FAR) 15.404-4(c)(4)(i)(B).

Design services subject to the 6% fee cap include schematic design, design development, construction documents, project manuals and specifications, design narratives with analysis, cut sheet assemblies, brief opinions of probable construction cost (at UNIFORMAT II Level 3 detail or less), design review meetings, green building rating system documentation, energy models, and all associated overhead, profit, and internal expenses. Non-design services explicitly excluded from the 6% limitation encompass travel reimbursement, facility investigations and evaluations, preliminary project analysis and design prospectus preparation, surveys (topographic, property boundary, utilities, construction staking), geotechnical investigations, regulatory permitting documents, materials testing, feasibility studies and master plans, cost estimates not based on designs or those exceeding UNIFORMAT II Level 3 detail, quantity survey cost estimates, NEPA documentation, models and renderings, as-built and HABS/HAER/HALS drawings, bid preparation and construction contracting assistance, construction observation and administration, submittal and shop drawing review, change order preparation, government-furnished design reviews, and value engineering services.

View the file

Other files

File Type Posted
SRS Shortlist training slides and TownHall Update Jul 2026.pdf PDF
A-E Shortlist Region 8 and 10PNW-IITF Firm Session MAR 2026.docx DOCX document
SRS Shortlist training slides and FIrm Info SF330 Review Training 19 MAR 2026.pdf PDF
ADHOC REPORT add_remove columns from SAM.GOV award search.pdf PDF
A-E Shortlist Region 8 and 10 Research Stations Firm Session Transcript FEB 2026.docx DOCX document
12445124R0001 Call for Qualifications SAM.GOV POSTING 01202026 Rev 2.docx DOCX document
Attachment F 2026_PRIOR YEAR QUESTIONS ASKED.pdf PDF
Firm SRS Shortlist training slides and FIrm Info SF330 Review Training 19 Feb 2026.pdf PDF
A-E Shortlist for Region 8 _10 SRS 2026 Firm Virtual QA Session Schedule.docx DOCX document
Attachment A 2026 AE SUBMITTAL COVER SHEET.pdf PDF
Attachment B 2026 STANDARD FORM 330.pdf PDF
12445121R0005 2026 SRS Renewal Request_ COMPANY NAME.pdf PDF
12445121R0005 SRS Renewal Request_ 2025.pdf PDF
12445124R0001 Townhall 2 Q and A Opportunity 8MAR24.docx DOCX document
12445124R0001 2024 Southern Research Station Shortlist (SRS) CONTRACTOR TOWNHALL SLIDE DECK AND FORMS.pdf PDF
12445124R0001 2024 Southern Research Station Shortlist (SRS) CONTRACTOR TOWNHALL TRANSCRIPT.pdf PDF
Virtual Contractor Townhall 25 JAN 2024 1400ET.docx DOCX document
Attachment B 2024 STANDARD FORM 330.pdf PDF
Attachment D 2024 SBA Table of Size Standards March 17 2023 Rev excerpt.pdf PDF
Attachment A 2024 AE SUBMITTAL COVER SHEET.pdf PDF
Attachment C 2024 DESIGN FEE LIMITATION NOTICE.pdf PDF
12445124R0001 Call for Qualifications SAM.GOV POSTING 02012024 Rev 1.docx DOCX document
Attachment F 2020_PRIOR YEAR QUESTIONS ASKED.pdf PDF
Attachment E_AE_RFP EXAMPLE_FORMAT_NO PROJECT.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Forest Southern Research Station Page 1 of 2 Service

A/E 6% Fee Limitation Solicitation Number: 12445124R0001

1.0 General

In accordance with Federal Acquisition Regulation (FAR) 15.4044(c)(4)(i)(B), fees for design services cannot exceed 6% of the Estimated Construction Cost Amount. This document provides additional guidance describing included and excluded services subject to the 6% fee limitation and is not meant to be allinclusive.

1.0 Design Services Subject to the 6% fee limitation:

1. Schematic design based on the Scope of Work and other Government furnished criteria.

2. Design development based on the Schematic Design.

3. Construction documents based on the Design Development

4. Project Manuals and Specifications

5. Design Narratives, also called Design Analysis. This includes design criteria and assumptions, references to standards, calculations, and a short descriptive analysis.

6. Assembly of packets of cut sheets.

7. Brief Opinions of Probable Construction Cost based on the design and updated at each design submittal where the level of detail is less than the UNIFORMAT II Level 3 designation.

8. Meetings for design review and presentation, but not public meetings.

9. Documentation for compliance with green building rating systems, such as the US

Green Building Council’s LEED rating systems.

10. Energy models of designs for code compliance and green building rating systems.

11. All time, including overhead and profit, for the items listed above

12. All internal expenses required to produce the design, such as copies to consultants, courier charges, phone calls, and meetings.

2.0 Non Design Services NOT subject to the 6% fee limitation

1. Travel shall be reimbursed in accordance with the Federal Travel Regulation.

2. Investigations and evaluations of existing facilities.

3. Preparation of a Preliminary Project Analysis, Design Prospectus, or Project

Program.

4. Surveys (examples: topographic, property boundary, utilities, construction staking).

5. Geotechnical investigation.

6. Creation and revision of documents based on the design intended solely for regulatory permitting, such as NPDES or DOT.

7. Materials testing.

8. Feasibility Studies and Master Plans.

9. Cost estimates not based on designs.

10. Cost estimates based on designs where the level of detail is greater than

UNIFORMAT II Level 3 designation.

11. Cost estimates created by quantity survey methods.

Forest Southern Research Station Page 2 of 2 Service

12. NEPA documentation and analysis.

13. Models, renderings, and photographs.

14. Preparation of as-built or record drawings.

15. Preparation HABS/HAER/HALS drawings and documentation.

16. Bid preparation and construction contracting assistance.

17. Construction observation, inspection, and administration.

18. Submittal and shop drawing review.

19. Preparation of construction change orders, requests for information, or supplemental instructions.

20. Review of Government Furnished Designs.

21. Value Engineering/Value Analysis Services.

Solicitation Number:
1.0 General
1. Schematic design based on the Scope of Work and other Government furnished criteria.
2. Design development based on the Schematic Design.
3. Construction documents based on the Design Development
4. Project Manuals and Specifications
5. Design Narratives, also called Design Analysis. This includes design criteria and assumptions, references to standards, calculations, and a short descriptive analysis.
6. Assembly of packets of cut sheets.
7. Brief Opinions of Probable Construction Cost based on the design and updated at each design submittal where the level of detail is less than the UNIFORMAT II Level 3 designation.
8. Meetings for design review and presentation, but not public meetings.
9. Documentation for compliance with green building rating systems, such as the US Green Building Council’s LEED rating systems.
10. Energy models of designs for code compliance and green building rating systems.
11. All time, including overhead and profit, for the items listed above
12. All internal expenses required to produce the design, such as copies to consultants, courier charges, phone calls, and meetings.
1. Travel shall be reimbursed in accordance with the Federal Travel Regulation.
2. Investigations and evaluations of existing facilities.
3. Preparation of a Preliminary Project Analysis, Design Prospectus, or Project Program.
4. Surveys (examples: topographic, property boundary, utilities, construction staking).
5. Geotechnical investigation.
6. Creation and revision of documents based on the design intended solely for regulatory permitting, such as NPDES or DOT.
7. Materials testing.
8. Feasibility Studies and Master Plans.
9. Cost estimates not based on designs.
10. Cost estimates based on designs where the level of detail is greater than UNIFORMAT II Level 3 designation.
11. Cost estimates created by quantity survey methods.
12. NEPA documentation and analysis.
13. Models, renderings, and photographs.
14. Preparation of as-built or record drawings.
15. Preparation HABS/HAER/HALS drawings and documentation.
16. Bid preparation and construction contracting assistance.
17. Construction observation, inspection, and administration.
18. Submittal and shop drawing review.
19. Preparation of construction change orders, requests for information, or supplemental instructions.
20. Review of Government Furnished Designs.
21. Value Engineering/Value Analysis Services.