This is a Questions and Answers document for Solicitation 1240LU26Q0030, the Fort Missoula Bakery Renovation project, dated May 5, 2026. The document addresses eight contractor inquiries regarding project scope and requirements.
Key clarifications include: lead-based paint test reports will be provided as an attachment, with abatement completed in 2019; no existing as-built drawings are available; Section 270000 Communications is excluded from the project scope; door exterior color is specified as Arugula SW 6446, with interior walls and chimneys requiring a custom mix matching existing walls; floor leveling may be accomplished using either self-leveling filler or concrete removal and replacement, at the contractor's discretion; handicap thresholds with PEMKO XG2212_PK773 hardware or equal will be installed on opening 103B; doors 100a and 104a have 4¾-inch stiles and contractors must confirm specified hardware compatibility and notify the Contracting Officer if issues arise; and additional details regarding interior door panel and sticking profile matching requirements will be provided in Amendment 0001. The contractor is also required to include lead and asbestos testing for the ceiling in their bid.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation 1240LU26Q0030 Fort Missoula Bakery Renovation
Question and Answers dated 05/05/2026
1. Are hazardous materials reports available for the building?
Lead-based paint test reports will be uploaded as an Attachment to the solicitation. Abatement of lead-based paint was completed in 2019 by Abatement Contractors of Montana. Window sealant and glazing were also abated. There are no test results for the ceiling. Contractor to include lead and asbestos testing for the ceiling.
2. Are there existing drawings/as-builts for the building?
No.
3. Is Section 270000 Communications included in the project?
No.
4. Is paint match/custom mix documentation available?
For door repairs, door exterior color is “Arugula SW 6446”. Interior walls, interior of doors, and exterior of chimneys is to use a custom mix matching the existing walls.
5. Should the floor of the office be leveled using a self-leveling filler or by cutting out concrete and pouring new concrete? Both are mentioned in different parts of the drawings.
Both are acceptable, this will be a means-and-methods decision for the contractor.
6. A501 calls for the removal of an existing inswing threshold and installation of a new handicap threshold on opening 103B. Are these doors being extended?
Yes, with PEMKO XG2212_PK773 or equal per door hardware schedule.
7. Please confirm width of stiles on existing doors to ensure the hardware will work on the door.
Doors 100a and 104a (those requiring new lock hardware) have 4 ¾” stiles. Contractor to confirm specified hardware will work with the doors and notify COR if not.
8. Will there be a requirement to match panel and sticking profiles on the new doors with the existing doors?
More details will be posted soon in SAM with Amendment 0001 regarding the interior door scope.