C05 Amendment 01 Sherando.pdf

PDF 896 KB Posted

Attached to
GAOA Sherando Recreation Area Rehabilitation, George Washington-Jefferson National Forest
Solicitation number
1240LT26Q0089
Issued by

About this file

This document is Amendment 1 to Solicitation 1240LT26Q0089 for the Sherando Recreation Area Rehabilitation project issued by the USDA Forest Service (USFS) on September 3, 2026.

The amendment extends the proposal submission deadline from September 8, 2026 at 5:00 p.m. to September 18, 2026 at 5:00 p.m. EDT. It adds two technical attachments: Attachment 10 (Bathhouse_Day Use DEQ & VDH permits) and Attachment 11 (Septic Calcs and Soils Reports). The amendment modifies the Technical and Project Management evaluation factor to establish calendar limitations requiring the bathhouse and water systems to be operational by August 13, 2027, with the campground closed to the public from November 1, 2026 through August 31, 2027. The contract period runs from November 2, 2026 through November 5, 2027. The amendment provides substantial clarifications through 80 questions and answers addressing project scope, technical specifications, site conditions, schedule requirements, and contractor responsibilities. Key clarifications include: horizontal directional drilling (HDD) is mandatory at all identified locations with specified casing requirements (HDPE SDR9 for stream crossings, ASTM A139 steel for steep slope); water distribution system specifications updated to reflect SDR9 pipe revisions; a new dewatering pay item added; clarification that temporary water service to the private residence is not required due to existing piping; permit documents for bathhouse and septic systems will be posted; rock excavation is anticipated and paid on actual quantities; existing utilities shown are for reference only with accuracy not guaranteed; and tree cutting limited to November 15 through March 31 window. The project involves campground and bathhouse rehabilitation including water system replacement, well house repairs, bathhouse renovations, and associated infrastructure work. Award, pricing terms, and set-aside information are not specified in this amendment document.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

1240LT26Q0089

x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

40LT

OGDEN UT 84401-2310

324 25TH ST

USDA-FS CSA INTERMOUNTAIN 8

DIS_GAOA09/04/20260001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

08/04/2026

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Solicitation 1240LT26Q0089, GAOA Sherando Recreation Area Rehabilitation, George

Washington-Jefferson National Forest, is amended as follows:

See Attachment 1 - Solicitation, Pg 1, SF-1442, 13. ADDITIONAL SOLICITATION REQUIREMENTS, change due date and time from September 8, 2026 at 5:00 p.m. to September 18, 2026 at 5:00 p.m. EDT.

See Attachment 1 - Solicitation, Pg 5-6, TECHNICAL DATA, (a) Attachments. Add Attachment

10 - Bathhouse_Day Use DEQ & VDH permits and Attachment 11 - Septic Calcs and Soils

Reports.

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

KELLIE J. SHAW

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 21CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

1240LT26Q0089/0001

See Attachment 1 - Solicitation, Pg 32, 1. Factor

1 - Technical and Project Management, (i)

Subfactor 1 - Technical Approach, change 1. to read "1. Calendar limitations on full shutdown of the campground (no public use) for only a limited part of the year (Nov - August). Bathhouse and water systems must be operational by August 13, 2027."

See Attachment 2 - SOI Sherando, delete in its entirety and replace with the attached revised

SOI.

See Attachment 3 - SOW Sherando, delete in its entirety and replace with the attached revised

SOW.

See Attachment 5 - Spec Water System 2b, the following changes are referenced in the question/answers:

024102 Removal & Disposal of Structures &

Obstructions, Section 3.2 (referenced in A33)

221100 Water Distribution (referenced in A5)

260523 Pump Controls and Control-Voltage

Electrical Power Conductors and Cables, Section

1.3 (referenced in A18, A20, A57)

312000 Earthwork, Section 1.5.A.3 (referenced in

A10)

330523 Utility Horizontal Directional Drilling

(referenced in A5, A50)

See Attachment 8 - Plans Water System 2a, the following changes are referenced in the questions/answers:

CU-03, CU-04 - Notes to clarify locations of SDR9 pipe (referenced in A5)

See attached for Site Visit Information and

Questions and Answers.

Period of Performance: 11/02/2026 to 11/05/2027

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

Amendment 01 Sherando Recreation Area Rehabilitation

1240LT26Q0089

September 3, 2026

P a g e 3 | 21

A site visit was held August 12, 2026 at the Sherando Recreation Area site. Below were attendees:

Name Company Rory Mullennex USFS Deed Vann WB Construction Robert Almand CCE Inc.

Leslie Weis Hydra Engineering Ray Martin MC3 Solutions Alan Peralta McKenzie Construction Chad Carpenter Plecker Construction Jay Moffett Moffett Paving & Excavating Adam Critzer Linco Inc.

Alex Fry Terra Constructs Nicholas Clarke HPC Cheryl Stockton McKim & Creed

Digging Servico Sam Berry James Berry

The following questions and answers are provided for information and/or clarification only.

Q1: Would the Government consider revising the relevant experience magnitude requirement to allow offerors to demonstrate experience with two projects having a construction value of $1,000,000 or greater?

A1: No. The relevant experience magnitude will remain unchanged. The size and complexity of the project require a higher level of experience.

Q2: Directional Drilling / Open-Cut Trenching: Would conventional open-cut trenching be acceptable in lieu of horizontal directional drilling at any or all locations currently shown to be bored? If open-cut trenching is not acceptable at all locations, please identify the specific crossings or segments where directional drilling/boring is mandatory. For locations where trenching may be permitted, please confirm the required casing, cover, restoration, erosion-control, and permitting requirements.

A2: All locations currently identified on the plans requiring horizontal directional drilling will require this method of installation. Open-cut trenching is not acceptable at these specific locations.

Q3: Stream Crossings / Permit Restrictions: Please confirm whether the Forest Service's Virginia Water Protection/USACE approval requires directional drilling or boring at any of the stream crossings. If so, please identify the specific crossings where open-cut construction would not be permitted and provide the applicable permit conditions.

A3: Directional drilling/boring is required by the Forest Service at all stream crossings. Open-cut construction is not permitted at any stream crossing. The Forest Service has confirmed that no USACE permit is required because boring methods will be used at stream crossings.

1240LT26Q0089

September 3, 2026

P a g e 4 | 21

Q4: 60 LF Boring on CU-15/CU-16 – Missing Pay Item: Drawings CU-15 and CU-16 indicate approximately 60 LF of boring from Sta. 1+65 to Sta. 2+25 beneath the road and small stream for the 2-inch HDPE distribution line and 1.5-inch supply line. The Schedule of Items does not appear to contain a corresponding horizontal directional boring pay item for this pipe combination. Please confirm which Schedule of Items line item is intended to include this work or revise the Schedule of Items to include a separate pay item.

A4: The pay Item for this boring location was inadvertently left off the schedule of items. A line item has been added to the corrected schedule – 0001BM - to account for this pay item.

Q5: HDD Casing Requirements: Specification Section 33 05 23 states that casing is required and that casing size is to be determined by the Contractor. Please confirm the required casing material for each directional bore and whether the steel casing requirements identified in Section 22 11 00 for paved-road crossings also apply to all HDD installations, including stream crossings and the steep-slope bore.

A5:

All Casings:

All carrier pipes shall be bundled for each boring, i.e., if multiple carrier pipes or conduits are to be installed at a boring location, they shall all be placed in a single casing pipe, such that there are no parallel casings. The Contractor shall select the casing inside diameters sufficiently large to ensure all bundled carrier pipe(s) and conduit(s) that will be installed in the casing can be installed successfully and with a minimum clear space of 2” on all sides of the bundled carrier(s) and conduit(s). The Contractor may increase this clear space at their own option for installation purposes.

Casing pipes for beneath-stream borings:

1. Material and Standards: All casing pipe shall be SDR9 manufactured from HDPE using PE4710 resin meeting a minimum cell classification of PE445574C per ASTM 3350. Pipe shall comply with AWWA C906. Specification 33 05 23 will be updated to reflect this information.

2. External Pressure Capacity Verification: The pipe must possess a short-term unconstrained critical collapse rating of at least 250 psi. Based on a 50-year material modulus, an initial installation ovality limit of 3% of the nominal diameter and a safety factor of 2.0, the casing must be engineered to provide a long-term safe allowable external fluid pressure limit of 40 psi against overburden and drilling fluid hydrostatic loads. Specification 33 05 23 will be updated to reflect this information.

Casing pipe for the steep-hill boring:

1. Material and Standards: All casing pipe shall be manufactured from ASTM A139 Grade B steel. The Contractor shall ensure the casing wall is sufficiently thick to enable successful installation and to ensure the maximum long-term ovality of the casing shall not exceed 3% of the nominal diameter. Specification 33 05 23 will be updated to reflect this information.

2. The Contractor shall ensure a strict minimum bending radius of the steel casing along the boring axis of 100’ x Casing Diameter in inches (e.g., 1,400’ for a 14” pipe). Specification 33 05 23 will be updated to reflect this information.

3. The Contractor shall determine the spacer frequency based on the steep slope of the bore.

1240LT26Q0089

September 3, 2026

P a g e 5 | 21

Road Crossings:

The steel casing requirements identified in Section 22 11 00 for paved-road crossings do not apply to any of the HDD installations. Specification 22 11 00 Water Distribution Systems, section 3.2.L.6 has been revised to require a minimum 3/8" wall thickness for steel casing pipe beneath asphalt roads.

Note: The full length of the 6” HDPE distribution pipe that is in the steep hill-side boring has been revised to SDR9.

Additionally, an 800 ft length of 4” HDPE between PRVs has been revised to SDR9. Quantities for these pipe types have been updated on the Schedule of Items. Notes for clarification will be included on the appropriate water system plan sheets to locate these revisions as part of a construction plan set.

Q6: Geotechnical / Subsurface Information: Please provide any available geotechnical reports, test pits, boring logs, rock data, groundwater observations, soil classifications, or other subsurface information for the proposed waterline, directional boring, bathhouse, septic, and sitework areas. If no subsurface investigation has been performed, please confirm that bidders are to price the work based solely on the information contained in the solicitation documents.

A6: Forest Service has a soils report prepared for the drainfield that will service the Upper Loop A Bathhouse. This information will be posted to Sam.gov with this solicitation. No additional geotechnical or subsurface investigation information is available for this project. Offerors will rely on information already provided with the solicitation.

Q7: Rock Excavation: Schedule of Items Item 0001BE includes an estimated quantity of 50 CY of rock excavation.

Please confirm that actual authorized rock excavation will be measured and paid at the Contractor's bid unit price based on actual in-place quantities. Please also confirm the definition and documentation requirements that will be used to determine when material qualifies for payment as rock excavation.

A7: Schedule of Items document has been updated to reflect method of measurement for all pay items, including 0001BE Earthwork: Rock Excavation. This line item now shows Actual Quantities (AQ) for method of measurement. See Section 31 20 00 Earthwork (1.5.A.2) for clarification about payment for rock excavation.

Q8: Existing Utilities / C-Loop: Specification Section 31 20 00 states that utilities exist in the C-Loop area but are not shown and that precise locations of existing utilities are not known. Please provide any available record drawings, utility maps, surveys, or other information showing existing water, sewer, electrical, communication, or other utilities throughout the project, particularly within C-Loop.

A8: Utilities shown on the plans are the best understanding that the FS has about potential locations of existing utilities.

These maps are for reference only and the accuracy of all depicted utility locations is not guaranteed.

Q9: Government-Furnished Survey Information: Specification Section 01 02 50 indicates that the Government will provide survey control sheets and proposed utility line coordinate information. Can these survey control sheets, northing/easting coordinates, and available electronic survey/CAD data be provided to bidders prior to bid so that quantities and installation conditions can be verified?

A9: Survey Control Points 1 and 2, along with their Northing, Easting, and Elevation are provided on Sheet CU-01 of the Drawings. Utility line coordinate information, including Point number and corresponding Northing and Easting, is provided on Sheet CU-19 of the Drawings. The utility line coordinate points are represented on each of the plan view sheets by an “x” and corresponding point number. A CAD version of the survey and design will be made available to the

1240LT26Q0089

September 3, 2026

P a g e 6 | 21 awarded contractor.

Q10: Dewatering Pay Item: Specification Section 31 20 00 states that dewatering outside of horizontal boring areas will be paid per hour of active dewatering and requires a minimum 100 GPM pump. A separate hourly dewatering item does not appear in the Schedule of Items. Please confirm which bid item should carry this cost or revise the Schedule of Items to include an hourly dewatering pay item.

A10: The Schedule of Items has been updated to include a pay item for hourly dewatering activity. See line-item 0001BE- 2 Earthwork – Dewatering (Outside Horizontal Boring Pits). Wording in specification 312000 Earthwork, Section 1.5.A.3, will be updated to the following: “Dewatering: Contractor shall remove all water while working and prior to backfill of areas to ensure backfill specifications are met. Dewatering for horizontal boring pits is included in pay item 330523.

Payment will be made per hour of dewatering actively operating and discharging water at the direction of the COR in areas outside of the horizontal boring areas. Minimum 100 gpm pump required for dewatering. Contractor shall submit daily, signed log sheets showing the exact start and stop times of the pump, signed off by the COR or their designated representative.”

Q11: Imported Above-Pipe-Zone Material: Specification Section 31 20 00 provides separate measurement and payment provisions for imported Pipe Zone Material and imported Above-Pipe-Zone Material. The Schedule of Items appears to include Item 0001BD for Pipe Zone Material but does not include a separate item for imported Above-Pipe-Zone Material. Please confirm how imported Above-Pipe-Zone Material will be measured and paid.

A11: Above-Pipe-Zone Material (APZM)shall be measured in accordance with Specification Section 31 20 00 (Part 2.2.B) Above-Pipe-Zone Material and shall only be used when the material removed from the trench does not meet the requirements described in either that Part or elsewhere in the Specifications. Item 0001BD-2 has been added to the Schedule of Items for payment and the unit of measure is Actual Quantity.

However, FS believes that due to the amount of Pipe-Zone Material (PZM) that will be imported, there will be a substantial amount of excavated material that will need to be disposed of under new Item 0001AD-2 Waste Material Disposal – Excavated Material (024100). FS further believes that there will be sufficient excavated material that meets the requirements for APZM that no APZM will need to be imported. The Contractor shall first use any material excavated from the trenches that meets the APZM requirements before importing any APZM.

Q12: Schedule of Items – AQ/DQ/LSQ Designation: Specification Section 01 12 50 identifies Actual Quantity (AQ), Designed Quantity (DQ), and Lump Sum Quantity (LSQ) methods of measurement. Please identify which method applies to each unit-price item in the Schedule of Items, particularly waterline, rock excavation, imported backfill, crushed aggregate, asphalt patching, and directional boring quantities.

A12: FS has updated the Schedule of Items to reflect a respective method of measurement for all line items. See the updated SOI document posted with the amendment.

Q13: Existing Permits and Approvals: The Statement of Work indicates that copies of approvals and permits obtained by the Forest Service can be made available upon request. Please provide all available permits and approvals applicable to the project, including the VDEQ erosion/stormwater approvals, Upper Loop A septic permit and approved plans, and Virginia Water Protection/USACE approvals and conditions.

1240LT26Q0089

September 3, 2026

P a g e 7 | 21

A13: Forest Service will share documents regarding permit approvals received from VDEQ and VDH for Bathhouse & Day Use project plans. These will be posted to Sam.gov. FS has documented that no USACE permit is necessary for the kayak boat launch work if the lake level is lowered during the construction phase for this work.

Q14: Asbestos and Lead-Based Paint Testing: The Statement of Work indicates that the Forest Service has not performed asbestos-containing material or lead-based paint testing at the CCC Beach Bathhouse or the existing Upper Loop A toilet building. Please confirm whether bidders are to include only the cost of surveys/testing in the base bid, or whether bidders are also expected to include an allowance for abatement and disposal of currently unknown hazardous materials. If ACM or LBP is discovered, will abatement beyond the testing scope be handled as a contract modification?

A14: FS has indicated that no asbestos or lead-based paint testing has been performed on the stated buildings.

Contractor shall be responsible for such testing as required. Any subsequent required abatement will be handled in accordance with the contract terms and conditions.

Q15: Existing Water Tank Coating – Hazardous Materials: Has the existing interior or exterior coating on the 24,000-gallon water storage tank been tested for lead, chromium, cadmium, or other regulated/hazardous constituents? If testing has been performed, please provide the reports. If not, please confirm how additional containment, worker protection, testing, transportation, and disposal costs associated with a hazardous existing coating will be handled.

A15: The Forest Service does not have any test reports about the existing or prior water storage tank coatings. The contractor shall be responsible for all labor, materials, tools and equipment for any containment, worker protection, testing, transportation, and disposal costs associated with an existing or previous coating.

Q16: Water Tank Welding Repairs: Specification Section 09 90 13 states that the lump-sum tank recoating work includes removal of the existing coating and any needed welding repairs. Please provide the most recent tank inspection report and identify all known structural deficiencies or anticipated welding repairs. If no inspection identifying the required repairs is available, please define the welding repair scope bidders should include in their lump-sum price and confirm that concealed or unforeseen structural repairs will be handled separately.

A16: The Forest Service has no tank inspection reports for this tank. See response in A17 for more clarification. Any perceived differing site conditions will be investigated and handled in accordance with the contract terms and conditions.

Q17: Existing Water Tank Condition: Please provide any available historical tank inspection reports, coating reports, photographs, previous repair records, coating product information, coating thickness information, or structural assessments that bidders may use to evaluate the anticipated surface preparation and repair requirements.

A17: The Forest Service has no tank inspection reports for this tank. FS has added “0011 Option Item #6: Inspect Water Tank and Prepare Report (AWWA D100 and AWWA M42)” to the Schedule of Items. If this Option Item is exercised, the Contractor shall perform a structural integrity and water safety/sanitation inspection of the tank after media blasting and surface preparation are complete but prior to re-coating of the tank, in accordance with AWWA D100 and AWWA M42, and prepare a report of conditions and recommendations for repairs.

Q18: Base Pump-Control Wiring vs. Options 0009/0010: Please clarify the relationship between Base Item 0002AD, which includes 1,200 LF of pump-control wiring replacement between the tank and Williams Branch well, and Option Items 0009 and 0010, which provide alternate conduit/wiring routes between these facilities. If either Option 0009 or 0010 is

1240LT26Q0089

September 3, 2026

P a g e 8 | 21 awarded, is Base Item 0002AD still to be performed in its entirety, or does the option replace a portion of the base scope?

A18: Item 0009AA and 0010AA have been removed from the Schedule of Items. Item 0002AD has been updated in the Schedule of Items to include conduit and correct the connection to be between the tank and Loop A wellhouse. See response in A19 for more clarification on conduit and wiring alignments.

Q19: Existing Pump-Control Conduit Condition: The Statement of Work indicates that Options 0009 and 0010 will only be performed if the existing conduit is determined to be inadequate or unusable. Please confirm whether the existing conduit has been tested or inspected. If so, please provide the results. If not, please identify when and by whom the existing conduit will be evaluated and what bidders should assume regarding its usability in the base bid.

A19: The existing conduit has not been tested or inspected. The FS has modified the scope and will no longer consider using this existing conduit (or wiring in conduit). New wiring and conduit will be used to connect the tank to the Loop A well house (including through the hillside boring and stream boring locations), and new wiring and conduit will be used to connect Loop A well to Williams Branch well.

Q20: Option 0010 Alignment Conflict: The Statement of Work describes Option Item 0010 as routing conduit and pump-control wiring through the casing along the steep slope and then following the original alignment to the Williams Branch well. The Schedule of Items description for 0010AA states that the conduit and wiring are installed "along service road."

Please clarify the intended alignment and limits of Option Item 0010.

A20: Item 0009AA and 0010AA have been removed from the Schedule of Items. Item 0002AD has been updated in the Schedule of Items to include conduit and correct the connection to be between the tank and Loop A wellhouse. See response in A19 for more clarification on conduit and wiring alignments.

Q21: Option 0010 / HDD-1 Casing Size: If Option Item 0010 is exercised, please confirm whether the casing associated with HDD Item 0001BH is required to accommodate the 6-inch waterline, 1.5-inch supply line, and the optional pump-control conduit. If so, please provide the required minimum casing diameter, conduit size, separation requirements, and arrangement so bidders can properly size the casing in the base bid.

A21: Option Item 0010AA has been removed from the Schedule of Items. The casing associated with HDD Items 0001BH is required to accommodate the 6-inch waterline, 1.5-inch supply line, and the 1-inch pump-control conduit which will all be bundled tightly together. The FS anticipates the required diameter of the casing pipe will be the same with the 1-inch conduit (see to-scale sketch below). In accordance with 330523 – 2.1.A, the Contractor is responsible for determining the appropriate size of the casing.

1240LT26Q0089

September 3, 2026

P a g e 9 | 21

Q22: HDD Access and Staging Areas: Please identify the areas that will be available for HDD equipment setup, boring pits, pipe fusion/stringing, drilling-fluid handling, and pullback operations. In particular, please confirm that sufficient temporary workspace and access will be available for the approximately 485 LF steep-slope bore and identify any limitations on clearing, grading, temporary access roads, or equipment size.

A22: In accordance with page 9, Section 5.8.1 of the Statement of Work, the Contractor shall arrange the location of all staging, laydown, and stockpile areas, subject to advance written approval by the Contracting Officer (CO). The CO will approve an adequate staging area within the project site for use in contractor operations. The Contractor is responsible for proposing suitable locations and obtaining written approval prior to mobilization.

Access necessary for HDD operations will be accommodated to the best of the ability of the Forest Service. All permanent structures and FS assets such as recreational buildings, furnishings, existing roads, and trees shall be protected from damage. Protect the stream from any impacts. Tree cutting and removal must be approved in advance by the FS.

Q23: Tree Removal Limits: Please provide the anticipated tree-removal limits or tree inventory for the waterline and sitework areas. The Statement of Work restricts tree removal to November 15 through March 31 and requires Forest Service approval of each tree. Please confirm that all required trees will be identified/approved early enough to allow removal within this window and that unforeseen tree removal required after March 31 will not delay the Contractor.

A23: The contractor shall identify which specific trees need to be removed as part of the waterline installation within the allowed corridor, mark/flag those trees, and obtain approval from the CO/FS prior to any removal. Cutting trees must occur within the Nov 15 – Mar 31 window, but removal can occur outside this window. Any perceived delay will be investigated and handled in accordance with the contract terms and conditions.

Q24: May 1, 2027 Water-System Milestone: The Statement of Work requires the water system to be fully operational by May 1, 2027. Please define the requirements for achieving "fully operational," including whether tank coating and curing, disinfection, bacteriological testing, hydrostatic/leak testing, well-pump installation, pump-control commissioning, and all distribution system work must be complete and accepted by that date.

A24: Forest Service has updated the Statement of Work, section 5.7 Project Site Closure dates. Specifically: “The campground can be closed to the public starting November 1, 2026, and stay closed until August 31, 2027. The contractor can work unobstructed during this timeframe and is responsible for maintaining closure of the project site during this time frame. Coordinate with the Forest Service to maintain government personnel access to the site in a safe and effective manner during this time.” Review the updated SOW Section 5.7 for more clarification.

Q25: May 21, 2027 Recreation Area Opening: Please clarify which portions of the base contract must be complete and available for public use by May 21, 2027. Specifically, please confirm whether the Beach Bathhouse, Lower Loop A Bathhouse, Upper Loop A Bathhouse, campground water system, roads, campsites, and other affected facilities must all be fully complete by this date or whether isolated work may continue after the Recreation Area reopens.

A25: See response to Question 24 and the updated Statement of Work, section 5.7.

1240LT26Q0089

September 3, 2026

P a g e 10 | 21

Q26: Water-System Testing and Agency Review Duration: Please identify all required pressure testing, flushing, disinfection, bacteriological sampling, water-quality testing, agency inspections, and approvals required before the new water system may be placed into service. Please also provide the anticipated Government/agency review durations bidders should include in the construction schedule.

A26: See specification section 221100 Water Distribution Systems for requirements regarding all water system testing.

Inspections shall be performed by the Forest Service per these specifications.

Q27: Temporary Water Service to Private Residence: The Statement of Work requires continuous water service to the private residence and indicates that a nearby well may be used while the distribution system is out of service. Please clarify whether the Contractor is responsible for furnishing temporary piping, pumps, controls, electrical connections, tanks, or other temporary facilities necessary to provide this service. If so, please provide the intended temporary connection point and approximate routing requirements.

A27: Water system piping to support continuous water service to the private residence already exists and therefore temporary water service to the Private Residence will not be required. A direct connection between the Loop A Well House and the private residence already allows it to be isolated from the rest of the water system. Per Note 4 on plan sheet CU-16 Water Service to Residence must be maintained throughout project duration except for an outage of one week to allow connecting new piping/plumbing system to residence. Water service to the residence can be provided from Loop A Well House and existing piping even when the rest of the Distribution system is inoperable.

Q28: Upper Loop A Electrical Service: Electrical Drawing E501 requires field verification of the existing and new electrical service locations and shows relocation of the existing CT/meter cabinet. Please provide the confirmed utility point of connection, available service capacity, and any applicable utility-company requirements. Please also confirm whether utility-company fees, meter/CT work, service modifications, or transformer upgrades are included in the Contractor's scope.

A28: The existing meter is to be removed from the wood post it is currently mounted to and reinstalled on the new support structure shown. The existing service disconnect is changing from an enclosed breaker to a service entrance rated panel with the same ampere rating. The service location is in the same location or very close proximity. The contractor is responsible for all utility fees and work as coordinated with the utility, Shenandoah Valley Electric Coop.

Q29: Existing Bathhouse Utility Connections: Please provide available as-built information for existing water, sanitary, and electrical services serving the Beach Bathhouse and Lower Loop A Bathhouse. Please confirm the intended limits of replacement at each exterior utility connection and how deficiencies discovered beyond the indicated tie-in points will be handled.

A29: All known, existing utilities on the project are included on the existing conditions sheets. There are no exterior electrical utility replacements for the Beach Bathhouse or Lower Loop A Bathhouse. Existing panels shall be used for branch circuits. Refer to electrical floor plans and panel schedules. The plumbing drawings show connecting to the existing domestic CW and sanitary waste piping serving those bathhouses. The plumbing contractor must field locate all existing piping prior to starting work.

Replacement of waterline lateral at Lower Loop A Bathhouse shall be to the inside of the mechanical chase of this building to allow for proper connection of the new interior plumbing. At the CCC Beach Bathhouse there are (2) existing

1240LT26Q0089

September 3, 2026

P a g e 11 | 21 water utility manholes exterior to both the existing men’s and women’s side of the bathhouse. The water connection into the women’s side is to be abandoned by cutting and capping the existing lines to this manhole and the manhole abandoned (salvage valves, remove piping, fill with construction debris, remove top 12”, make ground flush). The water connection on the men’s side will be the only service connection for the bathhouse. Contractor shall replace the existing 2” CW line going from the existing utility manhole into the building. No work shall be done to the existing bathhouse foundation or exterior walls as part of this water service connection. All other connections to existing buildings shall be as shown on the plans. Any perceived differing site conditions will be investigated and handled in accordance with the contract terms and conditions.

Q30: Upper Loop A Septic System: Please provide the complete Virginia Department of Health approved septic-system permit package, including approved plans, calculations, soil evaluation information, drainfield requirements, and permit conditions. Please confirm that bidders should price the septic system exactly as permitted and clarify how required revisions resulting from field conditions would be handled.

A30: The Sewage Disposal System Construction permit for the septic system is included with permit documents posted in Sam.gov as part of this amendment. Bidders shall rely on the plans and specs included in the solicitation for developing costs for the septic drainfield system for Upper Loop A Bathhouse. Septic system should be priced as permitted and constructed as directed by permit. Any perceived differing site conditions will be investigated and handled in accordance with the contract terms and conditions.

Q31: Staging and Laydown Areas: Please identify the areas that the Forest Service anticipates making available for contractor staging, trailers, material stockpiles, pipe storage/fusion, dumpsters, subcontractor parking, and equipment storage. Please identify any restrictions on the size, duration, or location of these areas that should be included in bid pricing.

A31: In accordance with page 9, Section 5.8.1 of the Statement of Work, the Contractor shall arrange the location of all staging, laydown, and stockpile areas, subject to advance written approval by the Contracting Officer (CO). The CO will approve an adequate staging area within the project site for use in contractor operations, including trailers, material stockpiles, pipe storage or fusion activities, dumpsters, subcontractor parking, and equipment storage. The Contractor is responsible for proposing suitable locations and obtaining written approval prior to mobilization.

The Contractor shall be fully responsible for protecting all materials, equipment, and supplies placed within the staging or laydown area against adverse weather, damage, theft, or any other risk of loss. The Government assumes no responsibility for any material or equipment stored on site.

No specific size, duration, or location restrictions beyond CO approval are identified in the Statement of Work. All approved locations must ensure safe access for Forest Service personnel and must not interfere with ongoing recreation operations outside the authorized closure period.

Q32: Road and Pavement Restoration Limits: Please confirm whether the 1,800 SF quantity under Item 0001BG represents the total anticipated asphalt patching for the water-system work. If actual pavement disturbance differs from the estimated quantity, please confirm that authorized asphalt patching will be measured and paid based on actual installed quantities.

1240LT26Q0089

September 3, 2026

A32: Line item 0001BG Road Asphalt Patching has Actual Quantities (AQ) for the method of measurement on the updated Schedule of Items. FS estimates 2,100 SF of asphalt patching, but actual quantities will be paid.

Q33: Existing Waterline Abandonment: The Statement of Work indicates that existing waterline is generally to remain abandoned in place except where it conflicts with the new work. Please clarify the required method of abandonment, including whether existing lines are to be drained, capped, plugged, or grouted, and identify locations where complete removal is specifically required.

A33: Any existing waterlines and associated appurtenances encountered during excavation operations shall be completely removed within the limits of excavation required for installation of the new piping, structures, or appurtenances. The existing waterlines shall be capped or plugged with a watertight cap or plug appropriate for piping material. If grouting is chosen, an acceptable method is to insert a backer material to a distance of 4’ within the pipe and fill the pipe from the backer material to the end with non-toxic non-shrink grout. Lines shall be drained prior to abandonment. See General Note #12 on Water System Plan Sheet CU-01 for more information about abandonment of structures and other components. Specification 02 41 02 shall be updated to reflect these abandonment requirements.

Q34: Material Disposal / Government Stockpile Locations: Please identify whether excavated rock, excess suitable soil, removed piping, valves, hydrants, timber, or other demolition materials are to be disposed of off-site, salvaged for the Government, or stockpiled at a designated location on Forest Service property.

A34: Refer to Spec 024100 Waste Material Disposal and Spec 024102 Removal and Disposal of Structures and Obstructions.

Q35: Optional Work Award Timing: Please confirm when bidders should anticipate notification regarding the award of Option Items 0006 through 0010. Where an option affects base-work design or installation—particularly Option 0010 and the HDD casing—please confirm that the option decision will be made before the affected base work must be fabricated or installed.

A35: Any award of base and optional contract line items shall be conducted strictly in accordance with the terms, conditions, and procedures established in the contract. All determinations related to the selection, sequencing, or authorization of option items will be made pursuant to the applicable contractual provisions and governing regulations.

Q36: Price Proposal / Volume Organization: Please confirm whether the Price Quote, including the completed Attachment 2 – Schedule of Items, is to be submitted within the same volume/file as the Technical Proposal, or whether the Price Quote is to be submitted as a separate volume/file.

A36: See Attachment 1 – Solicitation, page 30 & 34. Documents should be separate and clearly identified.

Q37: Past Performance Questionnaires (PPQs): Please clarify whether Past Performance Questionnaires (PPQs) are required as part of the proposal submission. If PPQs are required, please provide the applicable questionnaire/form, submission instructions, and any requirements regarding the number of references to be submitted.

A37: PPQ’s are not required in this solicitation. See Attachment 1 – Solicitation, Page 33 and 34 for past performance instructions.

P a g e 12 | 21

1240LT26Q0089

September 3, 2026

P a g e 13 | 21

Q38: Technical Approach Page Limit: Please confirm whether there is a page limitation for the Technical Approach narrative under Factor 1, Subfactor 1 – Technical Approach. If a page limit applies, please identify the maximum allowable number of pages and whether cover pages, tables, figures, and graphics are included in the page count.

A38: There are no page limitations for the technical proposal. See Attachment 1 – Solicitation, Pages 28-34 for technical proposal and price proposal instructions.

Q39: Project Schedule Page Limit: Please confirm whether there is a page limitation or other formatting restriction applicable to the proposed Project Schedule. If a limit applies, please identify the maximum allowable number of pages and whether an 11-by-17-inch schedule sheet is permitted and, if so, how such a sheet will be counted toward the proposal page limitation.

A39: There are no page limitations for the technical proposal, and 11x17 inch sheets are permitted.

Q40: Attachment 6 – Plans/Drawings: Attachment 6, Plans/Drawings – Bathhouse & Day Use Renovation 1(a) Part 1, does not appear to open or display properly with the currently posted file. Please confirm whether the posted file is complete and accessible and, if necessary, re-upload Attachment 6 in a standard PDF format that can be opened and reviewed by offerors.

A40: Attachment 6 – Plans/Drawings has been confirmed to be complete and accessible within the solicitation posting located at https://sam.gov/workspace/contract/opp/c5abb59379a746fcad19c830bbabc446/view. The file is a large-format drawing package, and offerors must use Adobe Acrobat or an equivalent program capable of opening large PDF drawing sets to properly view the contents. The Government has verified that the file opens and displays correctly when using appropriate software. At this time, no re-upload is required. If an offeror continues to experience access issues after using a suitable PDF viewer, the Government will provide technical assistance upon request.

Q41: Campground Closure and Required Operational Date: The solicitation states that full shutdown of the campground, with no public use, is permitted only during the limited period from November through May 1, while also requiring the bathhouse and water systems to be operational by May 21, 2027. Please clarify the intended operational requirements for the period between May 1 and May 21, 2027. Specifically, please confirm whether the campground is required to reopen to the public on May 1 and, if so, identify which bathhouse facilities and portions of the water distribution system must be fully operational by May 1 versus those that may remain out of service until May 21, 2027.

A41: See response to Question 24 and the updated Statement of Work, section 5.7.

Q42: I am contacting you in regards to the project mentioned above and would like to submit two Approved equal/Substitution requests.

A42: Any product substitutions will be handled after contract award in accordance with the specifications.

Q43: SOW 7.0.2 - The cost for performing the hazardous materials survey for ACM & LBP is to be included in the proposal. Is the cost for removal of the materials if found during the survey to also be included or will these cost be added by modification?

1240LT26Q0089

September 3, 2026

P a g e 14 | 21

A43: Per the Statement of Work, FS has indicated that no asbestos or lead-based paint testing has been performed on the stated buildings. Contractor shall be responsible for such testing as required. Any required abatement will be handled in accordance with the contract terms and conditions. (See Q14 & A14)

Q44: SOW 5.6.1 - Master Plumber Tradesman License - states that the Prime Contractor should hold a Virgina Board of Contractor's License with a designated Plumbing (PLB) trade speciality classification. Please verify that the Prime / GC will be required to have a state license since this is a federal project and land or advise if a subcontrator with the Master Plumber (MPLB) be acceptable? We do hold licenses in several states and which has been acceptable on multiple USDA / FS projects we have performed.

A44: The contractor is strongly encouraged to have a Virginia Board for Contractor’s License, but this is not required.

Personnel holding the active Master Plumber (MPLB) Tradesman License shall be under the direct employ of the awarded contracting firm or a designated subcontractor performing the relevant work. As stated in the SOW this person shall have responsible charge of plumbing and waterline installations.

Q45: S-101 - Please confirm that the structural repairs on this sheet are excluded.

A45: As per the Statement of Work, section 5.0.1.7 Excluded Scope, repair work identified on sheets S-101, A-201, and A- 202 have already been accomplished on the project and are excluded from this scope. Review the Statement of Work section for specific details.

Q46: Please confirm the items on this sheet which are to be excluded form the project per 5.0.1.7 of the SOW.

A46: As per the Statement of Work, section 5.0.1.7 Excluded Scope, repair work for roofing, structural timbers, dormer framing and windows identified on sheets S-101, A-201, and A-202 have already been accomplished on the project and are excluded from this scope. Review the Statement of Work section for specific details.

Q47: If liquidated damages are part of this contract, please provide amount per day.

A47: Liquidated damages are not included in this project.

Q48: Please identify the specific structure that must remain continuously served during replacement of the water distribution system and provide its required flow and pressure. Clarify whether the contractor is responsible for temporary piping, temporary pumping, chlorination/testing, backflow prevention, freeze protection, and associated temporary power. The solicitation allows only a maximum one-week shutdown.

A48: The specific structure that must remain continuously served is the Residence shown on Sheet CU-16 of the Drawings. Water system piping already exists between the Residence and the Loop A Well House (also shown on Sheet CU-16) and therefore new temporary infrastructure will not be required. Existing valving enables the Loop A Well House-to-Residence piping to be operated independently of the remainder of the water system. The FS anticipates that the Contractor can allow the piping between the Loop A Well House and the Residence to remain in-tact while performing replacement of the rest of the system. Once the rest of the system has been replaced, the FS anticipates the Contractor can then provide water to the Residence from the Williams Branch Well, while performing the Loop A Well House Repairs and piping replacement.

1240LT26Q0089

September 3, 2026

P a g e 15 | 21

Q49: Provide the required sequence of water-system cutovers and identify the maximum allowable outage duration for each campground facility/bathhouse in addition to the one structure specifically required to remain operational.

A49: Base Items 0001 Campground Water System Replacement and 0002 Well House Repairs (Both Wells) must be fully completed by August 13th to allow FS staff to start de-winterizing buildings. The “one structure” is assumed to be the Residence shown on Sheet CU-16, which is required to remain operational except for a duration of up to 1 week.; see answer to Q48 for more information about sequencing for the Residence.

Q50: Provide subsurface/geotechnical information along all horizontal directional drilling alignments, particularly the steep hillside bore between the campground and reservoir and all stream crossings. Identify anticipated rock, refusal conditions, groundwater, minimum bore depths, required casing, allowable drilling-fluid loss criteria, and whether rock drilling is to be included in the base bid.

A50: Forest Service has a soils report prepared for the drainfield that will service the Upper Loop A Bathhouse. This information will be posted to Sam.gov with this solicitation. No additional geotechnical or subsurface investigation information is available for this project. Offerors will rely on information already provided with the solicitation.

Specifications regarding horizontal directional drilling (HDD) are in spec section 33 05 23 Utility Horizontal Directional Drilling. Contractor shall be responsible to determine appropriate bore depths to prevent “frac-out" (accidental release of drilling fluid or mud to the ground surface or into a body of water). Specification 33 05 23 will be updated to reflect this requirement. It is the contractor’s responsibility to plan and prepare for the appropriate methods to apply for the boring locations identified. All likely material, including bedrock, should be accounted for in the preparation of the offeror’s bid. For drilling fluid losses, contractor shall comply with all federal, state and local regulations.

Q51: If an HDD alignment cannot be completed due to rock, cobbles, voids, loss of drilling fluid, or other concealed conditions, will an alternate alignment/open-cut method be authorized as a differing site condition, or must bidders include all such risk in the base price?

A51: Any perceived differing site conditions will be investigated and handled in accordance with the contract terms and conditions.

Q52: Please identify all permits already obtained for stream crossings, wetland impacts, dewatering, erosion/sediment control, or other environmental impacts, and clarify which remaining permits/fees are the contractor's responsibility.

A52: Review Section 5.5 of the Statement of Work (SOW), pages 7–8, for information about specific permits and approvals, including updates to this section.

This is the start of the file's text. The full file is on GovTribe.