Amend 0002_SUMMARY OF CHANGES.pdf
PDF 110 KB Posted
- Attached to
- Veterans Point Trail Rehabilitation Project
- Solicitation number
- 1240LT26Q0015
- Issued by
-
Department of Agriculture Forest Service
About this file
This is an Amendment Two (A0002) to a federal solicitation for the Veterans Point Trail Rehabilitation Project located in Black Hills National Forest, Pennington County, South Dakota. The amendment's primary purpose is to provide responses to contractor questions while maintaining all other existing terms and conditions of the original solicitation.
The solicitation number is 1240LT26Q0015 – A0002, issued by the USDA. The submission deadline for quotes remains February 24, 2026, at 9:00 a.m. Central Time, with submissions directed to Janice King (Contract Specialist) at janice.king@usda.gov and Lucas Dahlman (Contracting Officer) at lucas.dahlman@usda.gov. The email subject line must include "Veterans Point Trail Rehabilitation Quote – 1240LT26Q0015." The amendment addresses five contractor questions regarding quantity takeoffs for segmental retaining walls, asphalt rehabilitation, and gabion work; approved equipment access routes (existing trail and Path to Parking Lot with restrictions on crossing the pedestrian wooden bridge); public trail access during construction and required traffic control measures; designated staging and material storage areas; and working hour or seasonal restrictions. All answers reference specific sections within the Final Specifications (Attach 4) and Final Drawings (sheet 2 of 7 and sheet 5 of 7) for detailed requirements.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SUMMARY OF CHANGES
PROJECT: VETERANS POINT TRAIL REHABILIATION PROJECT
Black Hills National Forest, Pennington County, South Dakota
Solicitation Number: 1240LT26Q0015 – A0002
The purpose of Amendment Two (Amendment 0002) is as follows:
1) To provide responses to contractor’s questions;
2) All other terms and conditions remain the same.
Due date for quotes/responses remains the same: February 24, 2026, at 9:00 a.m. Central
Time. Email addresses for submission of quote: Janice King, Contract Specialist, at janice.king@usda.gov and Lucas Dahlman, Contracting Officer, at lucas.dahlman@usda.gov. In the submission of your quote, include in the email’s subject line: Veterans Point Trail Rehabilitation Quote – 1240LT26Q0015.
QUESTIONS and ANSWERS:
1. Are detailed quantity takeoffs available for the segmental retaining walls, asphalt rehabilitation areas, and gabion work, or should contractors rely solely on measurements from the drawings? See tables in the Final Drawings sheet 5 of 7.
2. What equipment access routes are approved for construction activities, and are there any restrictions on staging or material delivery paths? Equipment access is on the existing trail and the Path to Parking Lot shown in the Final Drawings sheet 2 of 7 and in Part 1.5.B: SITE
ACCESS of the General Requirements in the Final Specs, Attach 4. Equipment is not to cross the existing pedestrian wooden bridge.
3. Will the trail remain open to the public during construction, and if so, what level of traffic control is expected from the contractor? See Part 1.7.C: STAGING AREA of the General
Requirements in the Final Specs, Attach 4. See Part 1.11.A: PROTECTION OF PUBLIC of the
General Requirements in the Final Specs, Attach 4.
4. Are there designated staging and material storage areas available on site, and are there limits on temporary laydown zones? See Part 1.7.C: STAGING AREA of the General Requirements in the Final Specs, Attach 4.
5. Are there restrictions on working hours or seasonal limitations beyond those noted in the solicitation? See Part 1.10.A and Part 1.10.B: SCHEDULE of the General Requirements in the
Final Specs, Attach 4.
mailto:janice.king@usda.gov mailto:lucas.dahlman@usda.gov
File details come from the government source that posted it. Updated .