This document is Amendment 0005 to Request for Proposals (RFP) 1240LT24R0072 for the replacement of the Teton Canyon Bridge at the Caribou-Targhee National Forest in Idaho. The amendment addresses questions from prospective offerors and provides clarification on the acceptable access route and staging area for the project. Specifically, the Forest Service will establish a 10-15 foot wide access route using native soil, which the contractor may improve but must reclaim after project completion. The proposed staging area downstream of the bridge is acceptable, with the contractor responsible for reclaiming the disturbed area. The amendment also confirms the requirement for a 20% bid bond and extends the proposal due date to 18 October 2024. No special environmental or wildlife training is required for this project.

View the file

Other files

File Type Posted
Amendment 0007 - Page 2_QandAs_24OCT2024.pdf PDF
Amendment 0007 - 1st Page_QandAs and Extends to 28OCT2024.pdf PDF
Amendment 0006 - Page 2_Incorporate Bid Bond Clauses and Extend to 25OCT2024.pdf PDF
Attachment 10 - SF25 Performance Bond Form.pdf PDF
Attachment 9 - SF24 Bid Bond Form.pdf PDF
Attachment 11 - SF25A Payment Bond Form.pdf PDF
Amendment 0006 - 1st Page_11OCT2024.pdf PDF
Amendment 0005 - 1st Page_08OCT2024.pdf PDF
List of 30SEP2024 Site Visit Attendees_Teton Canyon Bridge.pdf PDF
Amendment 0004 - 1st Page_06OCT2024.pdf PDF
Amendment 0004 - Page 2_QandAs and Extends to 14OCT2024.pdf PDF
Amendment 0003 - Site Visit Announcement_24SEP2024.pdf PDF
Amendment 0002 - 2nd Page_18SEP2024_1240LT24R0072.pdf PDF
Attachment 8 - Treasure Lake Bridge Specs.pdf PDF
Amendment 0002 - 1st Page_18SEP2024_1240LT24R0072.pdf PDF
Attachment 5 - Photos for Sheep Bridge.pdf PDF
Attachment 6 - FP-14 Standard Specifications for Roads and Bridges.pdf PDF
Attachment 4 - Photos for Treasure Lake Bridge.pdf PDF
Amendment 0001 - 1st Page_13SEP2024_1240LT24R0072.pdf PDF
Attachment 1 - Plans and Drawings.pdf PDF
Amendment 0001 - Pages 2 and 3_13SEP2024_1240LT24R0072.pdf PDF
Attachment 2 - SOW_Teton Bridge Replacements.pdf PDF
Attachment 7 - DBA WD ID20240087 dtd 16FEB2024.pdf PDF
Attachment 3 - Bridges Project FS Supplemental Specs - FSSS.pdf PDF
Attachment 4 - DBA WD ID20240087 dtd 16FEB2024.pdf PDF
Attachment 1 - Plans and Drawings.pdf PDF
1240LT24R0072.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP 1240LT24R0072

Amendment 0005

a. The following are prospec ve offeror ques ons and the Government’s response to each of those ques ons:

Q13 – To gain access for the bridge, materials, and equipment, is it acceptable to establish a temporary path (12-15' wide) through a clearing in the tree line boarding the trail? A visit to the site revealed an approximate 366' path from the Teton Canyon Rd through a 15' sec on of the tree line to the bridge. This path will allow a limited amount of disrup on to the foliage. It appears that 2-3 small shrubs will need to be removed, which can be replanted upon demobiliza on. Addi onally, a 5' wide x 3' deep runoff will need to be filled temporarily with gravel or weed free soil to allow for equipment travel. This infill will also be reestablished to its original condi onal. Any other disturbances along the path of travel will be restored to the original condi on. A ached is a map showing the loca on of travel along with photos along the path. Please advise if this path of travel is acceptable.

A13 – The Forest Service will establish access to the Sheep Bridge site by reopening a currently reclaimed route. This is the only acceptable access route to the bridge site. The route will vary in wide from 10 to 15 feet and be constructed of na ve soil. The Forest will reclaim the access route a er the contractor completes the project. The contractor may make addi onal improvements to the access route as approved by the COR. Any improvements made by the contractor shall be reclaimed by the contractor. The proposed staging area immediately downstream of the bridge is acceptable. The contractor will be responsible for reclama on of the disturbed area. Map depic ng the access route the Forest Service will construct, is shown below.

RFP 1240LT24R0072

Amendment 0005

Q14 – Is this requiring a bid bond and if so, what percentage is it?

A14 – Yes, a bid bond will be required for this solicita on. The amount of the bid bond shall be 20% of the total proposed price, pursuant to FAR requirements.

Q15 – Is there any special environmental, or wildlife training required for this project?

A15 – There is no special environmental or wildlife training required for this project.

b. The deadline for receipt of proposals in response to this solicita on is hereby extended to 11:59 p.m. Central Time on 18 October 2024. Please email your Price and Technical Proposal to mary.harding@usda.gov.

File details come from the government source that posted it. Updated .