This document is an Amendment 0001 to a Request for Proposals (RFP) for the Teton Canyon Bridge Replacement Construction at Caribou-Targhee National Forest, Idaho, Solicitation Number 1240LT24R0072.

The key changes in this amendment include: (1) Providing the list of attachments to the solicitation, such as the Statement of Work, project specifications, and photos; (2) Revising the instructions for Factor 2 - Technical Approach to Performing the Work, which now requires the offeror to describe their proposed transport/logistics approach and provide a construction schedule; and (3) Adding a new Factor 3 - Key Personnel & Major Subcontractor(s), which will evaluate the qualifications of the proposed Site Superintendent/Foreman and Quality Control Manager, as well as the experience of major subcontractors. The amendment also changes Factor 3 - Price to Factor 4 - Price.

The solicitation is issued by the Department of Agriculture Forest Service, Region 4 - Intermountain Region, with proposals due by 5:00 p.m. Central Time on September 24, 2024.

View the file

Other files

File Type Posted
Amendment 0007 - Page 2_QandAs_24OCT2024.pdf PDF
Amendment 0007 - 1st Page_QandAs and Extends to 28OCT2024.pdf PDF
Amendment 0006 - Page 2_Incorporate Bid Bond Clauses and Extend to 25OCT2024.pdf PDF
Attachment 10 - SF25 Performance Bond Form.pdf PDF
Attachment 9 - SF24 Bid Bond Form.pdf PDF
Attachment 11 - SF25A Payment Bond Form.pdf PDF
Amendment 0006 - 1st Page_11OCT2024.pdf PDF
Amendment 0005 - Page 2_QandAs and Extends to 18OCT2024.pdf PDF
Amendment 0005 - 1st Page_08OCT2024.pdf PDF
List of 30SEP2024 Site Visit Attendees_Teton Canyon Bridge.pdf PDF
Amendment 0004 - 1st Page_06OCT2024.pdf PDF
Amendment 0004 - Page 2_QandAs and Extends to 14OCT2024.pdf PDF
Amendment 0003 - Site Visit Announcement_24SEP2024.pdf PDF
Amendment 0002 - 2nd Page_18SEP2024_1240LT24R0072.pdf PDF
Attachment 8 - Treasure Lake Bridge Specs.pdf PDF
Amendment 0002 - 1st Page_18SEP2024_1240LT24R0072.pdf PDF
Attachment 5 - Photos for Sheep Bridge.pdf PDF
Attachment 6 - FP-14 Standard Specifications for Roads and Bridges.pdf PDF
Attachment 4 - Photos for Treasure Lake Bridge.pdf PDF
Amendment 0001 - 1st Page_13SEP2024_1240LT24R0072.pdf PDF
Attachment 1 - Plans and Drawings.pdf PDF
Attachment 2 - SOW_Teton Bridge Replacements.pdf PDF
Attachment 7 - DBA WD ID20240087 dtd 16FEB2024.pdf PDF
Attachment 3 - Bridges Project FS Supplemental Specs - FSSS.pdf PDF
Attachment 4 - DBA WD ID20240087 dtd 16FEB2024.pdf PDF
Attachment 1 - Plans and Drawings.pdf PDF
1240LT24R0072.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP 1240LT24R0072

Amendment 0001

The following are changes to the solicitation:

a. Attachments to the solicitation are as follows:

Attachment 1 – Plans/Drawings Attachment 2 – Statement of Work (SOW) Attachment 3 – Bridges Project Forest Service Supplemental Specifications (FSSS) Attachment 4 – Photos for Treasure Lake Bridge Attachment 5 – Photos for Sheep Bridge Attachment 6 – FP-14 Standard Specifications for Roads and Bridges Attachment 7 – DBA WD ID20240087 dated 16FEB2024

b. The following are changes to Section L – Instructions to Offerors:

(1) Replace Factor 2 – Technical Approach to Performing the Work with the following revised version:

Factor 2 – Technical Approach to Performing the Work: Describe your planned approach to performing this construction project. For this factor, include:

(a) Your proposed transport and logistics approach for equipment, material and labor to the jobsite; and,

(b) A Construction Schedule showing activities, such as Completion of Bridge Design;

Submission of Shop Drawings to the Forest Service for Approval; Bridge Fabrication; Bridge Delivery; Removal and Disposal of Existing Bridge; Mobilization; Timing of Setting new Grade Beams (will it be late in the year or when the ground is frozen, for example?);

Instream Work Permit; etc. Use a Start Date of October 01, 2024 in your Construction Schedule (this Start Date is only for proposal evaluation purposes and is NOT a true Start Date).

(2) Add Factor 3 – Key Personnel & Major Subcontractor(s), as follows:

Factor 3 – Key Personnel & Major Subcontractor(s):

(a) Provide a detailed resume of your proposed Site Superintendent/Foreman who will interact directly with the COR and your proposed Quality Control Manager. The resumes of these two Key Personnel roles should include the individual’s full name; job title; job experience with dates and company names; training; license or certification.

(b) Provide the names of your proposed major Subcontractor(s) to include the Designer, Fabricator, Installer, etc.) and each Subcontractor’s role(s) in this project. Include the number of years of experience of your proposed Subcontractor(s).

RFP 1240LT24R0072

Amendment 0001

c. The following are changes to Section M – Evaluation Factors for Award:

(1) Add Factor 3 – Key Personnel & Major Subcontractor(s) to Paragraph M.3 Evaluation Factors, as follows:

Factor 3 – Key Personnel & Major Subcontractor(s)

The Government will evaluate the offeror’s proposed candidates for the Key Personnel roles of Site Superintendent/Foreman and Quality Control Manager to determine if these individuals possess the qualifications, knowledge and experience necessary to ensure the scope of the project is accomplished with quality workmanship, in accordance with the Government’s Plans and Specs and with minimal issues. The Government will also evaluate the offeror’s proposed Subcontractors to determine if they possess the resources and experience to execute their assigned taskings that are required for this project.

(2) Factor 3 – Price is changed to Factor 4 – Price.