This document is an amendment to a Request for Proposals (RFP) for the replacement of a bridge at Teton Canyon, Caribou-Targhee National Forest in Idaho. The key details are:

The amendment updates the list of attachments, incorporating Attachment 8 - Treasure Lake Bridge Drawings and Specs. It also provides responses to four questions from offerors, including clarification that the USFS requires pricing for installation of the Treasure Bridge. The due date for proposal submission has been changed to 11:59 p.m. Central Time on October 7, 2024.

The original solicitation, RFP 1240LT24R0072, is for the replacement of a bridge at Teton Canyon, Caribou-Targhee National Forest in Idaho. Proposals were originally due by 5:00 p.m. Central Time on September 24, 2024. The contracting agency is the Department of Agriculture Forest Service R4-Intermountain Region.

View the file

Other files

File Type Posted
Amendment 0007 - Page 2_QandAs_24OCT2024.pdf PDF
Amendment 0007 - 1st Page_QandAs and Extends to 28OCT2024.pdf PDF
Amendment 0006 - Page 2_Incorporate Bid Bond Clauses and Extend to 25OCT2024.pdf PDF
Attachment 10 - SF25 Performance Bond Form.pdf PDF
Attachment 9 - SF24 Bid Bond Form.pdf PDF
Attachment 11 - SF25A Payment Bond Form.pdf PDF
Amendment 0006 - 1st Page_11OCT2024.pdf PDF
Amendment 0005 - Page 2_QandAs and Extends to 18OCT2024.pdf PDF
Amendment 0005 - 1st Page_08OCT2024.pdf PDF
List of 30SEP2024 Site Visit Attendees_Teton Canyon Bridge.pdf PDF
Amendment 0004 - 1st Page_06OCT2024.pdf PDF
Amendment 0004 - Page 2_QandAs and Extends to 14OCT2024.pdf PDF
Amendment 0003 - Site Visit Announcement_24SEP2024.pdf PDF
Attachment 8 - Treasure Lake Bridge Specs.pdf PDF
Amendment 0002 - 1st Page_18SEP2024_1240LT24R0072.pdf PDF
Attachment 5 - Photos for Sheep Bridge.pdf PDF
Attachment 6 - FP-14 Standard Specifications for Roads and Bridges.pdf PDF
Attachment 4 - Photos for Treasure Lake Bridge.pdf PDF
Amendment 0001 - 1st Page_13SEP2024_1240LT24R0072.pdf PDF
Attachment 1 - Plans and Drawings.pdf PDF
Amendment 0001 - Pages 2 and 3_13SEP2024_1240LT24R0072.pdf PDF
Attachment 2 - SOW_Teton Bridge Replacements.pdf PDF
Attachment 7 - DBA WD ID20240087 dtd 16FEB2024.pdf PDF
Attachment 3 - Bridges Project FS Supplemental Specs - FSSS.pdf PDF
Attachment 4 - DBA WD ID20240087 dtd 16FEB2024.pdf PDF
Attachment 1 - Plans and Drawings.pdf PDF
1240LT24R0072.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP 1240LT24R0072

Amendment 0002

The following are changes to the solicitation:

a. Attachment 8 – Treasure Lake Bridge Specs is hereby incorporated into this solicitation.

Attachments to the solicitation are now as follows:

Attachment 1 – Plans/Drawings Attachment 2 – Statement of Work (SOW) Attachment 3 – Bridges Project Forest Service Supplemental Specifications (FSSS) Attachment 4 – Photos for Treasure Lake Bridge Attachment 5 – Photos for Sheep Bridge Attachment 6 – FP-14 Standard Specifications for Roads and Bridges Attachment 7 – DBA WD ID20240087 dated 16FEB2024 Attachment 8 – Treasure Lake Bridge Drawings and Specs

b. The following are offerors’ questions and the Government’s responses to those questions:

Q1 – Who do we contact for location, parking questions for a site visit to confirm access/site constraints, etc.?

A1 – Contact Jonathan Wheeler (Jonathan.wheeler2@usda.gov).

Q2 – In my review, I did not see any drawings for the second (optional) Treasure Bridge structure. Are these available for us to review/use for bid preparation?

A2 – Attachment 8 – Treasure Lake Bridge Drawings and Specs may be reviewed and used for proposal preparation, since it is now posted in SAM.gov.

Q3 – Is the grade beam design the same as the Sheep Bridge, or will drawings for these be provided?

A3 – Grade beam design is essentially the same as Sheep Bridge. Details are shown on the Treasure Bridge drawing.

Q4 – It appears that, for the Treasure Bridge, the USFS is not looking for installation, just supply. Can you confirm this?

A4 – The USFS requires pricing for installation of the Treasure Bridge. Installation of the Treasure Bridge are Line Items 00012 through 0019, which are Option Items 2A through 2H.

c. The due date and time for proposal submission is changed to 11:59 p.m. Central Time on October 7, 2024.