This document is a Statement of Work (SOW) for the Primrose Trail Reconstruction project on the Chugach National Forest in Seward, Alaska. The SOW outlines the scope of work for a 5-mile segment of the Primrose Trail, including trail reconstruction, drainage improvements, new trail construction, and obliteration of an existing steep/eroded trail section. Key tasks include brushing, trail tread restoration, surfacing with D-1 aggregate, drainage device construction, turnpike and puncheon installation, and new trail construction. The project has a period of performance from June 1, 2024 to November 1, 2026. The related federal contract opportunity solicitation number is 1240BJ24Q0010, issued by the U.S. Department of Agriculture Forest Service. The cut-off for pre-bid questions is August 5, 2024, and no substitution requests will be considered prior to award. Offerors must provide a complete technical proposal in response to the stated evaluation factors.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 1240BJ24Q0010-Amendment 2-SF30.pdf | ||
| 1240BJ24Q0010-Amendment 1-Solicitation-SF30.pdf | ||
| Amendment 1-PRIMROSE TRAIL DRAWINGS-ADDENDUM.pdf | ||
| Amendment 1-SOI Primrose Trail-ADDENDUM.pdf | ||
| Amendment 1-Work Log Primrose Trail-ADDENDUM.pdf | ||
| Amendment 1-RFI.pdf | ||
| Primrose Existing Conditions Photos.pdf | ||
| Primose Trail Reconstruction Specifications.pdf | ||
| Work Log Primrose Trail.pdf | ||
| Trail Design Parameters.pdf | ||
| PRIMROSE TRAIL DRAWINGS.pdf | ||
| Technical Evaluation Factors Questionnaire.pdf | ||
| Potential Primrose Staging Area Aerial Image.pdf | ||
| 1240BJ24Q0010 Primrose Trail Reconstruction Solicitation.pdf | ||
| General Decision Number AK20240002 01.05.2024.pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Primrose Trail Reconstruction
Statement of Work
Table of Contents Project Name General Information
1.0 Background and Purpose
2.0 Scope of Work
3.0 Location
Contractor Requirements
4.0 Technical Requirements / Tasks
5.0 Control of Traffic
6.0 Landscape Preservation
7.0 Use of Premises
8.0 Construction Stakes, Lines, and Grades
9.0 Disposal of Waste Material
10.0 Government Furnished Materials
11.0 Deliverables/Schedule
12.0 Coordination With Other Projects
13.0 Order of Precedence – Requirements, Specifications & Drawings
14.0 Applicable Laws, Regulations, Specifications and Guidance
Project Name Primrose Trail Reconstruction
General Information
1.0 Background and Purpose
This is a non-personal services contract to provide deferred maintenance services along an approximately 5-mile segment of Primrose Trail, on the Seward Ranger District, Chugach National Forest. General maintenance issues include extensive mud and poor drainage in low-lying sections, overly challenging and steep/eroded terrain requiring a reroute. The finished product following the completion of this contract will be a trail brought to USFS Class 3 Bicycle Design Parameters (Attachment 6, page 5), that can be sustainably maintained and is enjoyable for the public.
Period of performance June 1, 2024 – November 1, 2026
2.0 Scope of Work
This project is for extensive reconstruction and deferred maintenance of a 5-mile section of the Primrose Trail on the Chugach National Forest (CNF). A detailed list and descriptions are provided in Section 4.0, but a brief summary of the major work items include:
• Trail reconstruction consisting of 5 miles of brushing & general restoration (clearing, tread rehabilitation, removing protrusions, among others)
• Replacement of puncheon, turnpikes, drainage structures, and repair of stream fords.
• Over 4,000 LF of resurfacing existing trail surface (using D-1 aggregate, 6” depth).
• Obliteration of 1,347 LF of existing steep/eroded trail – average grade of around 30% at times.
• Construction of 1,368 LF of new trail, 36”-60” wide, with associated culverts (12”), puncheon, and over 1,000 LF of D-1 surfacing. New trail corridor will be through largely uplands territory with a grade up to 15%.
The breakdown is described below:
Base Bid:
• Mobilization
• Staking
• All trail work, excluding the re-route and obliteration (stations 245+00 to 258+68 on Work Log). These items will be broken down by individual task as shown on the Schedule of Items.
• Trail re-route and obliteration (stations 245+00 to 258+68 on Work Log)
3.0 Location
3.1 The project location is approximately 13 miles south of the community of Moose Pass. All work will be accessed from the Primrose Trailhead located at the end of Primrose Spur Rd (60.34°N; 149.37°W), near mile 17 of the Seward Highway. There is a large parking area at the end of the road near a boat launch, and a smaller access drive through the Primrose Campground. Contractor parking and staging is likely to be primarily in the boat launch parking lot. Access to the trailhead is gained by passing through the campground.
Boat launch must remain open and accessible to the public, no more than ¼ of the parking lot may be used to stage equipment, staging may only happen for 24 hours in a given week or as approved by COR.
3.2 While clearing and restoration work begins at the trailhead, the major work tasks begin approximately 0.5 miles from the trailhead.
3.3 There are no utilities available at the site. Cell-service is intermittent and unpredictable within the project area.
Contractor Requirements
4.0 Technical Requirements / Tasks
The Contractor shall provide the following trail maintenance tasks. See the attached specifications and drawings for task specific requirements and the full list of every work item. See the Work Log on Sheets 2-3, Drawings 900-02 and 900-03 of the drawing package for task location and quantity.
4.1 Work Log Staking: Contractor shall stake final work item locations for Government approval. Note that stations shown in Work Log are approximate to show sequencing and relative location of work items, some field deviation is anticipated. Staking will take place along the entire 5.0-mile section of trail where work is occurring.
4.2 Brush Cutting: Contractor shall cut and remove brush and other woody debris to the clearing limits defined within the plans. Brush cutting will take place along the entire 5.0-mile section of trail where work is occurring.
4.3 Existing Trail Restoration: Any existing deviations from the typical trail cross section and slope finish shall be restored as defined within the plans. This will occur along approximately 4.75 miles of the 5.0-mile work area.
4.4 Aggregate Surfacing: Where defined within the worklog, contractor shall provide D-1 aggregate surfacing on the trail tread surface, as defined within the plans. A total of 5,000+ LF of surfacing is expected, along with 75 LF of surfacing with rock retainers, as shown on the plans.
4.5 Drainage Device Construction and Maintenance: Contractor shall construct and maintain drainage dips, drainage ditches, and culverts as defined within the plans. Estimated quantities are:
4.5.1 Drain dip conversion or construction – 105 ea
4.5.2 Drain dip repair – 11 ea
4.5.3 Ditch repair or construction – 1,868 LF
4.5.4 Installation of 12” HDPE culvert – 212 LF, in lengths of 6’, 8’, and 12’
4.6 Construct Turnpike: This work consists of construction of turnpike sections, including excavation, embankment, retainers, geosynthetics, backfill, and drainage features. A total of 74 LF is required throughout the trail.
4.7 Construct Puncheon: This work consists of removal of the existing and construction of new puncheon, including excavation, embankment, backfill, and drainage features as shown on the plans. Decommissioning and removing existing puncheon are considered incidental to this task. Total new puncheon length is 124 LF for this project.
4.8 Obliteration of Existing Trail This work consists of removal and disposal of existing structures, including turnpikes, culverts, signs and posts, and other material within the trailway, above or below ground. This task will be required along 1,347 LF of trail that will be abandoned.
4.9 New Trail Construction Contractor shall construct new trail tread in a rerouted section of trail and obliterate the existing trail segment to be decommissioned. Work items for the reroute are provided within the Work Log and defined within the plans. New trail length is approximately 1,368 LF.
5.0 Control of Traffic
5.1 The contractor shall keep Primrose Trail open and maintained in such condition as to safely accommodate the public. No trail closures shall be in effect without written approval from the CO/COR.
5.2 The trail must be entirely passable for the Breath of Life run dates will be posted in the future estimated for 3 days in August, to include usable crossing structures in place. This will require safe and unimpeded access for large quantities of runners.
5.3 Temporary detours, approaches, crossings, and intersections with trails shall be provided and maintained in a safe and passable condition.
5.4 The contractor shall post warning signs on the trailheads for each trail to warn the public of work in progress, the times the work is being performed, and the trail status (open/closed) during working hours. This applies to all trailheads with direct links to the work site: The Primrose Trailhead, The Meridian Lakes Trailhead, and the Lost Lake Trailhead.
5.4.1 All signs shall conform to Section 6B-22 of the “Manual on Uniform Traffic Control Devices.”
6.0 Landscape Preservation
6.1 If a previously unidentified archaeological or historic site(s) is encountered, the contractor shall discontinue work in the general area of the site(s) and notify the contracting officer immediately. An active mine can be seen at mile 3.7 (mining equipment belongs to the miners and is private property). This is a historic site and the Contractor must not disturb or impact it in any way. The trail itself is historic and part of the INHT system, so alterations and modifications to the trail must strictly align with those described in this SOW, specifications, and project drawings unless approved otherwise by the CO.
6.2 All mineral materials, topsoil and straw or hay erosion control products used shall be certified as weed free under the State of Alaska’s Division of Agriculture weed free certification program.
6.2.1 Contractor’s equipment must be inspected for cleanliness prior to mobilizing to project location.
Coordinate with CO 14 days prior to mobilization.
6.3 Limit vegetation removal from May 1 – July 15. This includes clearing and grubbing, brushing, or any activity that would at all interfere with nesting migratory birds.
6.4 Rehabilitate and revegetate sites where damage has occurred to vegetation outside of the limits of work.
6.5 Operations shall be scheduled and conducted to minimize erosion of soils and to prevent silting and muddying of streams and rivers.
6.6 Pollutants such as raw sewage and other harmful materials shall not be discharged into or near streams and rivers or into natural or manmade channels leading thereto.
6.7 Waste motor oil, fuel, lubricant, bitumen, and similar hydrocarbons shall be collected and returned to the supplier. They shall not be wasted on the ground or buried.
6.8 All contractor furnished equipment and vehicles to be used at the job site shall be cleaned and free of invasive species (noxious weeds), seeds, external grease and oil and shall be inspected prior to entrance onto Federal lands. The restriction shall include equipment and vehicles intended for off-road use, whether they are owned, leased, or borrowed by the Contractor or Subcontractor.
6.9 Approval for the use of land-based motorized equipment such as ATVs less than 50” wide, small-scale excavators, and track haulers may be granted if the equipment is shown to be capable of operating within the trailway and/or at material sources for loading without damage to the surrounding area. The use of equipment outside of the trailway will not be allowed if it will damage vegetation or soil or create drainage problems. Cross-country movement of equipment, outside of the staked trailways, shall not be permitted unless approved in writing by the CO. Land based motorized equipment may be operated on the existing trail alignment.
6.10 Provide an Equipment Operation Plan that describes the type of equipment, how the equipment will used, safety precautions for the particular equipment, how the equipment will be moved to and from the work areas, and other considerations. The use of helicopters in the project area is allowed.
6.11 All protective plating and armoring shall be intact and properly functioning on the equipment to reduce the potential for damaging hydraulic hoses or the undercarriage.
6.12 Spill kit approved by OSHA for petroleum product leaks shall be always onsite.
6.13 All damage to trail tread, trail structures or water control structures caused by use of equipment will be repaired by the contractor at no expense to the Government.
6.14 Immediately extinguish, without expense to the Government, all fires on or in the vicinity of the project which are caused by the Contractor's employees, whether set directly or indirectly as a result of construction operations, without direction by the Forest Service.
7.0 Use of Premises
7.1 The area may be frequented by bears, which may become habituated to humans and may be attracted by activity and food. Maintain control of garbage and food so that no wildlife can access them.
7.2 All aircraft use dates; and take off, landing, and flight path locations need to be approved by the CO prior to project implementation.
7.2.1 Aircraft maintain a minimum landing distance of one-half mile from all observed mountain goats or Dall sheep.
7.2.2 Aircraft maintain a 1,500-foot minimum vertical distance from all observed mountain goats or Dall sheep.
7.2.3 Aircraft not allowed from October 1 through June 15.
7.3 Sanitation Facilities: Aside from the trailhead restroom facilities, the Contractor shall be responsible for providing and maintaining their own sanitation facilities in accordance with state and federal waste disposal regulations.
7.4 There are no known birds of prey nest trees in the vicinity of the project area, but if such trees are discovered no disturbance will be allowed within 330 feet of the trees and additional mitigation measures may be applied. The Contractor shall be compensated for any cost impacts associated with a reroute or other avoidance measures associated with the discovery of a bird of prey nest. See Specifications Section 1000 for additional wildlife and environmental guidance.
7.5 Before any suspension of work all trailways shall be left in a condition suitable for traffic.
8.0 Construction Stakes, Lines, and Grades
8.1 The Contractor is responsible for all field staking of the items on the Work Log, located on Sheets 2-3, Drawings
900-02 and 900-03, of the drawing package. The Government will review and approve the exact locations and provide technical guidance as needed.
8.2 The Government will flag the location of the re-route trail to guide staking on this section of the work.
9.0 Disposal of Waste Material
9.1 Remove all waste material from the project area and dispose offsite unless specified otherwise.
9.2 Native timber may be disposed of on-site but must be scattered (not stacked) and placed where not readily visible from the trail.
10.0 Government Furnished Materials
10.1 Borrow material for trail construction that is excavated in the construction of the trail. No borrow sites outside of the current and proposed trailway are available. Any additional fill materials must be procured offsite by the Contractor.
10.2 Rock material sourced onsite for trail construction or reconstruction shall only be taken from the trailway.
No borrow sources outside of the trailway are allowed unless designated and approved by the CO. Any additional rock needed for retainers or headwalls must be procured offsite by the Contractor.
11.0 Deliverables/Schedule
11.1 Tasks and Associated Deliverables: Timely submission of deliverables is essential to successful completion of this requirement. Schedules for key deliverables are shown below in Table 1. All deliverables shall be submitted electronically to the CO and COR. The Government shall review the Contractor's plans as submitted for completeness and applicability. Proposed modifications of Contractor's plans will be discussed with the Contractor prior to acceptance. The Contractor must allow a minimum of two weeks for each submittal review, one week for re-review, and four weeks for the FRP design and calculation review.
11.2 Reporting Requirements: The contractor is required to provide written progress reports weekly. The report can be submitted via email to the COR. The progress report shall cover all work completed during the specified period, status of material orders, and present the work to be accomplished during the subsequent period. This report shall also identify any problems that arose and a statement explaining how the problem was resolved. This report shall also identify any problems that have arisen but have not been completely resolved and provide an explanation. This report is not a substitute for regular communication between the contractor and the COR.
11.3 Project Plan and Schedule: Work schedule will be submitted with the Contractor’s proposal; if timelines change by more than five business days the Contractor must resubmit and/or keep CO updated of all changes in writing.
Table 1
12.0 Coordination With Other Projects
The section of the Seward Highway near this project is currently undergoing construction, which may complicate some contractor access and operations. Proper coordination with USFS and/or Alaska Department of Transportation may be necessary at times. The Seward Highway, MP 17 to 22.5 Rehabilitation project information can be found at: https://www.alaskanavigator.org/projects/seward-highway-mp-17-225-rehabilitation.
13.0 Order of Precedence – Requirements, Specifications & Drawings Any inconsistency in the specifications of this solicitation and any resultant contract shall be brought to the CO/COR for resolution, but general precedence occurs in the following order:
1) Statement of Work – Special Contract Requirements
2) Project Specifications
A. Trail Log/Work List
B. Standard Specifications
3) Contract Drawings
A. Drawings, figured dimensions over scaled dimensions
B. Drawings, large scale drawings over small scale drawings
Deliverable Objective Due
Time of Gov Approval After Submittal
Updated Work Schedule
To notify the government of when the contractor shall be on site performing work and of significant work milestones. Ref.
item 11.3
As changes arise.
7 Days
Weekly Status Report Report documenting tasks & issues weekly.
Ref Para 11.2
Every Friday by 4:00 PM AKST until completion of contract
7 Days
Traffic Control Plan
To ensure trails and roadways remain open and that all personnel have reduced risk of traffic related injuries. Reference:
909.10.01
One week prior to any work that conflicts or interferes with traffic.
7 Days
Equipment Operation Plan
To inform CO of intended equipment. Ref para 6.9
10 business days prior to mobilization to the site.
7 Days
Blasting Plan To inform CO of blasting work, if planned. 10 business days prior to planned commencement of work, if applicable.
7 Days
Helicopter Operations Plan
To inform CO of helicopter operations and safety plans, if planned.
One week prior to commencement of helicopter operations, if applicable.
7 Days https://www.alaskanavigator.org/projects/seward-highway-mp-17-225-rehabilitation
C. Schedules on drawings over notations on drawings
4) Staking on the ground
14.0 Applicable Laws, Regulations, Specifications and Guidance
14.0 Project specific drawings and specifications
14.1 FOREST SERVICE STANDARD SPECIFICATIONS FOR CONSTRUCTION OF TRAILS AND TRAIL BRIDGES ON FOREST SERVICE PROJECTS, 10/30/2014. These may be viewed online at:
https://www.fs.usda.gov/recreation/programs/trail-management/documents/plans/supporting_documents/Trail_Specifications.pdf
Note that this version supersedes EM-7720-103, Standard Specification for Construction and Maintenance of Trails (1996).
14.2 Manual on Uniform Traffic Control Devices (MUTCD): https://mutcd.fhwa.dot.gov/
14.3 Project Specifications are as follows:
Section 901—Terms, Format, Abbreviation and Definitions Section 902—Intent of Contract Section 904—Control of Materials Section 906—Measurement and Payment Section 905—Quality Assurance and Quantity Measurement Section 907—Mobilization Section 908—Construction Survey, Staking, Flagging and Cleanup Section 909—Maintenance for Traffic and Temporary Construction Access Section 911—Tread and Prism Section 912—Clearing Limits Section 913—Surfacing Section 914—Climbing Turn Section 917—Fords Section 919—Trailway Special Project Specifications: Solid Rock Removal Section 921 – Culverts Section 925—Ditches Section 927—Drain Dips Section 932—Turnpikes Section 934—Puncheons Section 983 – Removal of Structures and Obstructions Section 991—Aggregate and Rock Section 992 – Pipe Material Section 994 – Geosynthetic Material Section 1000—Supplemental Wildlife and Environmental Requirements
15.0 Attachments
1. Project Drawings
2. Project Specifications
3. Work Log
4. Photographs
5. Instructions for Proposal and Evaluation Criteria
6. National Trail Design Parameters
7. Staging Area Arieal Image https://mutcd.fhwa.dot.gov/
| Project Name |
| General Information |
| 1.0 Background and Purpose |
| 2.0 Scope of Work |
| 3.0 Location |
| Contractor Requirements |
| 4.0 Technical Requirements / Tasks |
| 5.0 Control of Traffic |
| 6.0 Landscape Preservation |
| 7.0 Use of Premises |
| 8.0 Construction Stakes, Lines, and Grades |
| 9.0 Disposal of Waste Material |
| 10.0 Government Furnished Materials |
| 11.0 Deliverables/Schedule |
| 12.0 Coordination With Other Projects |
| 13.0 Order of Precedence – Requirements, Specifications & Drawings |
| 14.0 Applicable Laws, Regulations, Specifications and Guidance |