Amendment 1-SOI Primrose Trail-ADDENDUM.pdf

PDF 381 KB Posted

Attached to
Primrose Trail Reconstruction Federal contract opportunity
Solicitation number
1240BJ24Q0010
Issued by
Department of Agriculture Forest Service

About this file

This document is an Amendment to Solicitation No. 1240BJ24Q0010 for the Primrose Trail Reconstruction project in Seward, Alaska within the Chugach National Forest.

The solicitation is for a contract to provide all required labor, equipment, and materials necessary to reconstruct and perform deferred maintenance on a 5-mile section of the Primrose Trail. The project location is approximately 13 miles south of Moose Pass, with access from the Primrose Trailhead. The solicitation includes a detailed bid schedule with various work items such as mobilization, brush cutting, trail restoration, aggregate surfacing, culvert installation, and new trail construction. All offerors will be required to provide a bid bond, and the successful awardee must provide performance and payment bonds. Prospective offerors must be registered in the System for Award Management (SAM) database. The cut-off for pre-bid questions is August 5, 2024, and no substitution requests will be considered prior to award. Offers must respond as described in Sections L and M, and proposals that fail to provide a complete technical response may be rejected.

View the file

Other files for this federal contract opportunity

Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation No. 1240BJ24Q0010 Primrose Trail Reconstruction

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS

B.1 SCHEDULE OF ITEMS – BID SCHEDULE_AMENDMENT 1

Item Task Measurement

Method Pay Unit QTY Cost/Unit

Total Cost

Base Bid Items 90701 Mobilization LSQ LS 1 90702 Work Log Staking LSQ LS 1 91210 Brush Cutting CQ MI 5 91106 Existing Trail Restoration CQ LF 24500 91300 Aggregate Surfacing (Type TSS-1) CQ LF 3790 91301 Aggregate Surfacing (Type TSS-2) CQ LF 26 91302 Trail Resurfacing, W/ Retainers. TSR-1 CQ LF 55 91303 Trail Resurfacing, W/ Retainers. TSR-2 CQ LF 20 91701 Construct Ford CQ EA 2 92101 New 12" Corrugated Culvert, 6' CQ EA 4 92102 New 12" Corrugated Culvert, 8' CQ EA 10 92103 New 12" Corrugated Culvert, 12' CQ EA 2 92104 Replace In-Kind Culvert, 8' CQ EA 9 92105 Replace In-Kind Culvert, 12' CQ EA 1 92205 Waterbar to Drain Dip Conversion CQ EA 47 92501 New Side Ditch CQ LF 395 92504 Repair Side Ditch CQ LF 1473 92701 Construct Drain Dip CQ EA 58 92706 Repair Drain Dip CQ EA 11 93201 Construct Turnpike CQ LF 74 93401 Construct puncheon CQ LF 10

Trail Re-route 91116 Obliterate Abandoned Trail CQ LF 1347 91150 New Trail Construction CQ LF 1,368 91260 Solid Rock Removal CQ LF 25 91300 Aggregate Surfacing (Type TSS-1) CQ LF 1091 92102 New 12" Corrugated Culvert, 8' CQ EA 2 93401 Construct puncheon CQ LF 114

PROJECT TOTAL

Unit of Measurements CQ = Contract Quantity EA = Each LF = Linear Foot LS = Lump Sum MI = Mile LSQ = Lump Sum Quantity

ADDENDUM : 92504 QTY CHANGED FROM 1473 TO 1510

Hampton Coogle Cross-Out maimoua Highlight

Solicitation No. 1240BJ24Q0010 Primrose Trail Reconstruction

B.2 SCHEDULE NOTES

Unique Entity ID (SAM): ________________________

EMAIL: ______________________________________

All offerors will be required to provide a Bid Bond (20%) with their proposal submission. Performance and Payment Bonds (100% each) will be required of the successful awardee.

Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price. Include bond payments under Pay Item 151(01) Mobilization.

NOTE: prospective awardee shall be registered and active in the System for Award Management (SAM) data base when submitting an offer and shall continue to be registered until time of award, during performance, and through final payment of a contract resulting from this solicitation. Information on registration may be obtained via the internet at: http://www.sam.gov. All contractors and vendors must complete the electronic version of the Representations and Certifications in the SAM system.

See Section L and Section M for Instructions to Offerors and Submittal Requirements.

PART I—THE SCHEDULE
SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS
B.1 SCHEDULE OF ITEMS – BID SCHEDULE
B.2 SCHEDULE NOTES
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C.1 SCOPE OF CONTRACT
This project is comprised of all required labor, equipment and materials necessary to perform the following work including but not limited to: reconstruction and deferred maintenance of a 5-mile section of the Primrose Trail on the Chugach National Fo...
C.2 PROJECT LOCATION
The project location is approximately 13 miles south of the community of Moose Pass. All work will be accessed from the Primrose Trailhead located at the end of Primrose Spur Rd (60.34 N; 149.37 W), near mile 17 of the Seward Highway. There is a large...
C.3 MAGNITUDE OF CONSTRUCTION PROJECT
C.6 SPECIFICATIONS APPLICABLE TO THIS INDIVIDUAL PROJECT
SPECIFICATIONS AND SUPPLEMENTAL SPECIFICATIONS LIST
C.8 PRODUCTS SAMPLES AND/OR SUBMITTALS
C.10 MATERIAL CERTIFICATIONS AND TESTING REPORTS
C.11 BIO-PREFERRED
SECTION D--PACKAGING AND MARKING
D.1 D.2 PROJECT LABELING FOR OFFICIAL CORRESPONDENCE
SECTION E--INSPECTION AND ACCEPTANCE
E.1 CLAUSES
52.246-12 Inspection of Construction (AUG 1996)
SECTION F--DELIVERIES OR PERFORMANCE
F.1 CLAUSES
G.1 CLAUSES
452.215-73 Post Award Conference (NOV 1996)
G.9 CONFORMITY WITH DRAWINGS AND SPECIFICATIONS
SECTION H--SPECIAL CONTRACT REQUIREMENTS
H.1 CLAUSES
STORAGE AND STOCKPILING OF MATERIALS
POTENTIAL SAFETY HAZARDS
LANDSCAPE PRESERVATION
PART II--CONTRACT CLAUSES
SECTION I--CONTRACT CLAUSES
I.1 CLAUSES
52.252-6 Authorized Deviations in Clauses (NOV 2020)
PART III--LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS
PART IV--REPRESENTATIONS AND INSTRUCTIONS
SECTION K--REPRESENTATIONS, CERTIFICATIONS, AND
OTHER STATEMENTS OF OFFERORS OR RESPONDENTS
K.1 PROVISIONS
L.1 PROVISIONS
52.252-1 Solicitation Provisions Incorporated by Reference (FEB 1998)
M.1 PROVISIONS
M.2 EVALUATION OF OFFERS
FACTOR 1: NON-PRICE EVALUATON CRITERIA
M-2 AWARD DETERMINATION

File details come from the government source that posted it. Updated .