About this file
This document is an Amendment to Solicitation No. 1240BJ24Q0010 for the Primrose Trail Reconstruction project in Seward, Alaska within the Chugach National Forest.
The solicitation is for a contract to provide all required labor, equipment, and materials necessary to reconstruct and perform deferred maintenance on a 5-mile section of the Primrose Trail. The project location is approximately 13 miles south of Moose Pass, with access from the Primrose Trailhead. The solicitation includes a detailed bid schedule with various work items such as mobilization, brush cutting, trail restoration, aggregate surfacing, culvert installation, and new trail construction. All offerors will be required to provide a bid bond, and the successful awardee must provide performance and payment bonds. Prospective offerors must be registered in the System for Award Management (SAM) database. The cut-off for pre-bid questions is August 5, 2024, and no substitution requests will be considered prior to award. Offers must respond as described in Sections L and M, and proposals that fail to provide a complete technical response may be rejected.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 1240BJ24Q0010-Amendment 2-SF30.pdf | ||
| Amendment 1-PRIMROSE TRAIL DRAWINGS-ADDENDUM.pdf | ||
| Amendment 1-Work Log Primrose Trail-ADDENDUM.pdf | ||
| 1240BJ24Q0010-Amendment 1-Solicitation-SF30.pdf | ||
| Amendment 1-RFI.pdf | ||
| Potential Primrose Staging Area Aerial Image.pdf | ||
| Trail Design Parameters.pdf | ||
| PRIMROSE TRAIL DRAWINGS.pdf | ||
| Technical Evaluation Factors Questionnaire.pdf | ||
| Primrose Existing Conditions Photos.pdf | ||
| Primose Trail Reconstruction Specifications.pdf | ||
| Work Log Primrose Trail.pdf | ||
| 1240BJ24Q0010 Primrose Trail Reconstruction Solicitation.pdf | ||
| General Decision Number AK20240002 01.05.2024.pdf | ||
| Primrose SOW_Trail.pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation No. 1240BJ24Q0010 Primrose Trail Reconstruction
PART I—THE SCHEDULE
SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS
B.1 SCHEDULE OF ITEMS – BID SCHEDULE_AMENDMENT 1
Item Task Measurement
Method Pay Unit QTY Cost/Unit
Total Cost
Base Bid Items 90701 Mobilization LSQ LS 1 90702 Work Log Staking LSQ LS 1 91210 Brush Cutting CQ MI 5 91106 Existing Trail Restoration CQ LF 24500 91300 Aggregate Surfacing (Type TSS-1) CQ LF 3790 91301 Aggregate Surfacing (Type TSS-2) CQ LF 26 91302 Trail Resurfacing, W/ Retainers. TSR-1 CQ LF 55 91303 Trail Resurfacing, W/ Retainers. TSR-2 CQ LF 20 91701 Construct Ford CQ EA 2 92101 New 12" Corrugated Culvert, 6' CQ EA 4 92102 New 12" Corrugated Culvert, 8' CQ EA 10 92103 New 12" Corrugated Culvert, 12' CQ EA 2 92104 Replace In-Kind Culvert, 8' CQ EA 9 92105 Replace In-Kind Culvert, 12' CQ EA 1 92205 Waterbar to Drain Dip Conversion CQ EA 47 92501 New Side Ditch CQ LF 395 92504 Repair Side Ditch CQ LF 1473 92701 Construct Drain Dip CQ EA 58 92706 Repair Drain Dip CQ EA 11 93201 Construct Turnpike CQ LF 74 93401 Construct puncheon CQ LF 10
Trail Re-route 91116 Obliterate Abandoned Trail CQ LF 1347 91150 New Trail Construction CQ LF 1,368 91260 Solid Rock Removal CQ LF 25 91300 Aggregate Surfacing (Type TSS-1) CQ LF 1091 92102 New 12" Corrugated Culvert, 8' CQ EA 2 93401 Construct puncheon CQ LF 114
PROJECT TOTAL
Unit of Measurements CQ = Contract Quantity EA = Each LF = Linear Foot LS = Lump Sum MI = Mile LSQ = Lump Sum Quantity
ADDENDUM : 92504 QTY CHANGED FROM 1473 TO 1510
Hampton Coogle Cross-Out maimoua Highlight
Solicitation No. 1240BJ24Q0010 Primrose Trail Reconstruction
B.2 SCHEDULE NOTES
Unique Entity ID (SAM): ________________________
EMAIL: ______________________________________
All offerors will be required to provide a Bid Bond (20%) with their proposal submission. Performance and Payment Bonds (100% each) will be required of the successful awardee.
Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price. Include bond payments under Pay Item 151(01) Mobilization.
NOTE: prospective awardee shall be registered and active in the System for Award Management (SAM) data base when submitting an offer and shall continue to be registered until time of award, during performance, and through final payment of a contract resulting from this solicitation. Information on registration may be obtained via the internet at: http://www.sam.gov. All contractors and vendors must complete the electronic version of the Representations and Certifications in the SAM system.
See Section L and Section M for Instructions to Offerors and Submittal Requirements.
| PART I—THE SCHEDULE |
| SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS |
| B.1 SCHEDULE OF ITEMS – BID SCHEDULE |
| B.2 SCHEDULE NOTES |
| SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK |
| C.1 SCOPE OF CONTRACT |
| This project is comprised of all required labor, equipment and materials necessary to perform the following work including but not limited to: reconstruction and deferred maintenance of a 5-mile section of the Primrose Trail on the Chugach National Fo... |
| C.2 PROJECT LOCATION |
| The project location is approximately 13 miles south of the community of Moose Pass. All work will be accessed from the Primrose Trailhead located at the end of Primrose Spur Rd (60.34 N; 149.37 W), near mile 17 of the Seward Highway. There is a large... |
| C.3 MAGNITUDE OF CONSTRUCTION PROJECT |
| C.6 SPECIFICATIONS APPLICABLE TO THIS INDIVIDUAL PROJECT |
| SPECIFICATIONS AND SUPPLEMENTAL SPECIFICATIONS LIST |
| C.8 PRODUCTS SAMPLES AND/OR SUBMITTALS |
| C.10 MATERIAL CERTIFICATIONS AND TESTING REPORTS |
| C.11 BIO-PREFERRED |
| SECTION D--PACKAGING AND MARKING |
| D.1 D.2 PROJECT LABELING FOR OFFICIAL CORRESPONDENCE |
| SECTION E--INSPECTION AND ACCEPTANCE |
| E.1 CLAUSES |
| 52.246-12 Inspection of Construction (AUG 1996) |
| SECTION F--DELIVERIES OR PERFORMANCE |
| F.1 CLAUSES |
| G.1 CLAUSES |
| 452.215-73 Post Award Conference (NOV 1996) |
| G.9 CONFORMITY WITH DRAWINGS AND SPECIFICATIONS |
| SECTION H--SPECIAL CONTRACT REQUIREMENTS |
| H.1 CLAUSES |
| STORAGE AND STOCKPILING OF MATERIALS |
| POTENTIAL SAFETY HAZARDS |
| LANDSCAPE PRESERVATION |
| PART II--CONTRACT CLAUSES |
| SECTION I--CONTRACT CLAUSES |
| I.1 CLAUSES |
| 52.252-6 Authorized Deviations in Clauses (NOV 2020) |
| PART III--LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS |
| PART IV--REPRESENTATIONS AND INSTRUCTIONS |
| SECTION K--REPRESENTATIONS, CERTIFICATIONS, AND |
| OTHER STATEMENTS OF OFFERORS OR RESPONDENTS |
| K.1 PROVISIONS |
| L.1 PROVISIONS |
| 52.252-1 Solicitation Provisions Incorporated by Reference (FEB 1998) |
| M.1 PROVISIONS |
| M.2 EVALUATION OF OFFERS |
| FACTOR 1: NON-PRICE EVALUATON CRITERIA |
| M-2 AWARD DETERMINATION |
File details come from the government source that posted it. Updated .