Amendment 0002_RFI Responses with updated specs_drawings.pdf

PDF 21 MB Posted

Attached to
NCCCWA Fire System Upgrades, Kearneysville, WV
Solicitation number
1232SA26Q0485
Issued by

About this file

This document is a Pre-Bid Request for Information (RFI) Responses package for the Leetown, WV Fire Systems Upgrades project, issued by USDA on May 13, 2026. The RFI responses address 48 questions submitted by potential contractors regarding project scope, technical requirements, and implementation approach for fire suppression and fire alarm system upgrades.

Key project requirements include installation of two fire pumps in N+1 redundancy configuration with the existing pump retained as secondary backup; replacement of the fire pump controller with a same-manufacturer unit to enable lead-lag power interlock; installation of a new dry sprinkler system in Tank Area 131; fire alarm system replacement with hardwired interconnection to existing equipment; and comprehensive disinfection and testing. The contractor must provide a fire pump with 500 gpm capacity at 65 psi rated pressure, implement automatic sequencing to prevent simultaneous pump operation, and maintain service during construction through careful outage planning per IFC and NFPA 241. Critical clarifications confirm that no underground piping changes are included, existing underground conduit and wire should be reused only for small connections under 3 feet, the existing 4-inch fire department connection should be relocated outside the building, and the space in Tank Area 131 is classified as light hazard. The specification requires compliance with NFPA 13, NFPA 20, NFPA 72, and ARS Manual 242.2, with shop drawings and final acceptance tests required before project completion within 240 days. The contractor is responsible for water flow testing and must provide a schedule accommodating long-lead item procurement while the generator has been confirmed capable of supporting dual pump operation.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Leetown, WV Fire Systems Upgrades Pre-Bid RFI Responses 5/13/2026

RFI # Summary Request for information Response By Date

1 How many weldolets need to be replaced? Replace weldolets as required after inspection for each sprinkler and armover/sprig. Contractor will have to warranty install. Adam Paterson 5-May-26

2 Can the contractor cut out leaks, or does the government require entire branch lines to be replaced?

Replace weldolets, as required, after inspection for each sprinkler and armover/sprig. Contractor will have to warranty install. Branchline is connected through couplings. Follow threading and pipe schedule requirements indicated on the FX001. Contractor to evaluate means and methods for required replacement in accordance with construction documents. Adam Paterson 5-May-26

3 Is the security system part of the fire alarm system scope? Security system central reporting system is integrated with fire alarm central reporting in the radionics D9412 panel. Security interface is limited to the panel internal wiring and disconnection and removal of fire alarm wiring. Security must be commissioned as a dedicated security reporting DACT. Fire alarm system reporting must be removed from the Radionics D9412 panel and provided with a new DACT separate from the security system. Both systems must be commissioned by licensed/certified and experienced personnel. Adam Paterson 5-May-26

4 What kind of fire watch does the government require? Follow IFC and NFPA 241 for fire watch criteria along with notes on sheets FA001/ FX001 on outage limitations. Systems must be kept working to the greatest extent possible. Coordinate outages with contracting officer representatives. Adam Paterson 5-May-26

5 Will USDA provide a list of corroded sprigs, arm-overs, and hangers to be replaced, or is quantification the contractor's responsibility?

See fire suppression demolition drawings. Existing sprinklers are indicated on the demolition sheets.

Each sprinkler has an armover/sprig with note 1 or 2. New sprinklers should be installed back into same locations. Provide new hangars as required to conduct work. Adam Paterson 5-May-26

6 What is the maximum number of simultaneous fire alarm or sprinkler zones that can be out of service at one time?

Follow procedures for biocontrol on sprinkler drawings and specifications. Coordinate outages for zones with client. Contractor to determine best sequencing using means and methods on outages. Outages require fire watch and continued overnight outages across the entirety of the two zones are not permitted.

Adam Paterson 5-May-26 7 Is the existing fire pump retained as backup, or removed at project end? Final project will have two fire pumps in N+1 redundancy. Provide schedule of value for replacement of existing fire pump, as alternative. Existing fire pump controller has been shifted to base bid for lead lag power interlock between fire pumps. Adam Paterson 5-May-26

8 Can a temporary bypass be proposed to maintain service while the fire pump is being demolished. Please advise whether use of the bypass will be accepted without requiring a fire watch, or if a fire watch will be required for the duration of the impairment/demolition period

Contractor to determine means and method. Existing fire pump replacement is an option/alternate which should have a schedule of value replacement cost. Baseline fire pump is existing to remain with a second new primary fire pump to be provided adjacent to the existing fire pump. See updated drawings. Bypass to be discussed along with project schedule with USDA and building. Adam Paterson 5-May-26

9 Also, FD112 Note 2 calls for demolition of a 2-inch line , however based on the site walk and page FX102, the existing piping is a 4-inch run. Please confirm that the existing 4-inch line is to be demolished and new pipe is to be installed.

Existing FDC sprinkler pipe is 4" and intended to be existing to remain. Demolish fire department connection and locate fire department connection outside building where fire department can access. See updated drawings. Adam Paterson 5-May-26

10 Detail 2 on FD112 shows removal of a 2 inch pipe. We were unable to locate this pipe during the site walk and the Facility Personnel were not aware of the need to remove a pipe in this area. The route shown for this pipe is the same as the pipe to the FDC. Please clarify what pipe, if any, is to be removed in this area.

Do not demolish the existing 4" fire department sprinkler line in the corridor. The 2" line is shown on as-built drawings as a connection to the inspector test connection which is existing to remain. Demolish the existing fire department connection inside the extended outdoor fish tank area which the fire department cannot access. See revision 1 drawing. Adam Paterson 5-May-26

11 Keynote 1 on FD401 indicates the existing Backflow Preventer is to be reused. Please confirm this is listed for use in the vertical position.

Backflow preventer is 6" Ames 2000SEand is listed for vertical installation.

Adam Paterson 5-May-26

12 Keynote 7 on FD401 states” …retain the fire pump to relocate.” Please confirm this should state ” …retain the fire pump controller to relocate.”

Confirmed. Relocate existing fire pump controller to make room for the new primary fire pump controller. See revision 1 drawing FX401. Adam Paterson 5-May-26

13 See FX102. This shows new Dry System Zone 1-3. Please confirm the Hazard Classification to be used for this room.

The space is filled with tanks of water and was determined to be light hazard. Have your NICET designer qualify and confirm this design sprinkler hazard classification. Adam Paterson 5-May-26

14 FX401 Keynote 6. This mentions a Battery Terminal Cabinet. Electric Fire Pumps do not have batteries. Please clarify.

See revision 1 FX401 note 6. Provide new fire pump controller and connect to existing fire pump.

Coordinate power interlock between two fire pump controllers using native in panel controls. Adam Paterson 5-May-26

15 Spec 211313 Paragraph 1.2.1.1 calls for a Fire Hydrant Flow Test as well as a Fire Pump Test. Generally both tests are not required. Please confirm if just a Fire Pump Test is sufficient.

Provide fire hydrant flow test and fire pump test.

Adam Paterson 5-May-26

16 Spec 211313 Paragraph 1.2.3 references the QCFPE. Does this individual need to be a 3rd party?

Individual does not need to be 3rd party.

Adam Paterson 5-May-26

17 Spec 213000 Paragraph 1.2 is regarding sequencing of the two fire pumps. The existing fire pump controller is not capable of sequencing and will need to be replaced in order to do this. Please confirm if we are to replace the existing controller. It should also be noted that the existing Fire Pump Controller is obsolete and parts are no longer available.

Replace existing fire pump controller with same manufacturer as new fire pump controller to allow for lead lag interface and interlock. See revised specification and FX401.

Adam Paterson 5-May-26 18 Spec 213000 Paragraph 2.4.1.1 calls for all Sch. 40 pipe. Other sections of the spec as well as notes on the drawings allow Sch 10 pipe for sizes 2 ½” and larger. Please clarify which piping can be Sch. 10.

Provide minimum schedule 10 pipe for wet pipe black steel pipe for 2-1/2" and larger. See revised specification.

Adam Paterson 5-May-26 19 Spec 213000 Paragraph 2.5 is regarding Disinfection Materials. Typically this only applies to projects with new underground piping. Please confirm this does not apply to this project.

Follow NFPA 13 criteria for disinfection. No underground pipe changes are included in the project.

Adam Paterson 5-May-26 20 Our fire pump supplier has stated that the wiring arrangement for power to the two fire pumps is not correct. Each needs to have a dedicated supply and they can’t be spliced together. Please evaluate code on this and advise of needed changes.

NFPA 20 and NEC 70 Section 695. The fire pumps can be wired off the same feeder if they each have a controller with fully independent disconnecting means as well as there is an alternate source (generator).

Evelyn Di Savino 5-May-26 21 Due to the extensive work in the fire pump room, the fire pump will be out of service for several weeks, which will leave all of the sprinkler systems unable to deliver sufficient water pressure. This will require around the clock fire watch. Please provide details on the level of fire watch required.

Do not remove the existing fire pump out of service. Plan new connections to limit outages. Follow IFC and NFPA 241 for fire watch criteria along with notes on sheets FA001/ FX001 on outage limitations.

Systems must be kept working to the greatest extent possible. Coordinate outages with contracting officer representatives.

Adam Paterson 5-May-26 22 In order to install the new Dry System in Tank Area 131, we will need to access the roof level to install piping. In addition to the new main pipes shown on FX102, there will be 2 or 3 branch lines that will run the full length of the building. This room is mostly filled with tanks and there isn’t room to walk between the tanks let alone room for a manlift. Some tanks were empty during the site visit. Is it possible for temporary changes in the usage of the tanks be made so that approximately one fourth of the tanks are emptied and temporarily removed to allow for pipe installation? If yes, this would need to happen multiple times until the system installation is complete. If no, please state what can be done temporarily to allow for installation of the new piping.

Ongoing laboratory experiments will not allow for movement of tanks. Plan for scaffolding.

Adam Paterson 5-May-26 23 It was stated during the site visit that an alternate price is to be provided to replace the existing fire pump. This is not shown on the Schedule of Pricing. Please advise if this is to be provided. This pump is severely corroded and should be replaced.

Provide schedule of value for replacement of existing fire pumpas an option/alternative. If alternate is not selected fire pump is existing to remain as secondary backup fire pump. Existing fire pump controller will be disconnected and removed. Provide two new fire pump controlers, one for each fire pump capable of native lead lag power sequence and interlock by same manufacturer. Adam Paterson 5-May-26

24 There are references to ARS Manual 242.1. This document appears to be for project design requirements. As this project is fully designed, please clarify how this applies to the SOW for this project.

Contractor must follow ARS Manual 242.2 criteria in designing both the fire suppression and fire alarm criteria in addition to NFPA 13 and NFPA 72 for contractor provided shop drawings, product data, etc.

Adam Paterson 5-May-26 25 Please confirm whether a Potter fire alarm system is acceptable, assuming it meets all applicable NFPA, UL, and project performance requirements.

Follow design criteria, if Potter meets the criteria listed on construction documents then manufacturer is approved. Adam Paterson 5-May-26

26 If Potter is not acceptable, please identify any required or pre-approved manufacturers or provide the basis for acceptability (e.g., “open protocol,” compatibility with existing campus systems, or required integration platform)

Solo source manufacturer is not approved per CFR. Follow design criteria, if Potter meets the criteria listed on construction documents then manufacturer is approved.

Adam Paterson 5-May-26 27 Do you require this interconnection to be achieved by hard-wired circuits, a listed wireless solution, or are either acceptable as long as the complete system complies with NFPA and the design intent?

Reconnect to existing hardwire copper between panel locations. Provide associate terminations, box, conduit as required by ARS manual 242.1 and NFPA 70.

Adam Paterson 5-May-26 28 If hard-wired interconnection is required, please clarify whether the project scope includes providing and installing new underground raceways and cabling between the affected buildings, or if an existing pathway is to be reused.

No new underground wire expected. Reuse existing underground conduit and wire between panels.

Adam Paterson 5-May-26 29 Reuse existing conduit where its condition is acceptable and it meets current code; and Small reuse of conduit, less than 3 feet, is approved where connecting to existing auxiliary equipment, such as fire suppression monitoring and control and generators. Stand up new fire alarm system and then demolish existing fire alarm system following commissioning of provided fire alarm system.

Adam Paterson 5-May-26 30 Temporarily cross-trip (interconnect) the new and old fire alarm panels, in a code-compliant manner, in order to bring the new system up in sections while reusing existing conduit and wiring as areas are converted?

Contractor to plan out connections to auxiliary equipment with limited outages. Do not reuse existing wire and conduit. Do not plan it reuse existing wire, conduit, ceiling tiles, backboxes, mounts, hangars, etc. Adam Paterson 5-May-26

31 The existing system must still remain active until final cutover, and Existing system to remain active until coordinated interfaces with telephone, fire suppression, generator, etc. Adam Paterson 5-May-26

32 The overall phasing, labor, and material scope will be significantly increased, which may impact the feasibility of the 240-day completion requirement.

Propose a schedule your team can meet and list out critical path items per specification requirements.

Adam Paterson 5-May-26

33 Do you require any monitoring of lab fume hoods (e.g., sash position, exhaust fan status, low airflow, or shutdown status) by the fire alarm system?

Do not shut down dedicated exhaust fans. No fire alarm interface is required.

Adam Paterson 5-May-26

34 If yes, please identify the required points (supervisory/trouble, shutdown interlocks, etc.)

and provide revised drawings/details or a written description of required interfaces.

No interface required with lab hood exhaust fans.

Adam Paterson 5-May-26 35 NFPA requirements generally call for a 2-hour fire-rated fire pump room. During the site visit, the existing Fire Pump Room was observed not to be fully 2-hour rated, specifically:

the block walls are not sealed to the underside of the deck.

IBC 913 and NFPA 20 calls for a 1 hour fire barrier in non-high rise sprinklered buildings, however enclosing the room is not part of the project scope. This will be handled by the building under another project. Provide new penetrations in the CMU wall with the expectation for a 1 hour fire barrier.

Adam Paterson 5-May-26 36 Due to the complexity and safety implications of this high-voltage/generator scope, may the

Government schedule an additional focused site visit specifically for electrical subcontractors to inspect the existing normal and emergency power feeds, generator connections, and routing to the fire pump controller?

Contracting Officer to advise on additional site visit date & time.

Adam Paterson 5-May-26 37 In light of the apparent corrosion and the overall scope of this fire protection upgrade, should the existing 6" DCDA backflow be assumed to be replaced with a new unit rather than reused? If replacement is acceptable or preferred, please confirm that the contractor should base pricing on providing a new 6" DCDA backflow assembly installed per the new arrangement.

Corrosion on backflow preventer is on surface. Internal pipe inspections were conducted and backflow is in working order.

Adam Paterson 5-May-26 38 Please confirm the correct required jockey pump pressure rating and discharge setting. Provide pressure maintenance pump for minimum 10 gpm @ 115 psi. Contractor to determine incoming water supply pressure at fire pump and adjust as required by their design. Adam Paterson 5-May-26 39 Is the new fire pump controller required to also be an ATS-type (with integral automatic transfer switching between normal and emergency power), or is a different configuration acceptable (e.g., separate ATS upstream with a standard fire pump controller)?

Yes. Provide new fire pump with integrated ATS.

Adam Paterson 5-May-26 40 If an ATS-type fire pump controller is required, has the existing generator been evaluated for available capacity to support simultaneous running of the fire pump and any other connected emergency loads, including potential operation of both pumps where applicable? If not, please provide:

Generator has been evaluated and can provide power. Be accurately aware that contractor must program design the two fire pumps to never run at the same time. Electrical wiring must be provided to interlock the two pumps to never draw run power at the same time. The existing fire pump will be come a backup redundant fire pump for the building, second to the new fire pump provided under this project unless alternate is accepted. Adam Paterson 5-May-26

41 Direction on whether the contractor is to assume sufficient generator capacity or include evaluation/upgrade in the scope.

Generator has been evaluated and can provide required power in accordance with NFPA 20, NFPA 37, and NFPA 110.

Adam Paterson 5-May-26 42 The existing solicitation package, as received, does not appear to include a separate set of detailed electrical drawings specifically addressing the high-voltage/generator power work associated with the fire pump controller removal/relocation and other power modifications.

Please confirm whether there are separate electrical drawings for this project. If such drawings exist, can they be issued as an additional attachment to ensure accurate and safe design and pricing of the electrical scope? If no dedicated electrical drawings exist, please clarify whether the contractor is expected to design-build the electrical portion (under performance criteria) and, if so, what design parameters and existing documentation will be provided.

Electrical drawings were included in sheets 23 to 29. Confirm all drawings were included in solicitation package.

Evelyn Di Savino 5-May-26 43 Can the Government clarify whether any waivers or variances to the Buy American / domestic content requirements may be considered for long-lead fire protection equipment (e.g., fire pumps and controllers) where compliant products would jeopardize the 240-day completion period?

No waivers, provide schedule with long lead items indicate for required schedule adjustments.

Adam Paterson 5-May-26 44 Alternatively, can the Government confirm whether the contract completion time (240 days after award) is flexible and subject to adjustment via amendment if documented manufacturer lead times for compliant components exceed that period?

No waivers, provide schedule with long lead items indicate for required schedule adjustments.

Adam Paterson 5-May-26 45 Can the Government provide a current city (or site) water supply flow test (static, residual, and flow at a known demand), or will the contractor be responsible for performing and basing design on a new flow test?

Provide fire pump and fire hydrant water flow tests per FX001 notes.

Adam Paterson 5-May-26 46 Can the Government provide a current city (or site) water supply flow test (static, residual, and flow at a known demand), or will the contractor be responsible for performing and basing design on a new flow test?

Contractor responsible for testing.

47 The solicitation suggests removal of the existing fire pump and possible reuse, but does not clearly state whether:

• The existing pump is to be fully overhauled and reinstalled,

• Evaluated and reused “as is” if acceptable, or

• Replaced entirely with a new pump.

Existing fire pump to remain. Provide new fire pump controller for existing fire pump. Se revised drawings.

Adam Paterson 5-May-26 48 Due to project complexities, such as lab scheduling and access, tank protection measures, overhead work with overhead obstacles and lab access requirements, such showering out, we assess the current prescribed Period of Performance will be difficult and perhaps unattainable.

Propose a schedule your team can meet and list out critical path items per specification requirements.

NCCCWA Fire System Upgrades 12305B24F0185

SECTION 01 20 00

PRICE AND PAYMENT PROCEDURES

11/20, CHG 5: 02/25

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification.Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Schedule of Prices; G

SD-03 Product Data

Weight Certificates

1.2 SCHEDULE OF PRICES

1.2.1 Data Required

Schedule of Prices must have cost summarized and totals provided for each construction category. Provide a detailed breakdown of the Contract price, giving quantities for each of the various kinds of work, unit prices, and extended prices. Indirect activities (e.g., meetings, presentations, submittals, surveys, haul road or storage yard maintenance, dust control, security) will not be cost loaded. Evenly distribute the costs across the associated construction activities. Contractor overhead and profit including salaries for field office personnel, if applicable, must be proportionately spread over all pay items and not included as individual pay items.

1.2.2 Payment Schedule Instructions

Payments will not be made until the Schedule of Prices has been submitted to and accepted by the Contracting Officer. For construction phase progress payment(s), the Schedule of Prices must include detailed construction activities. The Schedule of Prices must be fully developed with detailed construction line items.

For Fast-Tracked or Critical Path Submittals of construction projects, the Schedule of Prices must includeconstruction line items for each fast-tracked/ critical path phase(s), submitted to and accepted by the Contracting Officer during the Post Award Kickoff Meetings and confirmed prior to starting construction work in that phase.

1.3 CONTRACT COST BREAKDOWN

The Contractor must furnish within 30 days after the date of Notice to Proceed, and prior to the submission of its first partial payment estimate, a breakdown of its single job pay item or items which will be

SECTION 01 20 00 Page 1 reviewed by the Contracting Officer as to propriety of distribution of the total cost to the various accounts. Any unbalanced items as between early and late payment items or other discrepancies will be revised by the Contracting Officer to agree with a reasonable cost of the work included in the various items. This Contract cost breakdown will then be utilized as the basis for progress payments to the Contractor.

1.4 CONTRACT MODIFICATIONS

In conjunction with the Contract Clause DFARS 252.236-7000 Modification Proposals-Price Breakdown, and where actual ownership and operating costs of construction equipment cannot be determined from Contractor accounting records, base equipment use rates listed.

1.5 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT

1.5.1 Content of Invoice

Requests for payment will be processed in accordance with the Contract Clause FAR 52.232-27 Prompt Payment for Construction Contracts and FAR 52.232-5 Payments Under Fixed-Price Construction Contracts. Invoices not completed in accordance with contract requirements will be returned to the Contractor for correction of the deficiencies. Include the documents listed below in the requests for payment.

a. The Contractor's invoice, following specification criteria, showing in summary form, the basis for arriving at the amount of the invoice.

Invoicing must include certification by Quality Control (QC) Manager as required by the Contract.

b. Monthly Work-hour report.

c. Updated Construction Progress Schedule and tabular reports required by the contract.

d. Contractor Safety Self Evaluation Checklist.

e. Updated submittal register.

f. Solid Waste Disposal Report.

g. Certified payrolls.

h. Updated testing logs.

i. Other supporting documents as requested.

1.5.2 Submission of Invoices

Monthly invoices and supporting forms for work performed through the anniversary award date of the Contract must be submitted to the Contracting Officer within 5 calendar days of the date of invoice. For example, if Contract award date is the 7th of the month, the date of each monthly invoice must be the 7th and the invoice must be submitted by the 12th of the month.

SECTION 01 20 00 Page 2

1.5.3 Final Invoice

a. A final invoice must be accompanied by the certification required by DFARS 252.247.7023 Transportation of Supplies by Sea, and the Contractor's Final Release. If the Contractor is incorporated, the Final Release must contain the corporate seal. An officer of the corporation must sign and the corporate secretary must certify the Final Release.

b. For final invoices, the original Contractor's Final Release Form must be provided directly to the respective Contracting Officer prior to submission of the final invoice. Once receipt of the original Final Release Form as been confirmed by the Contracting Officer, the Contractor must then submit final invoice and attach a copy of the Final Release Form .

c. Final invoices not accompanied by the Contractor's Final Release and required certifications associated with USDA requirements and NFPA 13, NFPA 20, and NFPA 72 record of completion forms will be considered incomplete and will be returned to the Contractor.

1.6 PAYMENTS TO THE CONTRACTOR

Payments will be made on submission of itemized requests by the Contractor which comply with the requirements of this section, and will be subject to reduction for overpayments or increase for underpayments made on previous payments to the Contractor.

1.6.1 Obligation of Government Payments

The obligation of the Government to make payments required under the provisions of this Contract will, at the discretion of the Contracting Officer, be subject to reductions and suspensions permitted under the FAR and agency regulations including the following in accordance with FAR

32.103 Progress Payments Under Construction Contracts:

a. Reasonable deductions due to defects in material or workmanship;

b. Claims which the Government may have against the Contractor under or in connection with this Contract;

c. Unless otherwise adjusted, repayment to the Government upon demand for overpayments made to the Contractor; and

d. Failure to maintain accurate "as-built" or record drawings in accordance with FAR 52.236.21 and the contract.

e. Failure to submit accurate monthly schedule updates in accordance with the contract.

1.6.2 Payment for Onsite and Offsite Materials

Progress payments may be made to the Contractor for materials delivered on the site, for materials stored off construction sites, or materials that are in transit to the construction sites under the following conditions:

a. FAR 52.232-5(b) Payments Under Fixed Price Construction Contracts.

b. Materials delivered on the site, but not installed, and off-site

SECTION 01 20 00 Page 3 materials to be considered for progress payment must be major high cost, long lead, special order, or specialty items, not susceptible to deterioration or physical damage in storage or in transit to the construction site. Examples of materials acceptable for payment consideration include, but are not limited to, structural steel, non-magnetic steel, non-magnetic aggregate, equipment, machinery, large pipe and fittings, precast/prestressed concrete products, plastic lumber (e.g., fender piles/curbs), and high-voltage electrical cable. Materials not acceptable for payment include consumable materials such as nails, fasteners, conduits, gypsum board, glass, insulation, and wall coverings.

c. Provide the Contracting Officer with documentation (e.g., Purchase Orders or Material Contracts) to justify payment for materials in advance of installation. When appropriate, include the Defense Priorities and Allocations System (DFAS) ratings (e.g., DX or DO) on purchase orders or material contracts to ensure timely delivery.

d. Materials to be considered for progress payment prior to installation must be specifically and separately identified in the Contractor's estimates of work submitted for the Contracting Officer's approval in accordance with Schedule of Prices requirement of this Contract.

Requests for progress payment consideration for such items must be supported by documents establishing their value (e.g., paid invoices) and that the title requirements of the clause at FAR 52.232-5 Payments Under Fixed-Price Construction Contracts have been met.

e. Ensure materials are adequately insured and protected from theft and exposure. Provide insurance documentation (e.g., Builder's Risk Insurance) which covers the overall value of the materials to be paid in advance of installation.

f. Provide a written consent from the surety company with each payment request for offsite materials.

g. Materials to be considered for progress payments prior to installation must be stored either in Hawaii, Guam, Puerto Rico, or the Continental United States. Other locations are subject to written approval by the Contracting Officer.

h. Materials in transit to the job site or storage site are not acceptable for payment.

1.7 SINGLE JOB PAYMENT ITEMS

Payment items for the work of this Contract for which Contract job payments will be made are listed in the [BIDDING][PRICING] PROPOSAL SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, are included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

SECTION 01 20 00 Page 4

1.7.1 Mobilization and Demobilization

1.7.1.1 Payment

Payment will be made for costs associated with mobilization and demobilization and other direction in specifications and standard USDA manual 242.1.

1.7.1.2 Unit of Measure

Unit of measure: Summarize schedule of prices data above under the following.

1. Fire Alarm system

2. Fire Pump 1

3. Fire Pump Controller 1

4. Fire Pump Controller 2

5. Electrical to fire pump 1 and controller 1

6. Electrical fire pump and fire pump controller 2

7. Demolition fire alarm and fire suppression

8. Fire Alarm Commissioning

9. Fire Pumps Commissioning

10. Security Commissioning job.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

SECTION 01 20 00 Page 5

SECTION 21 30 00

FIRE PUMPS

04/08, CHG 1: 08/13

PART 1 GENERAL

1.1 SUMMARY

Except as modified in this Section or on the drawings, install fire pumps in conformance with NFPA 20 , NFPA 70 , and NFPA 72 . In the event of a conflict between specific provisions of this specification and applicable NFPA standards, this specification governs. Devices and equipment for fire protection service must be UL Fire Prot Dir listed or FM APP GUIDE approved. Interpret all reference to the authority having jurisdiction to mean the Contracting Officer or the Contracting Officer Representative Division .

1.2 SEQUENCING

1.2.1 Primary Fire Pump

Provide primary fire pump that automatically operates when the pressure drops to 90 psi. Provide pumps that continue to run until shut down manually. The fire pump must automatically stop operating when the system pressure reaches 105 psi and after the fire pump has operated for the minimum pump run time specified herein.

1.2.2 Secondary Fire Pump

Operate secondary fire pump at 20 psi increments, set below the primary fire pump starting pressure. The fire pump must automatically stop running at 115 psi and after the fire pump has operated for the minimum pump run time. Prevent fire pumps from starting simultaneously and start sequentially at intervals of 5 to 10 seconds. The owner intends only to use the existing fire pump as a backup to the new fire pump, in the event the new fire pump is de-energized for maintenance. The electrical system will only support one fire pump running.

1.2.3 Pressure Maintenance Pump

Operate pressure maintenance pump when the system pressure drops to 100 psi.

Stop pump automatically when the system pressure reaches 115 psi and after the pump has operated for the minimum pump run time specified herein.

1.3 FIRE PUMP INSTALLATION RELATED SUBMITTALS

The Fire Protection Specialist must prepare a list of the submittals, from the Contract Submittal Register, that relate to the successful installation of the fire pump(s), no later than 7 days after the approval of the Fire Protection Specialist and the Manufacturer's Representative.

Include a letter of approval signed and dated by the Fire Protection Specialist with the submittals identified on this list when submitted to the Government.

1.4 REFERENCES

The publications listed below form a part of this specification to the

SECTION 21 30 00 Page 1 extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME)

ASME B16.3 (2021) Malleable Iron Threaded Fittings, Classes 150 and 300

ASME B16.5 (2020) Pipe Flanges and Flanged Fittings NPS 1/2 Through NPS 24 Metric/Inch Standard

ASME B16.18 (2021) Cast Copper Alloy Solder Joint Pressure Fittings

ASME B16.22 (2021) Wrought Copper and Copper Alloy Solder Joint Pressure Fittings

ASME B16.26 (2024) Standard for Cast Copper Alloy Fittings for Flared Copper Tubes

ASME B16.39 (2020) Standard for Malleable Iron Threaded Pipe Unions; Classes 150, 250, and 300

ASME B31.1 (2022) Power Piping

AMERICAN WATER WORKS ASSOCIATION (AWWA)

AWWA 10084 (2017) Standard Methods for the Examination of Water and Wastewater

AWWA B300 (2024) Hypochlorites

AWWA B301 (2024) Liquid Chlorine

AWWA C111/A21.11 (2023) Rubber-Gasket Joints for Ductile-Iron Pressure Pipe and Fittings

AWWA C606 (2022) Grooved and Shouldered Joints

ASTM INTERNATIONAL (ASTM)

ASTM A47/A47M (1999; R 2022; E 2022) Standard Specification for Ferritic Malleable Iron Castings

ASTM A53/A53M (2024) Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless

ASTM A183 (2014; R 2020) Standard Specification for Carbon Steel Track Bolts and Nuts

ASTM A193/A193M (2024) Standard Specification for Alloy-Steel and Stainless Steel Bolting Materials for High-Temperature Service and Other Special Purpose Applications

ASTM A194/A194M (2024) Standard Specification for Carbon

SECTION 21 30 00 Page 2

Steel, Alloy Steel, and Stainless Steel Nuts for Bolts for High-Pressure or High-Temperature Service, or Both

ASTM A536 (1984; R 2019; E 2019) Standard Specification for Ductile Iron Castings

ASTM A795/A795M (2021) Standard Specification for Black and Hot-Dipped Zinc-Coated (Galvanized) Welded and Seamless Steel Pipe for Fire Protection Use

ASTM B42 (2020) Standard Specification for Seamless Copper Pipe, Standard Sizes

ASTM B62 (2017) Standard Specification for Composition Bronze or Ounce Metal Castings

ASTM B75/B75M (2020) Standard Specification for Seamless Copper Tube

ASTM B88 (2022) Standard Specification for Seamless Copper Water Tube

ASTM B135/B135M (2017) Standard Specification for Seamless Brass Tube

ASTM D2000 (2018) Standard Classification System for Rubber Products in Automotive Applications

ASTM F436 (2011) Hardened Steel Washers

FM GLOBAL (FM)

FM APP GUIDE (updated on-line) Approval Guide https://www.approvalguide.com/

NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)

NEMA MG 1 (2021) Motors and Generators

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 20 (2025) Standard for the Installation of Stationary Pumps for Fire Protection

NFPA 70 (2023) National Electrical Code

NFPA 72 (2025) National Fire Alarm and Signaling Code

NFPA 1963 (2019) Standard for Fire Hose Connections

NATIONAL INSTITUTE FOR CERTIFICATION IN ENGINEERING TECHNOLOGIES

(NICET)

NICET 1014-7 (2012) Program Detail Manual for Certification in the Field of Fire Protection Engineering Technology (Field

SECTION 21 30 00 Page 3

Code 003) Subfield of Automatic Sprinkler System Layout

UL SOLUTIONS (UL)

UL 448 (2020) UL Standard for Safety Centrifugal Stationary Pumps for Fire-Protection Service

UL Fire Prot Dir UL Product IQ (updated online) at https://productiq.ulpropsector.com/en

1.5 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government. Submit the following in accordance with Section

01 33 00 SUBMITTAL PROCEDURES:

The USDA representative.

SD-01 Preconstruction Submittals

Fire Pump Installation Related Submittals; G

Fire Protection Specialist; G

No later than 14 days after the Notice to Proceed and prior to the submittal of the fire pump installation drawings

SD-02 Shop Drawings

Installation Drawings; G

As-Built Drawings; G

Piping Layout; G

Pump Room; G

SD-03 Product Data

Catalog Data; G

Spare Parts; G

Preliminary Tests; G

At least 14 days prior to the proposed date and time to begin Preliminary Tests

Field Tests; G

At least 2 weeks before starting field tests

Manufacturer's Representative; G

SECTION 21 30 00 Page 4

Field Training; G

SD-06 Test Reports

Preliminary Tests; G

3 copies of the completed Preliminary Tests Reports, no later that 7 days after the completion of the Preliminary Tests.

Final Inspection and Tests; G

SD-07 Certificates

Fire Protection Specialist; G

No later than 14 days after the Notice to Proceed and prior to the submittal of the fire pump installation drawings

Qualifications of Welders; G

Qualifications of Installer; G

Preliminary Test Certification; G

Final Test Certification; G

SD-10 Operation and Maintenance Data

Operating and Maintenance Instructions; G

At least 14 days prior to conducting field training

Flow Meter; G

Submit Data Package 2 for flow meter and controllers in accordance with Section 01 78 23 OPERATION AND MAINTENANCE DATA.

1.6 EXTRA MATERIALS

Submit Spare Parts data for each different item of equipment and material specified. Include a complete list of parts and supplies, with current unit prices and source of supply, and a list of parts recommended by the manufacturer to be replaced after 1 year and 3 years of service. Include a list of special tools and test equipment required for maintenance and testing of the products supplied by the Contractor.

1.7 QUALITY ASSURANCE

1.7.1 Fire Protection Specialist

Perform work specified in this section under the supervision of and certified by the Fire Protection Specialist. Submit the name and documentation of certification of the proposed Fire Protection Specialists. The Fire Protection Specialist is an individual who is a registered professional engineer and a Full Member of the Society of Fire Protection Engineers or who is certified as a Level IV Technician by National Institute for Certification in Engineering Technologies (NICET) in the Automatic Sprinkler System Layout subfield of Fire Protection Engineering Technology in accordance with NICET 1014-7 . Engage the Fire

SECTION 21 30 00 Page 5

Protection Specialist regularly in the design and installation of the type and complexity of system specified in the Contract documents. The specialist is an individual who has served in a similar capacity for at least three systems that have performed in the manner intended for a period of not less than 6 months.

1.7.2 Qualifications of Welders

Submit certificates of each welder's qualifications prior to site welding;

certifications more than one year old are not acceptable.

1.7.3 Qualifications of Installer

Prior to installation, submit data for approval showing that the Contractor has successfully installed fire pumps and associated equipment of the same type and design as specified herein, or that he has a firm contractual agreement with a subcontractor having such required experience. Include the names and locations of at least two installations where the Contractor, or the subcontractor referred to above, has installed such systems. Indicate the type and design of each system and certify that each system has performed satisfactorily in the manner intended for a period of not less than 18 months.

1.7.4 Preliminary Test Certification

When preliminary tests have been completed and corrections made, submit a signed and dated certificate with a request for a formal inspection and tests.

1.7.5 Final Test Certification

Concurrent with the Final Acceptance Test Report, submit certification by the Fire Protection Specialist that the fire pump installation is in accordance with the contract requirements, including signed approval of the Preliminary and Final Acceptance Test Reports. Submit data for approval showing the name and certification of all involved individuals with such qualifications at or prior to submittal of drawings.

1.7.6 Manufacturer's Representative

Perform work specified in this section under the supervision of and certified by a representative of the fire pump manufacturer. Submit the name and documentation of certification of the proposed Manufacturer's Representative, concurrent with submittal of the Fire Protection Specialist Qualifications. Engage the Manufacturer's Representative regularly in the installation of the type and complexity of fire pump(s) specified in the Contract documents. The representative is an individual who has served in a similar capacity for at least three systems that have performed in the manner intended for a period of not less than 6 months.

1.8 DELIVERY, STORAGE, AND HANDLING

Protect all equipment delivered and placed in storage from the weather, excessive humidity and temperature variations, dirt and dust, or other contaminants. Additionally, either cap or plug all pipes until installed.

SECTION 21 30 00 Page 6

PART 2 PRODUCTS

2.1 MATERIALS AND EQUIPMENT

a. Provide materials and equipment that are standard products of a manufacturer regularly engaged in the manufacture of such products and that essentially duplicates items that have been in satisfactory use for at least 2 years prior to bid opening.

b. Submit manufacturer's catalog data included with the Fire Pump Installation Drawings for each separate piece of equipment proposed for use in the system. Indicate the name of the manufacturer of each item of equipment, with data annotated to indicate model to be provided. In addition, provide a complete equipment list that includes equipment description, model number and quantity. Catalog data for material and equipment includes, but is not limited to, the following:

(1) Fire pumps, drivers and controllers including manufacturer's certified shop test characteristic curve for each pump. Shop test curve may be submitted after approval of catalog data but must be submitted prior to the final tests.

(2) Pressure maintenance pump and controller.

(3) Piping components.

(4) Valves, including gate, check, globe and relief valves.

(5) Gauges.

(6) Hose valve manifold test header and hose valves.

(7) Flow meter.

(8) Restrictive orifice union.

(9) Associated devices and equipment.

c. Provide a nameplate that identifies the manufacturer's name, address, type or style, model or serial number, contract number and accepted date; capacity or size; system in which installed and system which it controls and catalog number for all equipment. Affix standard nameplates securely in a conspicuous place and easy to read to pumps and motors. Provide nameplates and markings in accordance with UL 448 .

Provide electric motor nameplates with the minimum information required by NFPA 70 , Section 430-7.

2.2 FIRE PUMP

Provide electric motor driven fire pump. Provide pump capacity rated at 500 gpm with a rated net pressure of 65 psi. Furnish no less than 150 percent of rated flow capacity at not less than 65 percent of rated net pressure. Provide centrifugal in-line fire pump. Equip horizontal pump with automatic air release devices. Use maximum rated pump speed of 3560 rpm when driving the pump at rated capacity. Provide pump that is automatic start and automatic stop. Provide pump conforming to the requirements of UL 448 . Ensure fire pump discharge and suction gauges are oil-filled type.

SECTION 21 30 00 Page 7

2.3 REQUIREMENTS FOR FIRE PROTECTION SERVICE

2.3.1 General Requirements

Provide Materials and Equipment that have been tested by Underwriters Laboratories, Inc. and are listed in UL Fire Prot Dir or approved by Factory Mutual and listed in FM APP GUIDE. Where the terms "listed" or "approved" appear in this specification, such means listed in UL Fire Prot Dir or FM APP GUIDE.

2.3.2 Alarms

Provide audible and visual alarms as required by NFPA 20 on the controller. Provide remote supervision as required by NFPA 20 , in accordance with NFPA 72 under Section 28 31 70. Provide remote alarm devices located as indicated. Activate alarm signal upon the following conditions: electric motor controller has operated into a pump running condition, loss of electrical power to electric motor starter, and phase reversal on line side of motor starter. Provide weatherproof exterior alarm devices. Provide alarm silencing switch and red signal lamp, with signal lamp arranged to come on when switch is placed in OFF position.

2.4 ABOVEGROUND PIPING COMPONENTS

2.4.1 Pipe Sizes 2.5 inches and Larger

2.4.1.1 Pipe

Provide piping consisting of ASTM A53/A53M, Weight Class STD (Standard), Schedule 10, Type E or Type S, Grade A; black steel pipe. Join steel pipe by means of flanges welded to the pipe or mechanical grooved joints only.

Do not join piping by welding or weld fittings. Galvanize suction piping on the inside in accordance with NFPA 20 .

2.4.1.2 Grooved Mechanical Joints and Fittings

Provide joints and fittings that are designed for no less than 175 psi service and are the product of the same manufacturer. Provide malleable iron fitting and coupling houses conforming to ASTM A47/A47M, Grade 32510;

ductile iron conforming to ASTM A536, Grade 65-45-12. Provide flush type gasket that fills the entire cavity between the fitting and the pipe.

Provide cadmium plated or zinc electroplated, heat-treated steel nuts and bolts conforming to ASTM A183.

2.4.1.3 Flanges

Provide ASME B16.5 , Class 150 flanges. Provide flanges at valves, connections to equipment, and where indicated.

2.4.1.4 Gaskets

Provide AWWA C111/A21.11 , cloth inserted red rubber gaskets.

2.4.1.5 Bolts

Provide ASTM A193/A193M , Grade B7 bolts. Do not extend bolts less than three full threads beyond the nut with bolts tightened to the required torque.

SECTION 21 30 00 Page 8

2.4.1.6 Nuts

Provide ASTM A194/A194M , Grade 7 nuts.

2.4.1.7 Washers

Provide washers meeting the requirements of ASTM F436. Provide flat circular washers under all bolt heads and nuts.

2.4.2 Piping Sizes 2 inches and Smaller

2.4.2.1 Steel Pipe

Provide ASTM A795/A795M , Weight Class STD (Standard), Schedule 40, Type E or Type S, Grade A, zinc-coated steel pipe with threaded end connections.

Provide ASME B16.3 , Class 150, zinc-coated threaded fittings. Provide ASME B16.39 , Class 150, zinc-coated unions.

2.4.2.2 Copper Tubing

Provide copper tubing that is ASTM B88, Type L or K, soft annealed.

Provide ASME B16.26 , flared joint fittings. Provide pipe nipples consisting of ASTM B42 copper pipe with threaded end connections.

2.4.3 Pipe Hangers and Supports

Provide adjustable hangers and supports that are UL listed UL Fire Prot Dir or FM approved FM APP GUIDE. Finish of rods, nuts, washers, hangers, and supports must be zinc-plated after fabrication.

2.4.4 Valves

Provide valves that are UL listed UL Fire Prot Dir or FM approved FM APP GUIDE for fire protection service and with flange or threaded end connections.

2.4.4.1 Gate Valves and Control Valves

Provide outside screw and yoke (O.S.&Y.) type gate valves and control valves which open by counterclockwise rotation. Butterfly-type control valves are not permitted.

2.4.4.2 Tamper Switch

Equip the suction control valves, the discharge control valves, valves to test header and flow meter, and the by-pass control valves with valve tamper switches for monitoring by the fire alarm system.

2.4.4.3 Check Valve

Check valve must be clear open, swing type check valve with flange or threaded inspection plate.

2.4.4.4 Relief Valve

Provide spring operated type relief valve conforming to NFPA 20 . Provide a means of detecting water motion in the relief lines where the discharge is not visible within the pump house.

SECTION 21 30 00 Page 9

2.4.4.5 Circulating Relief Valve

Provide an adjustable circulating relief valve for each fire pump in accordance with NFPA 20 .

2.4.4.6 Suction Pressure Regulating Valve

Provide suction pressure regulating valve that is FM approved FM APP GUIDE.

Monitor suction pressure through a pressure line to the controlling mechanism of the regulating valve. Arrange valve in accordance with the manufacturer's recommendations.

2.4.5 Hose Valve Manifold Test Header

Construct header of steel pipe. Provide ASME B16.5 , Class 150 flanged inlet connection to hose valve manifold assembly. Provide approved bronze hose gate valve with 2.5 inch National Standard male hose threads with cap and chain; locate 3 feet above grade in the horizontal position for each test header outlet. Ensure welding is metallic arc process in accordance with ASME B31.1 .

2.4.6 Pipe Sleeves

Provide a pipe sleeve at each location where piping passes entirely through walls, ceilings, roofs, and floors, including pipe entering buildings from the exterior. Secure sleeves in position and location during construction. Provide sleeves of sufficient length to pass through entire thickness of walls, ceilings, and floors. Provide one inch minimum clearance between exterior of piping or pipe insulation, and interior of sleeve or core-drilled hole. Firmly pack space with mineral wool insulation.