This document outlines a federal contract opportunity for the modernization of the Agricultural Research Technology Center in Salinas, California. The project involves demolishing outdated buildings and constructing new facilities in two phases, including a West Lab/Office, East Lab/Office, and Headhouse/Greenhouse. The contract will be awarded using best value tradeoff to the offeror providing the best combination of past performance, team experience, and price/cost factors. The estimated period of performance is 1440 calendar days. The North American Industry Classification System code is 236220 and the small business set-aside amount is $36.5 million. The solicitation documents will be available on FedBizOpps on August 28, 2019, with a site walkthrough scheduled for September 12th. Proposals are due on October 11, 2019. The contract incorporates biobased product requirements.

View the file

Other files

Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

1232SA19R0033

x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

ARS-1232SA

BELTSVILLE MD 20705

RM 3-2102

5601 SUNNYSIDE AVENUE

USDA ARS ACQUISITION AND PROPERTY D

12/30/20190008

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

08/30/2019

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The purpose of this modification is to post the collected RFI responses to date (attached to amendment), the ARTC Sustainable Design Narrative, and revised drawings and specifications that address the relocation of temporary greenhouses from Hartnell College property to ARTC Salinas property.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

STEPHEN STOLTE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

NSN 7540-01-152-8070

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

USDA ARTC Salinas

12/27/2019

Amendment No. 8

RFI Responses

RFI # QUESTION ANSWER CONTRACTOR DATE RECEIVED DATE ANSWERED ANSWERED BY

1 We would like to submit the attached documentation for consideration to have Nordic Façade Panels, Crystal approved to bid as an “equal” to the specified Cembonit fiber cement product.

Nordic Façade Panels are approved as a bidding substitution in Section 07 44 56.

Western Specialty

Fabrications 9/4/2019

HDR

2 We respectfully submit for your consideration a request to approve products as an accepted substitute on USDA Agricultural Technology

Center (17-518857).

Please find links below for the following supporting documentation:

• Substitution request form

• Technical data sheets and MSDS forms for the appropriate product(s), confirming performance as specified

Substitution rejected - Use specified materials

Scranton Products 9/5/2019

HDR

3 1. We respectfully request that the government extend the current due date, October 11, 2019, 3-weeks to allow offerors to review the extensive information provided in the RFP, communicate the information with the subcontractor market, and assemble a competitive proposal that provides best value to the government.

Extended in AMD 01

Mortenson 9/17/2019

Extended in AMD 01 Steve Stolte

4 2. We respectfully request that the government extend the current RFI deadline, September 20, 2019, 1-week to September 27, 2019.

Extended in AMD 01

Mortenson 9/17/2019

Extended in AMD 01 Steve Stolte

5 Several (EL02, EL03, EP01, EP02, EP03) of the electrical plans are not printing correctly, apparently the room walls are drawn differently than on other pages, and disappear when printing, can you re-issue those pages with corrected layers?

Revised PDFs will be provided with

Amendment 002 JM Electric 9/19/2019

SETTY

6 We are requesting a time extension to the bid opening of four weeks

(one Month) to allow solicitation of proposals from local and non-local vendors. Due to complexity of the project specific trades need to be identified and interviewed so that proposal is submitted based on the criteria required in the solicitation

Extended in AMD 01 and 06. New bid date is tentively January 7, 2020.

Avila Construction 9/19/2019

Extended in AMD 01 Steve Stolte

Amendment No. 8

RFI Responses

7 If it affects the construction timeline, will a time allowance be given for delays of material purchase due to market availability?

The contractor would be expected to manage the procurement of long lead time items and factor that into their schedule. Any delays as a result of unforeseen market conditions or a failure for a supplier to meet their obligations would need to be looked at on a case by case basis by the EPM and CO.

JM Electric 9/19/2019

Steve Stolte

8 With a winter start date; there may be rains that delay the construction, will a time allowance be given?

Weather delays will be addressed post award. The contractor should keep a record of all days they are unable to work because of any unplanned events such as adverse weather conditions or

Government shut downs, JM Electric 9/19/2019

Steve Stolte

9 To what extent is the electrical contractor responsible for the design side of the project? It appears additional design is needed for:

Fire Alarm – specialist engineers required

Lutron lighting control

Cathode Protection system - requires specialist

Coordinated power supply - and generator –requires an Electrical

Engineer.

Shop drawings for noted systems are typical of construction projects. Coordinate with approved vendors to submit detailed shop drawings for review and approval.

JM Electric 9/19/2019

SETTY-Electrical

10 Are there any specifications for the EVS charging stations, and who is providing them? Only empty conduits and boxes are required for future EV charging stations at locations shown on drawings. The EV charging stations will be provided under a separate contract. See response to 49.

JM Electric 9/19/2019

SETTY-Electrical

11 Can we do our own testing, as we are a TEGG certified testing company? (26.081.4.1 Also see 26.24.13.3.5)

Testing services should be provided by a neutral Third Party JM Electric 9/19/2019

SETTY-Electrical

12 Can you clarify what is intended by this section regarding plugs

(26.09.23.2.1.1)?

Provide connections as required per selected manufacturer requirements.

JM Electric 9/19/2019

SETTY-Electrical

Amendment No. 8

RFI Responses

13 Regarding luminaires requiring a photocell switch, can this be disregarded, as there are light sensors in areas to control the lights?

(26.09.23.2.2.7)

Connect exterior fixtures via central photocell as per contract documents. All light fixtures are to be interfaced via the central lighting control system.

JM Electric 9/19/2019

SETTY-Electrical

14 Are there going to be any motorized window treatments controlled by

Lutron system?

No motorized window treatments are anticipated.

JM Electric 9/19/2019

SETTY-Electrical

15 Who will locate Keypads for the Lutron system- the architect or by our design?

Locate switches per contract documents.

JM Electric 9/19/2019

SETTY-Electrical

16 Are all switches to be Lutron system switches? All light switches must be compatible with the approved lighting control system.

JM Electric 9/19/2019

SETTY-Electrical

17 Is the Lutron needed to interface with the Isolation greenhouses? Lighting controls in the Isolation

Greenhouse do not need to be interfaced with the Lighting

Control System serving the Lab and Greenhouse/Headhouse structures.

JM Electric 9/19/2019

SETTY-Electrical

18 26.20.3.1.4 shows that 1/2 inch conduit is OK for lighting, but plans say all conduit shall be ¾”, so Is ½” OK or not?

All conduits shall be 3/4" minimum.

JM Electric 9/19/2019

SETTY-Electrical

19 Is High altitude EMP (HEMP) a condition here - for any wires?

(26.20.3.1.5.2+4)

High altitude EMP (HEMP) is not a condition here.

JM Electric 9/19/2019

SETTY-Electrical

20 No pipe in floor slabs - does this mean horizontally only? (26.20.3.1.10) No horizontal pipe runs will be permissble in floor slabs as noted. JM Electric 9/19/2019

SETTY-Electrical

21 For flexible conduit for lights, it shows 3/2"; is this a typo, and is MC

Cable 1/2' OK? (26.20.3.1.5.15)

Provide minium 3/4" flexible steel conduit.

JM Electric 9/19/2019

SETTY-Electrical

22 Please provide DOD instruction 8500.01 and 8510.01 for cybersecurity

(26.24.3.1.5.1.6)

DOD instructions are available through the DOD website JM Electric 9/19/2019

SETTY-Electrical

23 The Luminaire specifications are listed here, but the luminaires are already designated in the drawings, so are the ones in the luminaire schedules in the drawings approved? (26.51.)

Specifications provide minimum performance characteristics for the luminaires. Refer to the lighting fixture schedule in design drawings for the Basis of Design fixtures.

JM Electric 9/19/2019

SETTY-Electrical

24 Do you want visible nameplates attached to all lights, or can this be waived? (26.51.2.9.1)

Provide nameplate details for all equipment per specifications. JM Electric 9/19/2019

Amendment No. 8

RFI Responses

25 Is there a particular brand of American made generator that you want? Drawings were designed around

Kohler as the Basis of Design, however, all American brands may submit as long as they meet the generator performance characteristics.

JM Electric 9/19/2019

SETTY-Electrical

26 Is the greenhouse manufacturer providing greenhouse computer system, the weather station, sensors for humidity, temperature, damper motors etc.? Basically what are they providing, and what is the electrical contractor providing (26.05.3.2 +3.3)?

yes Greenhouse manufacture to provide all greenhouse equipment motors and controls. Electrical contractor to provide all load panels and wiring to motor supplied by manufacture and installed by greenhouse contractor.

JM Electric 9/19/2019

SETTY-Electrical /

Greenhouse Consult

27 On the walkways between East and West wings, what is the Light type?

See EL01 & EL02 (and see note referencing A302 & A406)

The light fixtures along the walkways are Type X2 JM Electric 9/19/2019

SETTY-Electrical

28 In room 129 on EL01 - 3 light with designation – should it be type "A"? Yes, they are the typical Type A light fixtures JM Electric 9/19/2019

SETTY-Electrical

29 No lights in dark room 149B & walk in cold rooms 126D & 240, are they preinstalled?

In dark room allow for a 2x4 LED troffer ceiling light with dimmer switch adjacent to door and an exterior message sign similar or equal to:

https://www.hubbell.com/dual-lite/en/Products/Lighting-

Controls/Emergency-Exit-

Lighting/Exit-Message-

Signs/Obsidian/p/2517929#prod-resources-section with "ROOM IN

USE" option. Lights in cold rooms are preinstalled

JM Electric 9/19/2019

SETTY-Electrical

30 On HE-300, in room with refrigerators, there is an un-designated light – type, is it type E?

Yes, Type E JM Electric 9/19/2019

SETTY-Electrical

31 Can there be onsite storage of lights and devices (of both phases) if purchased at beginning of job to maintain pricing - and can payment for them be provided at that time?

Pre-purchasing and storage of materials will be addressed post award.

Steve Stolte

Amendment No. 8

RFI Responses

32 Fixture counts on E401, E402 & E403

COMcheck - discrepancies:

I counted F as 33+29=62 not 31+37=68

I counted R as 12+9=21 not 21+16=37

I counted X2 as 8 not 2+1+1=4

Light fixtures in certain applications, per code, are exempt from Lighting Power Density calculations. The COMcheck report is a summary of the energy usage for only the fixtures required to be included in the analysis and should never be relied upon to estimate the total quantity of fixtures required in a facility. Contractor is responsible to provide all light fixtures required per contract documents.

JM Electric 9/19/2019

SETTY-Electrical

33 Fixture counts on HE100

COMcheck- discrepancies:

I counted D1as 3 not 0

I counted F as 14 not 16

I counted G2 as 15 not 0

Please confirm, or should I disregard COMcheck’s numbers?

Light fixtures in certain applications, per code, are exempt from Lighting Power Density calculations. The COMcheck report is a summary of the energy usage for only the fixtures required to be included in the analysis and should never be relied upon to estimate the total quantity of fixtures required in a facility. Contractor is responsible to provide all light fixtures required per contract documents.

JM Electric 9/19/2019

SETTY-Electrical

34 On page GE404, there are two lights in electrical room that are designated K2, but are not listed in that luminaire schedule; are these the same 'K2' as designated on page HE100?

Yes, same as K2 on HE100. Type

K2 will be added to the lighting fixture schedule on drawing GE100 as well.

JM Electric 9/19/2019

SETTY-Electrical

35 E001 note 26 – Having separate switches may not work with current

Lutron design, can it be disregarded?

Yes, the note can be disregarded.

Provide switches per floor plan drawings.

JM Electric 9/19/2019

SETTY-Electrical

36 ES02-(1+3) – What is the pole height for type AA site lights? Provide with 12' pole JM Electric 9/19/2019 SETTY-Electrical

37 EL01 – Are the type V lights to have battery backup? No, connect to the generator backed up circuit indicated on drawing EP01

Amendment No. 8

RFI Responses

38 E401 – Is there a designation for the surface raceway in lab rooms? No specific designation, raceway to meet specification as noted under section 26 20 00 2.3.1 JM Electric 9/19/2019

SETTY-Electrical

39 EP01 – note 32 – Please clarify which outlets the emergency off pushbuttons control.

All the normal power circuits outlets within the lab.

JM Electric 9/19/2019

SETTY-Electrical

40 EGH-300 – Are the EM lights here to have internal battery backup? Yes, All the EM lights to have internal back-up (Minium 90 minutes). Refer to note #4 in

Lighting fixture schedule on

Drawing EGH-601

JM Electric 9/19/2019

SETTY-Electrical

41 MGH-601 – Is the greenhouse manufacturer supplying the cooling venting and humidity controls, and supplying the motors for the greenhouse venting system etc. & other motors elsewhere?

Yes same as Item #26 The manufacture to supply all controls.

Don’t under stand motors else where portion

JM Electric 9/19/2019

Greenhouse Consulting

42 EGH-601 – Note 5 - What is the primary voltage feeding the transformer?

Electrical service is fed from the adjacent Hartnell College Campus.

Primary voltage is 12KV.

JM Electric 9/19/2019

SETTY-Electrical

43 GE-400 – Are the ORC panels provided by the greenhouse manufacturer?

Yes I would imagine this is the computer control JM Electric 9/19/2019

SETTY-Electrical /

Greenhouse Consult

44 GE-801 – Who is providing the MCC cabinets, the greenhouse manufacturer?

Electrical contractor to provide all electrical distribution equipment and associated infrastructure.

JM Electric 9/19/2019

SETTY-Electrical /

Greenhouse Consult

45 HE-400 – What are the solar collectors & equipment? The space is allocated for future solar collector equipment and is not part of the current contract.

JM Electric 9/19/2019

SETTY-Electrical

46 HE-400 – What are the DDC controllers? Direct digital controls for HVAC equipment operation and maintainence.

JM Electric 9/19/2019

SETTY-Electrical

47 HE-400 – Note 1 - What is the auxiliary contact? Relay contact control wiring for

DDC controls.

JM Electric 9/19/2019

SETTY-Electrical

48 HE-400 – Note 5 – What is the electrical gutter to be used for? Provide empty pull box with four

(4) 1 1/2" sleeves for future connections as per contract documents.

Amendment No. 8

RFI Responses

49 Are you planning to include EV charging stations for this project?

If so, we would like to send a proposal based on your site plans. Our statement of qualifications is attached.

We have included language in our standard Solar ARS RFP to require that there be empty conduits and boxes for future EV charging stations under solar carport structures. We don’t have carport structures at Salinas. And an ESPC can’t be used to build “mobility” energy conservation measures.

VERDEK 9/24/2019

We have included language in our standard

Solar ARS RFP to require that there be empty conduits and boxes for future EV charging stations under solar carport structures. We don’t have carport structures at Salinas. And an ESPC can’t be used to build “mobility” energy conservation measures.

Sandy Morgan

Div 00

50 1. We respectfully request that the government extend the current

RFI deadline, September 27, 2019, an additional 2-weeks.

Can not extend

Mortenson 9/24/2019

Can not extend Steve Stolte

51 2. FAR 52.225-9 "Buy American - Construction Materials" was provided in the solicitation. This version of the BAA FAR clause excludes trade agreement act countries as origins for construction materials.

Please confirm that FAR 52.225-11 "Buy American - Construction

Materials Under Trade Agreements" should be applicable in lieu of

52.225-9.

Substitute FAR 52.225-11 for FAR

52.225-9

Mortenson 9/24/2019

Steve Stolte

52 3. What is the construction cost limitation for the project? The Government's cost limitation is not provided as it could adversely effect contractor pricing.

Mortenson 9/24/2019

Steve Stolte

53 4. We request that an additional site visit be scheduled to allow for trade partner investigation of the site and existing buildings.

Additional site visits can not be scheduled. Mortenson 9/24/2019

Amendment No. 8

RFI Responses

54 5. Solicitation Section B.2 - Notes to Offerors states "A detailed cost breakdown shall be included with the proposal in Volume One….. If negotiations are held, the Offeror's detailed cost breakdown will be used by the Government." Solicitation page 77 under Factor 5 - Price states "If there is only one responsible Offeror and the Government is unable to determine price reasonableness through competition the

Offeror's detailed cost breakdown will be used to determine if the prices are fair and reasonable." Since subcontractor pricing is received up until minutes before the proposal is due, it is not practicable for

Offerors to provide such a breakdown with their proposals on the proposal due date. Please confirm that submission of a detailed cost breakdown will only be required at a date after the initial proposal submission and only if the Government is unable to determine price reasonableness through competition.

The"Note to Offerors" referenced in section B.2 should be reworded to "- A detailed cost breakdown should be maintained and provided upon Government request. The breakdown shall include profit and overhead and contain documentation on subcontractor pricing."

Mortenson 9/24/2019

Steve Stolte

Div 01 Mortenson 9/24/2019

55 1. Specification section 01 30 00 paragraph 1.5 requires the contractor to provide progress photos, however 01 14 00 paragraph

1.3.C.3 states "No photography of ARS premises is allowed without written permission of the Contracting Officer." Will permission be granted to all project management personnel?

The Contracting Officer will authorize progress photography for the entire construction area of the facility with no restrictions.

Mortenson 9/24/2019

Steve Stolte

56 2. 01 30 00 1.7.2 states "For routine projects where the superintendent is permitted to also serve as the Quality Control (QC)

Manager as established in Section 01 45 00.00 40 QUALITY CONTROL, the superintendent must have qualifications in accordance with that section." Please confirm this statement does not apply and that the QC

Manager must have no other duties.

The Superintendent will not serve as the QC Manager; however, the

QC Manager could also serve as the Safety Manager. Mortenson 9/24/2019

Steve Stolte

57 3. Page 38 of the solicitation states "Contractor shall provide continuous monitoring for noise, dust, chemical vapor generation, volatile organic compounds, and vibration. At no time shall noise exposure to any ARS staff exceed 75 dB. Contractor shall provide to the

Contracting Officer a written weekly update of the all test results and also for proposed work for the subsequent two weeks (a two week

“look-ahead”) involving any construction activity that will produce loud noises, heavy vibrations, strong smells, or significant dust inside ARS staff occupied space." This appears to be a requirement for renovation work, please confirm this monitoring is not applicable to the project.

Continuous monitoring is not applicable. Although this prokect is more applicable to renovation interior work, efforts should be made to keep nuisance elements

(dust, noice, etc) to levels compliant with local/ state/

Federal standards for major construction in an urban populated area.

Mortenson 9/24/2019

Amendment No. 8

RFI Responses

58 4. Solicitation Section H.12 Key Personnel paragraph (a) lists the following positions; Project Manager, Quality Control Manager, Commissioning Representative, and Superintendent/Site Safety and

Health Manager. Specification Section 01 35 26 paragraph 1.7.1.2 states that the Quality Control Manager can be the SSHO on this project. Section 01 45 00.00 10 paragraph 3.4.2 states that the CQC

System Manager is assigned no other duties. Please confirm:

As stated in RFI #56, the QC manager could perform Safety manager duties, at about a 50/50 or 60/40 split.

Mortenson 9/24/2019

Steve Stolte

59 a. The Contractor's SSHO must be a full time position with no other duties assigned.

See 58 Mortenson 9/24/2019

Steve Stolte

60 b. The Contractor's Quality Control Manager must be a full time position with no other duties assigned

See 58 Mortenson 9/24/2019

Steve Stolte

61 5. Paragraph H.2 of the solicitation states The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies and that the Contractor will be charged at prevailing rates. Please provide the prevailing rates

Contractors will pay for utility usage during construction for this project.

Contractor trailers should be metered and expect standard rates.

Mortenson 9/24/2019

Steve Stolte

62 6. Solicitation Section H.12 lists a Commissioning Representative as one of the Key Personnel to be assigned to the project. Please provide any minimum requirements (education level, etc) for this person.

See Section 01 91 00.15 for the lead commissioning firm hired by the GC as a 1st tier subcontractor Mortenson 9/24/2019

Steve Stolte

63 7. Does the Commissioning Representative need to be an employee of the Prime Contractor, or can they be an employee of the Contractor's

Commissioning firm?

Shall be an employee of the independent commissioning firm hired by the General Contractor.

Mortenson 9/24/2019

Steve Stolte

64 8. Is the Commissioning Representative position a full time position with no other duties?

It should be a full time position.

Duties would be spelled out in their job description provided by the commissioning firm hired by the GC.

Mortenson 9/24/2019

Steve Stolte

65 9. Specification Section 01 91 00.15 references a Commissioning

Team, and requires a commissioning representative for each subcontractor associated with the systems to be commissioned. Can a single person cover more than one area provided that the single person is qualified to oversee the commissioning of the systems?

Yes, subject to qualifications approval by the Contracting

Officer

SETTY

Amendment No. 8

RFI Responses

66 10. Drawing A002-2 shows the north bridge between the east and west wing of the lab as alternate 2002. This alternate is not on the bid schedule. Please advise if the bridge should be base bid or if a new bid form will be provided with this listed as an alternate.

The bridge should be in the base bid.

Mortenson 9/24/2019

SETTY

67 11. Drawing A002-2 - Phase One Site Plan shows the east parking lot and east entrance as part of Phase 1. The sequence of work in Spec

Section 01 11 00 lists that work as part of Phase 2. Please confirm that the east parking lot and east entrance are to be included in Phase 2 work.

The east parking lot and east entrance are to be included in

Phase 2 work as indicated on drawing A002-3

Mortenson 9/24/2019

SETTY

68 12. Note 7 on Sheet S103 alludes to the roof screen wall being an alternate. Please confirm that the screen wall should be included in the base bid.

Screen wall to be included in base bid. Mortenson 9/24/2019

SETTY

69 13. Details for Generator Enclosure on Sheet A420 are all marked

"NOT USED". Is the generator enclosure required?

Generator enclosure is provided by generator manufacturer as provided for in Specification section 26 32 15.00 10

Mortenson 9/24/2019

SETTY

70 14. Sheet A001 includes a note calling for a bicycle storage enclosure.

No details were found for this enclosure. Is this a requirement?

The enclosure is a specified product found in Section 12 93 00. Mortenson 9/24/2019

HDR

71 15. Sheet AD001, where are microplots going to be relocated to?

Outside of the limits of construction?

Microplots will be relocated outside the limits of construction Mortenson 9/24/2019

SETTY

72 16. Headhouse structural plans were not provided. Please provide guidance to price the headhouse structure.

See Drawings GS-100, GS-106, HS-

100, & HS-300

Mortenson 9/24/2019

SETTY

73 17. The swing space foundation plans were not provided. Please provide guidance to price the foundations for the swing space.

See Drawing SGH-101

Mortenson 9/24/2019

SETTY

74 18. Solicitation section H.30. Please confirm County/Local planning and development permits are not required to be obtained for this project.

If required, this would be a reemburseable expense. Mortenson 9/24/2019

Steve Stolte/SETTY

75 19. Solicitation section H.30. Please confirm that a building permit(s) is not required for this project.

If required, this would be a reemburseable expense.

Mortenson 9/24/2019

Steve Stolte/SETTY

76 20. Section 01 11 00 - 1.2.2.1 lists demolition of buildings 64A, 65A, 69, 68, and 88 in both Phase 1 work and Phase 2 work. Drawing AD001 delineates B68, 69, & 82 in Phase 1 and 64A, 65A, 87, 88 in phase 2.

Please clarify during which phase these buildings should be demolished.

Demolition shall be as provided for on Drawing AD001

Amendment No. 8

RFI Responses

77 21. Section 01 11 00 - 1.2.2.1 - b Note 1 Reads "Demolition of Building

17 to Lab Buildings (NIC)". Please confirm that demolition of Building 17 is in the Contractor's scope, and this note is referring to Relocation of

Building 17 occupants to Lab Buildings.

Demolition of Building 17 is in the contractor's scope as part of

Phase 2. Note 1 should read, "Relocation of Building 17 occupants and equipement to Lab

Buildings (N.I.C.)"

Mortenson 9/24/2019

HDR

78 22. Please confirm that relocation of the Microplots will occur before the Contractor mobilizes on-site, as this area will be needed for the

Contractor's staging area.

Microplots will be relocated prior to contractor mobilization. Mortenson 9/24/2019

Steve Stolte/SETTY

Div 02 Mortenson 9/24/2019

79 1. Please provide existing building drawings for all buildings to be demolished.

Drawings of buildings 3, 18, 17, 18

& 62 are available for review at the site and copies will be provided to the successful bidder upon award. Greenhouse drawings 64, 65, 68, & 69, may or may not be available. If available, they will be included for review, and copies provided after award

Mortenson 9/24/2019

HDR

80 2. Solicitation Section C.4 references a Government provided hazardous materials report which Offerors are to use to prepare their bids. The specification includes a report that lists in general terms what materials are present, but no quantities are provided. Please provide the referenced testing and sampling report listing all hazardous materials to be abated, including quantities, to be used as the basis of bidding.

The General Contractor shall conduct lead and asbestos surveys prior to demolition of older structures on the site and comply with Title 40 code of Federal

Regulations Part 61 and the applicable provisions of the Air

District's Rule 424

Mortenson 9/24/2019

Steve Stolte

81 3. Sheet C3.0 includes a note that reads "Fence (Match existing)" in reference to the fencing around the swing space greenhouses. Please provide a specification for the fencing to be matched.

Contractor to visit site and price new fencing on characteristics of existing fencing.

Mortenson 9/24/2019

Greening Urban

Div 06 Mortenson 9/24/2019

82 1. Please provide elevations for the casework located in RM 126E Lab

Support. The dashed lines indicate extent locations for equipment. They are not casework elevation lines.

HDR

Amendment No. 8

RFI Responses

83 2. Interior Elevation 5/IN105 has objects in the lunch room elevation with no identification. Please provide information about these objects in the elevation.

These are Bulletin Cabinets, item

DB-1 as noted in the Finish Color

Key on sheet A606 and included in spec 10 11 00

Mortenson 9/24/2019

HDR

Div 07 Mortenson 9/24/2019

84 1. Detail 1/L402 calls out stucco finish at the exterior of the pond equipment vault. Please provide a specification for the stucco system to be used.

Specification section has been added.

Mortenson 9/24/2019

Rana Creek

85 2. Please provide a specification for the Aluminum Sunshade systems, both the large one as shown on Detail 10/A504, and the smaller ones shown on Sheet A401 (no details provided).

Specification section 10 71 13 has been added and section 09 90 00 has been revised. Details 1/A401 and 10/A504 have revised notes pertaining to the sunshade. Self adhering air barrier noted in detail

10 has been added to spec section

07 60 00.

Mortenson 9/24/2019

HDR

Div 08 Mortenson 9/24/2019

86 1. Specification 081116 paragraph 1.3 requires Structural Calculations for Deflection and Antiterrorism. What is the governing standard for antiterrorism for this project? UFC 4-010-01 was not seen referenced. If the 2018 version is applicable, the requirement for blast engineering the doors/frames can likely be waived pending the threat analysis.

There is no anti-terrorism requirement for this project.

Mortenson 9/24/2019

HDR

87 2. Specifications 08 44 00 and 08 51 13 list the requirements to submit structural and thermal calcs for the curtainwall. Since antiterrorism was listed in 081116, shall the curtainwalls and windows also be designed to antiterrorism standards? If so, what is the governing standard and version (e.g. UFC 4-010-01, 2018).

There is no anti-terrorism requirement for this project.

Mortenson 9/24/2019

HDR

88 3. The door schedule lists "Frame Type 7" for multiple doors. Please provide an elevation and sections of this frame type. Change "Frame Type 7" as follows and as revised on sheet A605:

1. Doors 133B and S202 to have

Type 1 frame (HM)

2. Doors 250A, 250C and 253C to have Type 4 frame (cased opening)

Amendment No. 8

RFI Responses

89 4. Greenhouse drawing GS-120 includes a note for glazing to see schedule on GS-110. There is not a schedule of glazing on GS-110.

Please provide this schedule.

Drawing GS-110 has been revised to include the glazing schedule.

Mortenson 9/24/2019

Greenhouse Consult

90 5. Detail 1/A714 Indicates alternates #1004, #1007, and #2003;

however, these are not indicated on the Bid Form. Please clarify if these alternates are applicable.

These alternates are part of the base bid and not applicable. Mortenson 9/24/2019

SETTY

Div 09 Mortenson 9/24/2019

91 1. Sheet A102 calls out 8/A404 as enlarged plan for Stair 1, 10/A404 as enlarged plan for Stair 3, and 5/A404 as enlarged plan for Stair 4.

G001 states A404 as "not used", please provide enlarged plans for the previously listed stairs.

Reference new sheet A404 which includes enlarged stair plans for

Stair 1, Level 1 and Level 2 (details

7 and 8) and Stair 3, Level 1 and

Level 2 (details 9 and 10). The enlarged plan for Stair 4 is located on sheet A709, detail 5.

Mortenson 9/24/2019

HDR

92 2. Detail 13/HA-400 Typ. Restroom & Shower calls out ceramic tile as a wall finish for rooms HH.13 & HH.15. Please provide a specification section for the tile in the Greenhouse Set.

Reference SECTION 09 30 10 -

CERAMIC, QUARRY, AND GLASS

TILING of the Laboratory

Specifications.

Mortenson 9/24/2019

SETTY

93 3. Sheet HA-500 Room Finish Schedule "Remarks" call to refer to spec

09650. No spec is listed in the Greenhouse spec set.

Reference SECTION 09 65 00

RESILIESNT FLOORING of the

Laboratory Specifications.

Mortenson 9/24/2019

SETTY

Div 10 Mortenson 9/24/2019

94 1. HA-105 and multiple other sheets refer to wall bumpers, please provide a specification. Detail 1/HA305 provides guidance regarding the wall bumpers.

Mortenson 9/24/2019

SETTY

Div 12 Mortenson 9/24/2019

95 1. 12 31 00 references BSL-3 in the sealants section, but none of the other parts of the RFP indicate any biosafety level requirements. Is BSL-

3 (or any other BSL level) required at any location(s)?

This project was designed for BSL-

1 labs. BSL-3 is not required in any location.

Mortenson 9/24/2019

HDR

96 2. Please provide elevation 6W/AP103.

Elevation 6W/AP103 is the same as Elevation 6/AP103. The note to the bottom left of elevation 6 indicates that the casework in elevation 6 is to be wood in 6W.

Mortenson 9/24/2019

HDR

97 3. Please provide a Lab Casework specification section for the

Greenhouse Set.

Referenc e Section 10 56 13 STEEL

SHELVING

Mortenson 9/24/2019

Div 13 Mortenson 9/24/2019

Amendment No. 8

RFI Responses

98 1. Spec Section 13 34 13 in the Labs Specs document lists Conley's

Greenhouse Manufacturing & Sales, or approved equal as the basis of design manufacturer of the greenhouses & insect house, and requests that others submit a request for substitution in accordance with

Division 01. Spec Section 13 34 20 in the Greenhouse Specs document lists six other manufacturers as acceptable, none of which are Conley's.

Please confirm Conley's is an acceptable manufacturer for the greenhouses in Phase 2, and confirm that the 6 manufacturers listed in

Phase 2 specs are acceptable for the greenhouses in Phase 1.

Submit request for substitution in accordance with Division 01.

Mortenson 9/24/2019

HDR

99 2. Drawing GS-100 has a note that states "Prior to starting construction, contractor shall provide engineer of record with complete shop drawings of all prefabricated buildings with engineering calculations and reactions signed and sealed by registered structural engineer to validate the foundation design show here. These drawings shall serve as the base drawings for bidding only, not for construction."

Specification 13 34 20 does not list a requirement for delegated design.

Please confirm the structural design of the greenhouses is to be a delegated design feature, and advise on what components of the greenhouse shall be designed by the contractor (e.g. foundations, structure, glazing, etc).

Foundations are already designed, but they are based on assumptions that may be different from what the prefab metal building assumes/requires. The intent of the note is for the

Designer to revise the foundation design (as needed) in response to completed shopdrawings.

Mortenson 9/24/2019

Greenhouse Consult

100 3. In the Greenhouse there are two existing cold rooms to locate to that location. Please confirm who is relocating the cold rooms. If it is us, please provide a spec.

The two cold rooms, A & B, located to the east of the

Headhouse are currently located to the south of building 17; A is 12' x 8' and B is 14" x 10'. Contractor is to survey existing utility requirements and provide appropriate utility hookups.

Mortenson 9/24/2019

SETTY

Div 22-23 Mortenson 9/24/2019

101 1. 23 31 13.00 40 lists design analysis and calculations as a required submittal. Please confirm this is not applicable for this scope of work.

This is not applicable for this scope of work. Mortenson 9/24/2019

SETTY Mech.

Received 2019 09 27 102 The Solicitation F.2 states to “complete the entire work ready for use not later than 1440 calendar days after receipt of Notice to Proceed for design on the base contract”. Please confirm the contractor is not required to furnish the design.

The contractor is not required to furnish the design.

Walsh 9/27/2019

Amendment No. 8

RFI Responses

102 The Solicitation B.2 Notes to Offerors states that a detailed cost breakdown is to be provided. Please provide a format for this breakdown. Not providing a similar format for all bidders to use may result in incomparable pricing information.

Correct, the design is provided.

Paragraph F.2 should read "The

Contractor shall be required to (a) commence work under this contract within 15 calendar days after the date the Contractor receives the Notice to Proceed, (b) prosecute the work diligently, and

(c) complete the entire work ready for use not later than 1440 calendar days after receipt of

Notice to

Proceed. Optional Items, if awarded, shall require no additional time to the contract.

Walsh 9/27/2019

Steve Stolte

104 The Solicitation D.1 states that Contractors are to provide a program to view the contractor’s submission if the Government does not have the program needed to view the files. Can the Government computers read

.PDF files?

Adobe PDF files are acceptable.

Walsh 9/27/2019

Steve Stolte

105 The SF 1442 states that offers are due by 1300 hours local time. Please confirm that this is 1300 Eastern time.

Correct, 1300 Eatern Time Walsh 9/27/2019

Steve Stolte

106 The Solicitation H.2 states Contractor is to pay for use of utilities at prevailing rates charged to the Government or reasonable rates determined by the Contracting Officer. Will the Government please provide the prevailing rates or determined reasonable rates to assist in determining costs in the preparation of the Contractors bid?

See answer provided in RFI #61

Walsh 9/27/2019

Steve Stolte

107 The RFI cutoff date is currently 27 September 2019. Will the

Government consider extending the RFI cutoff date till 25 October 2019 in order to allow Contractors additional time to obtain any necessary clarifications on technical details of the project?

The RFI cutoff date can not be extended. We will attempt to answer all RFIs so please submit any that you may have, we just can not guarantee aftering them after the cutoff

Walsh 9/27/2019

Steve Stolte

108 01 11 00 Summary of work outlines Phase One and Phase Two for the project. Are the items listed under each Phase (One or Two) required to be completed in any sequential order?

If the sequence of items under each phase is to be modified, revised sequence shall require approval of the user.

Amendment No. 8

RFI Responses

109 01 11 00 requires buildings 64A, 65A, and 88 to be demolished in Phase

One. Architectural drawings indicate these buildings are to be demolished in Phase Two. Please clarify. See response to RFI 76

Walsh 9/27/2019

HDR

110 01 11 00 Phase Two states “Demolition of Building 17 to Lab Buildings

(N.I.C.)” AND also states “Demolish 3, 17, 18 & 19”. Please clarify whether demolition of building 17 is required of the contract. Demolition of Building 17 is required in Phase II.

Walsh 9/27/2019

HDR

111 01 11 00 Specifications state to “relocate sheds 75 and 77” drawings indicate relocation of sheds 76 and 77. Please clarify.

Follow the drawings, which indicate sheds 76 & 77 to be relocated as indicated on A002-3 Walsh 9/27/2019

SETTY

112 On the plan sheet AD001 "Existing Site Plan (Demo)", Building 32 is not shaded as a building to remain, but is not indicated for demolition on specifications (01 11 00 p.2) or plan sheets under Phase 1 or 2. Please advise.

Building 32 remains and shall not be demolished.

Walsh 9/27/2019

SETTY

113 Specifications require demolition of Building 29 (01 11 00 p.2). This building is not shown on the demolition drawings. Please advise.

There is no building 29 to demolish. Bldg. 63 (previously known as Bldg 29) shall be demolished as late in the schedule as possible without impacting schedule.

Walsh 9/27/2019

SETTY

114 In the phasing specifications, "Create staging area" is listed twice (01 11

00 p.2). Please provide clarification.

The references to staging areas are associated with the phase I staging area shown on A002-2 and the Phase II staging area shown on

A002-3

Walsh 9/27/2019

SETTY

115 Building 76 is listed as a building to demolish in the phasing specifications (01 11 00 p.2), and a shed to relocate on plan sheet

AD001. Please provide clarification.

Bldg 76 is to be relocated to a location as indicated on Drawing

A001.

Amendment No. 8

RFI Responses

116 There may be unknowns identified by the Engineer, that will impact the design and subsequent installation of the electrical system. We cannot hire them to start until after the bid is awarded, so this creates the possibility of an extra unknown expense, that could be significant.

So, I guess I need to RFI on this, and ask if USDA will pay for additional expense should that happen; do you agree?

We carry a contingency to cover change orders from unforeseen conditions and scenarios like the one you are describing. Our AE did their best to get the design right the first time and we should be able to get the RFIs answered with enough time for accurate bidding. Change orders happen on every project like this so it would be relatively routine to make some adjustments as it progresses. We are just using this one solicitation for the whole project, we aren’t separating into electrical or civil or anything like that.

JM Electric

9/27/2019

Steve Stolte

Div 00

117 1. Please confirm that the Government will provide responses to RFIs

2 weeks prior to the proposal deadline and will provide 1 week for follow-up RFIs for any additional clarification required after receiving the RFI responses.

ARS is making every effort to ensure adequate response time to our RFI responses.

Steve Stolte

118 2. Page 71 of 80, L.11. Proposal Submission

Requirements/Instructions, paragraph (b.):This section provides the address for delivery of proposals, however does not specify whether offerors may hand deliver proposals. If hand delivery by offerors is acceptable, please provide any general instructions that may be necessary (i.e. facility access procedures)

Contractors wishing to hand deliver their proposals shall notify the Contracting Officer by calling

301-504-1187 from the main lobby of the GWCC building and the CO or representative will come down to receive them.

Steve Stolte

119 3. Page 72 of 80, L.11. Proposal Submission

Requirements/Instructions (c): To allow for the maximum amount of time to receive subcontractor pricing, please confirm that the Price

(Volume 1) does not need to be included on the electronic copy (Flash

Drive) of the proposal. If desired, an electronic copy of Volume 6 may be furnished via next-day delivery on the day after the proposal deadline.

The Price schedule can be provided to the Contracting

Officer seperately via email.

Proposals received without a hard copy of the price may not be considered complete.

Amendment No. 8

RFI Responses

121 4. Page 72 of 80, L.11. Proposal Submission

Requirements/Instructions (c): This section states "The Offeror shall elect to submit SF330 forms for design firm qualifications subject to the same presentation format and content requirements of the

Solicitation." Please confirm SF330 forms are not applicable to this proposal, as the solicitation is fully designed.

Correct, this was included in error.

SF 330s are not applicable.

Steve Stolte

Div 01

122 1. 01 57 19: The Responsible Party required to submit a NOI must be the Property Owner in the State of California; is the USDA planning on submitting the Notice of Intent and Notice of Termination submittals for this Project? Also, because the project shall be completed in two phases; please confirm a separate NOI and NOT submittal will be required for each phase of the Project.

This is a single project requiring a single NOI and NOT submittal even though it will be completed in phases. The NOIs will be handled by the GC as an agent of the

USDA.

Steve Stolte

123 2. 01 57 19: Based on the current and historical use of the Property, there is likely to be hazardous materials stored on-Site. Will the USDA be cleaning out all impacted buildings of chemicals and hazardous materials (other than asbestos, lead and other hazardous building materials) prior to demolition? Also, the USDA will need to sign-off on all required manifests and be determined the generator for any waste generated during the Project?

Yes to both Steve Stolte

124 3. 01 57 19: Are any known environmental risks located within the

Project site? Does the USDA have any documents (Phase I/II, etc.)

identifying historic releases or tanks on-Site and has any on-Site sampling or cleanup been completed?

There are no known evirnonmental risks that ARS is aware of. See Attached EA and EA

& ESA for the Hartnell parcel.

Steve Stolte

125 4. 01 57 19: Spill Prevention, Control and Countermeasure Plan: Are there any existing tanks or additional tanks (including transformers, ASTs, or any container 55 gallons or greater) needed for work on-Site that will remain within the project limits during construction?

None to the best of our information.

Amendment No. 8

RFI Responses

126 5. 01 57 19: Endangered Species/Sensitive Habitats: Section 7 of the

Endangered Species Act requires Federal agencies to "request of the

Secretary information whether any species which is listed or proposed to be listed may be present in the area of such proposed action" for any project that is conducted, permitted, funded, or licensed by any Federal agency. A letter from the local office and a species list which fulfills this requirement can only be obtained by requesting an official species list from either the Regulatory Review section in IPaC or from the local field office directly. Please confirm this has been completed and advise if any species or habitats are anticipated to be a consideration for this project.

See attached Final Environmental

Assessment, dated November 2, SETTY

127 6. Specification section 01 33 29 for the Lab states "Refer to

Attachment 1, HPSB Checklist at the end of this specification

HPSB Checklist provided as part of

Amendment

HDR

128 Section" and that we are to "Provide all work required to incorporate the applicable HPSB Guiding Principles Requirements indicated on the

HPSB Checklist". Please provide this HPSB Checklist.

See RFI 127

HDR

129 Specification section 01 45 35 for the lab states "Perform Special

Inspections in accordance with the Statement of Special Inspections, Schedule of Special Inspections and Chapter 17 of ICC CBC. The

Statement of Special Inspections and Schedule of Special Inspections are included as an attachment to this specification." Please provide the

Statement of Special Inspections and Schedule of Special Inspections -they are currently not included in the specifications.

Contractor to follow Chapter 17 of the ICC CBC

SETTY

130 7. Section 01 11 00 – 1.2.2.1 states "The construction of this project shall be divided into two phases; phase one and phase two; built in that sequence. Each construction phase will be executed independently, as a stand-alone project, and when completed, shall be a fully functional building without the construction of the next phase." Please clarify if there is a transition or owner move out/move in duration required between phase 1 and phase 2 or are we allowed to immediately start phase 2 after completing phase 1.

While there may be select portions of Phase 2 that can start immediately, the USDA will require one week to transition into the completed structures of

Phase 1.

SETTY

131 8. 01 11 00, paragraph 1.2.2.1. Please provide if there is a transition duration required between the establishment of the swing spaces and the demolition of the existing greenhouses.

The USDA will require no more than one week to affect the transition.

Div 05

Amendment No. 8

RFI Responses

132 1. Specification 05 05 23.16 states "Fabricate work in an AISC Certified

Fabrication Plant, Category Std. Work must be erected by an AISC

Certified Erector, Category ASCE." Please confirm the requirement of an

AISC-certified erector may be waived as long as AISC practices are followed by the erector.

Non concur. Fabricator and erector shall conform with specification requirements.

HDR

Div 07

133 1. Please confirm that Specification Section 07 42 13 2.2.1 Aluminum

Sheet applies to the Shadow Box detail on Sheet A512 or if 2.2.2 Steel

Sheet governs.

Aluminum sheets are to be used where the detail notes indicate that material.

HDR

Div 09

134 1. Sheet HA-500 Room Finish Schedule calls out GB (Gypsum Board) &

CB (Cement Board) as substrates. No specification section is included for these in the Greenhouse spec set.

Reference 09 29 00 of the

Laboratory Specifications

SETTY

Div 10

135 1. Please provide an enlarged toilet floor plan for room 105A in the lab and rooms HH.13 and HH.15 in the Headhouse

See Drawing HA-105 for enlarged plans of HH.13 & HH.15. Enlarge plan for 105A added to drawing

A411. HDR/SETTY

136 2. Please provide a spec for toilet accessories for the greenhouse Toiler accessories to be similar to those used in Phase 1. See sheet

A411 & Specification Section 10 28

13. SETTY

137 3. Please provide locations for DB-1 in lunchroom See Resonse to RFI No. 83 HDR/SETTY

Div 13

138 1. Please confirm who is relocating the cold rooms in HH.10 in the

Headhouse. If it is by the general contractor, please provide a spec.

The Scope…