12-E3. FRONTIER UWS 449033-1 RANCH RD SIDEWALK 3182025.pdf

PDF 228 KB Posted

Attached to
RANCH ROAD SIDEWALK FROM US 19 TO PONDEROSA AVENUE
Solicitation number
IFB-KM-26-058
Issued by
Pasco County, Florida

About this file

This is a Florida Department of Transportation (FDOT) Utility Work Schedule for Frontier Communications, the utility agency/owner (UAO), related to the Ranch Road Sidewalk construction project in Pasco County. The document establishes the terms and timeline for Frontier Communications to relocate and adjust its telecommunications utilities to accommodate FDOT's sidewalk construction project along Ranch Road from US 19 to Ponderosa Avenue. The utility work encompasses six distinct activities: adjusting four handholes away from the sidewalk at stations 107+10, 112+12, 126+8, and 133+17; holding and protecting a Broad Band Fiber Optic Cable (BFOC) during headwall installation between stations 135+90 and 136+20; and holding and protecting BFOC and buried telephone cable during drainage installation between stations 148+00 and 149+20. All utility work is scheduled to occur during FDOT project construction, with a total of 10 consecutive calendar days required for completion. The utility work is contingent upon the placement of sidewalk and installation of headwall and drainage infrastructure.

Frontier Communications' work must comply with the 2017 Utility Accommodation Manual and requires the utility company to obtain a utility permit prior to commencing work. All work is to be conducted during normal business hours (8 a.m. to 5 p.m., Monday through Friday, excluding holidays), with work outside these hours requiring 72 hours' advance notice. Frontier's field representative, Vince Theodosis (727-942-8326), must be notified when work occurs within two feet of Frontier facilities and serves as the primary point of contact during construction. Frontier retains access throughout the project duration to monitor and maintain its facilities to ensure service continuity. The utility work schedule was dated November 2024 and signed by Frontier's Network Engineer, Christopher Scott Hand, on March 18, 2025.

View the file

Other files

File Type Posted
17-FEDERAL PROVISIONS - CONSTRUCTION - IF NEEDED.pdf PDF
6-A. ADVERTISEMENT PAGE.pdf PDF
9-E9.4 Appendix 2 cover.pdf PDF
33-E1. PLANS.pdf3.pdf PDF
10-G3. REQUIRED CONFLICT OF INTEREST DISCLOSURE.pdf PDF
29-E9.9.1 Appendix 6.pdf PDF
7-E9.8 Appendix 5 Cover.pdf PDF
3-D. SPECIAL CONDITIONS.pdf PDF
1-E6. CHARTER No Conflict Letter 2024 08.pdf PDF
24-E9.9 D Appendix 5 SPECS.pdf PDF
27-E9.3 LAP Agreement - Executed.pdf PDF
13-G4. REQUIRED CERTIFICATION OF UNDERSTANDING.pdf PDF
28-E5. MCI No Conflict Ranch Road Sidewalk.pdf PDF
4-E7. TECO Gas No Conflict Letter 2025 01.pdf PDF
5-E9.1 Appendices Coversheet.pdf PDF
8-B. INSTRUCTIONS TO BIDDERS.pdf PDF
21-C. GENERAL CONDITIONS.pdf PDF
16-E. PROJECT SPECIFIC SPECIAL CONDITIONS-SPECIAL PROVISIONS-TECH SPECS-PERMITS-REPORTS.X.pdf PDF
15-G2. REQUIRED FLORIDA TRENCH SAFETY ACT CERTIFICATION AND DISCLOSURE STATEMENT.pdf PDF
25-E9.6 Appendix 3.pdf PDF
11-E9.2 Appendix 1 cover.pdf PDF
20-F. BID PROPOSAL-OFFEROR FORM.pdf PDF
32-E8. WREC No Conflict Ranch Road Sidewalk.pdf PDF
19-H. AGREEMENT.pdf PDF
2-E2. - SWFWMD PERMIT.pdf PDF
31-E9. ZAYO No Conflict Ranch Road Sidewalk.pdf PDF
23-I. POST AWARD DOCUMENTS.pdf PDF
22-E9.5 Appendix 2.pdf PDF
18-E9.7 Appendix 4.pdf PDF
30-E4. Pasco County Traffic No Conflict Ranch Road Sidewalk.pdf PDF
26-G5. REQUIRED DOCUMENTS FOR LAP PROJECTS - ONLY IF APPLICABLE.pdf PDF
14-G1. REQUIRED BID BOND.pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Rule 14-46.001 F.A.C

FLORIDA DEPARTMENT OF TRANSPORTATION

UTILITY WORK SCHEDULE

December 14, 2016

Pursuant to Section 337.403 F.S., the UAO and FDOT agree to the UAO’s need for relocation or adjustment to its utilities and FDOT’s need for a schedule for the UAO to effect the relocation or adjustment. This utility work schedule is based on FDOT plans dated in the project information box below. Any deviation by FDOT or its contractor from these plans, may void this utility work schedule. Upon notification by FDOT of a change to these plans, the UAO may negotiate a new utility work schedule. The UAO agrees to notify FDOT and the contractor in writing prior to starting, stopping, resuming, and completing work in accordance with this utility work schedule. The UAO shall obtain a utility permit and comply with requirements of the 2017 Utility Accommodation Manual (UAM) for all work done under this utility work schedule. The UAO is not responsible for events beyond the control of the UAO that could not be reasonably anticipated by the UAO and which could not be avoided by the UAO with exercise of due diligence at the time of the occurrence.

FDOT PROJECT INFORMATION

Financial Project ID: 449033-1-52-01 Federal Project ID:

State Road Number: County: Pasco FDOT Plans Dated: 11/2024 District Document No.:

UTILITY AGENCY/OWNER (UAO)

Utility Company: Frontier Communications UAO Project Rep: Christopher Hand Phone: 813-431-0328 E-mail: christopher.s.hand@ftr.com UAO Field Rep: Vince Theodosis Phone: 727-942-8326 E-mail: vince.theodosis@ftr.com

UTILITY SIGNATURE

I have reviewed the FDOT plans referenced above and submit this utility work schedule in compliance with UAM Section 5 and agree to be bound by the terms of this utility work schedule.

UAO Rep. Date 3 / 18 / 2025 Name Christopher Scott Hand Title Network Engineer Public Works

ENGINEER OF RECORD SIGNATURE

I attest this utility work schedule is compatible with the FDOT plans referenced above.

EOR. Date / / Name Bryan Anderson,P.E Title Engineer of Record

APPROVAL BY DISTRICT UTILITIES

This utility work schedule is complete and acceptable to FDOT.

FDOT Rep. Date / / Name Title

SECTION A: SUMMARY OF UTILITY WORK

The below days are the total numbers of days shown for all activities in Section C of this utility work schedule. The breakdown of how these days are to be incorporated into the FDOT project and the dependence of these days upon the completion of other activities by the UAO or others is shown in Section C.

Days prior to FDOT project construction: 0 Days during FDOT project construction: 10

FLORIDA DEPARTMENT OF TRANSPORTATION

Financial Project ID: 449033-1-52-01 Utility Company: Frontier Communications FDOT Plans Dated: 11/2024

SECTION B: UAO SPECIAL CONDITIONS/CONSTRAINTS

Frontier and Frontier Contractors' normal business hours are from 8am to 5pm, Monday through Friday (excluding Holidays).

Any work outside of normal business hours to be scheduled a minimum of 72 hours in advance.

Caution is to be used when excavating near or around Frontier facilities.

Frontier inspector Vince Theodosis 727-942-8326 is to be the point of contact during construction and to be notified when working within 2' of Frontier faculties.

Frontier is to have access throughout the duration of the project to monitor and maintain facilities for the ability to provide service

FLORIDA DEPARTMENT OF TRANSPORTATION

FDOT Plans Dated: 11/2024

SECTION C: UAO’s WORK ACTIVITIES

Act.

No.

Utility Facility (type, size, material, status)

From Station/ Offset

To Station/ Offset

Utility Work Activity Description

Dependent Activity TCP Phase

Consecutive Calendar Days

Prior to During Const. Const.

1 HANDHOLE 107+10,

16’LT

ADJUST HANDHOLE

AWAY FROM

SIDEWALK

PLACING OF

SIDEWALK 0 1

2 HANDHOLE 112+12,

16’LT

ADJUST HANDHOLE

AWAY FROM

SIDEWALK

PLACING OF

SIDEWALK 0 1

3 HANDHOLE 126+8,

16’LT

ADJUST HANDHOLE

AWAY FROM

SIDEWALK

PLACING OF

SIDEWALK 0 1

4 HANDHOLE 133+17,

15’LT

ADJUST HANDHOLE

AWAY FROM

SIDEWALK

PLACING OF

SIDEWALK 0 1

5 BFOC 135+90,

22’LT

136+20, 22’LT

HOLD AND

PROTECT BFOC

DURING

HEADWALL

INSTALLATION

0 3

6 BFOC AND BT 148+00,

22’LT

149+20, 22’LT

HOLD AND

PROTECT

DURING

DRAINAGE

INSTALLATION

0 3

FLORIDA DEPARTMENT OF TRANSPORTATION

FDOT Plans Dated: 11/2024

SECTION C: UAO’s WORK ACTIVITIES

Act.

No.

Utility Facility (type, size, material, status)

From Station/ Offset

To Station/ Offset

Utility Work Activity Description

Dependent Activity TCP Phase

Consecutive Calendar Days

Prior to During Const. Const.