22 April 09 New Norton Sound Regoinal Hospital
Midnight Sun Court Reporters (907) 258-7100
8 NEW NORTON SOUND REGIONAL HOSPITAL
NOME, ALASKA
9 PRE-PROPOSAL MEETING
12 Taken April 22, 2009
Commencing at 9:00 a.m.
14 Volume I - Pages 1 - 64, inclusive
16 Taken at
Alaska Native Health Consortium
17 1901 Bragaw Street
Anchorage, AK 99508
24 Reported by: Valerie Martinez
2 (Pages 2 to 5)
1 A P P E A R A N C E S 3 Indian Health Service
Division of Engineering Services - Seattle
Abram Vinikoor, Contracting Officer 5 Paul Geisert, P.E., Project Officer
Henry Hardnett, AIA, Project Architect
Indian Health Service 7 Alaska Area Native Health Service
Office of Environmental Health & Engineering - Anchorage
Dale Mossefin, P.E., Director, Health Facilities 9 Engineer
Tom Coolidge, P.E., Director, OEH&E
Norton Sound Health Corporation
Angie Barr, AIA, Kumin Associates 12 Jay Farmwald, P.E., DOWL HKM
Cliff Gray, Project Manager 14 Nome Eskimo Community 15 Denise Barengo, Executive Director
Emma Goodwin, Deputy Director 18 Taken by:
19 Valerie Martinez 21 BE IT KNOWN that the aforementioned proceedings were 22 taken at the time and place duly noted on the title page 23 before Valerie Martinez, Notary Public within and for 24 the State of Alaska.
1 P R O C E E D I N G S
2 MR. VINIKOOR: I'm Abe Vinikoor. I'm the
3 contracting officer for the Indian Health Service, the
4 Division of Engineering Services in Seattle, and I want
5 to thank you all for coming and welcome to the
6 pre-proposal conference for the new Norton Sound
7 Regional Hospital.
8 Does everyone have a copy of the agenda? I
9 can pass some out. No? And there's a sign-in sheet
10 that is going around, too. I'd appreciate it.
11 Do you have copies? Everyone good?
12 So if you could all sign that sign-in sheet.
13 We have a stenographer that's taking notes. And what we
14 plan to do is post the minutes on the FedBizOpps web
15 site. We're going to post the presentations that we do
16 as well, as well as a copy of the sign-in sheet. So
17 you'll all be on the web eventually. We'll probably do
18 that towards the end of the week.
19 What I'd like to do now is have everyone in
20 the government and Norton Sound folks introduce
21 themselves. The government is sort of huddled over here
22 and Norton Sound is sort of over there, but we do get
23 along. For some reason, we took opposite sides of the
24 room. So why don't we start with some introductions.
25 MR. MOSSEFIN: Good morning. My name is Dale
1 Mossefin. I'm with the Alaska Area Native Health
2 Service. I'm in the Office of Environmental Health &
3 Engineering. And I'm the area director of the health
4 facility engineering program.
5 MR. GEISERT: I'm Paul Geisert. I'm with the
6 Indian Health Service, Division of Engineering Services
7 in Seattle. I'm the project officer.
8 MR. FARMWALD: Jay Farmwald with DOWL HKM
9 Engineers here in Anchorage working with Norton Sound on
10 program and project management over the last couple
11 years.
12 MS. BARR: I'm Angie Barr with Kumin
13 Associates Architects here in Anchorage. We're the
14 architects of record on the project.
15 MR. VINIKOOR: Do you want to introduce
16 yourself?
17 MS. BARENGO: Good morning. I'm Denise
18 Barengo, and I'm the executive director for the Nome
19 Eskimo Community, the tribe that serves the community of
20 Nome.
21 MS. GOODWIN: And my name is Emma Goodwin.
22 I'm the deputy director for Nome Eskimo Community.
23 MR. BARNES: I'm Russ Barnes, assistant
24 project manager with Norton Sound.
25 MR. GRAY: I'm Cliff Gray. I'm the project
1 manager for Norton Sound.
2 MR. HARDNETT: Henry Hardnett. I'm an
3 architect. I'm an alternate project manager. I'm with
4 Seattle IHS, Division of Engineering Services.
5 MR. VINIKOOR: Thank you so much. Henry and
6 Paul, you know, work in our office in Seattle, and we're
7 a group of engineers and architects and contract
8 specialists specializing in construction for IHS
9 facilities. Paul Geisert will give a presentation and
10 discuss that a little more.
11 What we'd like to do is sort of go through the
12 agenda and take questions at the end, if you're okay
13 with that. If you feel you need to shout out something
14 in the middle, you know, go ahead. But if you could
15 identify yourself so the stenographer can take down your
16 name and who you work with and speak clearly so she's
17 able to write it down, we'd appreciate it.
18 So Paul, why don't you --
19 MR. GEISERT: Okay. Well, good morning.
20 Welcome to the Norton Sound Regional Hospital
21 pre-proposal meeting. I'm Paul Geisert. I'm the
22 project officer of the project, and I'll just give you a
23 brief project overview and status. Oh, by the way, 24 happy Earth Day.
25 I'd like to talk just a little bit about the
3 (Pages 6 to 9)
1 roles and responsibilities of our team consisting of the
2 Indian Health Service and representatives of the Norton
3 Sound Health Corporation.
4 First of all, I'm with the Indian Health
5 Service, Division of Engineering Services in Seattle.
6 And we are an agency within the Department of Health &
7 Human Services. We are the construction contract agency
8 for the project. Our director is Ken Harper. We're
9 divided into three branches in Seattle. We have a
10 contracting administration branch, a project management
11 branch, and a technical support branch.
12 Within the contracting administration branch
13 is the contracting officer. Abe Vinikoor is the
14 contracting officer. And just a note, only the
15 contracting officer can modify the contract, so any
16 changes to the work or contract, approval of the
17 payments, you know, settles requests for equitable
18 adjustments, makes final acceptance, et cetera.
19 I'm within the project management branch. I'm
20 the project officer, and I will be the contracting
21 officer's technical representative on the project. So I
22 work under the authority of Abe Vinikoor, the
23 contracting officer. I approve technical submittals, I
24 give directions to the contractor to clarify the
25 requirements in the contract documents, and I evaluate
1 the performance and progress for payment and acceptance.
2 In terms of what you guys are used to, I guess
3 I'm the overall project manager for the Indian Health
4 Service. As Abe pointed out earlier, Henry Hardnett --
5 where are you sitting, Henry? In the back there. He's
6 the alternate project officer or project manager.
7 Our technical support branch has licensed
8 architects and professional engineers. We've got civil, 9 mechanical, electrical engineers and architects. Their
10 role is as advisers to the contracting officer and to me
11 as the COTR and the project officer. They provide
12 support to us in the form of reviewing submittals, 13 interpreting codes, on-site monitoring, et cetera.
14 So you'll see us up there as a group
15 periodically come in. We maybe do a meeting at the
16 beginning of our visit, respective disciplines go their
17 own ways and check things out, and then at the end of
18 the visit up there we get together and have a close-out
19 meeting.
20 Just a friendly reminder, the project officer
21 and the COTR and the support staff are precluded from
22 taking action that modifies the contract. So they
23 cannot alter the performance schedule, I cannot alter
24 the performance schedule, increase the contract price, 25 or modify the contract language. That sole authority
1 rests with Abe Vinikoor, the contracting officer.
2 One of our other team members is the Alaska
3 Area Native Health Service, also within the Indian
4 Health Service and Department of HHS. Their director is
5 Christopher Mandregan. I put down here Office of
6 Financial Management because they'll be sort of in the
7 background doing some of the payment-type issues, fund
8 certification.
9 Tom Coolidge is the director of the Office of
10 Environmental Health & Engineering. Tom wasn't able to
11 be here today. But the person that you will be seeing
12 most on this project would be Dale Mossefin. Dale is
13 the director of Health Facilities Engineering.
14 And the role of OEH&E is a budgetary and
15 programmatic role. So, again, they will be kind of in
16 the background certifying funds. They are advocates
17 with the Norton Sound Health Corporation. They are
18 technical and programmatic advisers to the Division of
19 Engineering Services.
20 One of -- Dale will be a member of the project
21 leadership team. There will be one person from his
22 group that is a member of the RFP technical evaluation
23 review panel. And they will also provide periodic
24 on-site monitoring and technical support to the
25 contracting officer and the COTR.
1 Of course, the other member of the team is the
2 Norton Sound Health Corporation. Carol Piscoya is the
3 interim president and CEO. Cliff Gray is the project
4 manager. Cliff is in the back there. I think he
5 introduced himself earlier. Hey, Cliff.
6 The Norton Sound Health Corporation is the
7 landowner and they will be the facility owner and
8 operator after DES transfers the building to them at the
9 end of the project.
10 So the Norton Sound Health Corporation are
11 advisers to the Indian Health Service. And under the
12 Indian Self-Determination and Education Act, Public Law
13 93-638, Title V agreement with the IHS, they will
14 provide us certain services. They'll be furnishing
15 equipment and artwork not in this direct federal
16 contract. So basically everything but the Group 1
17 equipment they will be providing.
18 They will be providing construction contract
19 administrative services to IHS, so they'll be doing
20 things like reviewing contractor provided submittals, 21 changes to the work, time extension requests and like
22 matters, on-site inspection and surveillance.
23 There will be a resident engineer. Cliff will
24 be there as the project manager. They'll have various
25 quality assurance inspectors, special inspectors, things
4 (Pages 10 to 13)
1 like that. There will be Norton Sound Health
2 Corporation representatives on-site. And they also will
3 be providing recommendations to the government
4 contracting officer and COTR.
5 The Norton Sound Health Corporation CCA team
6 consists of in-house staff in Nome: The architect of
7 record; Angie's group, Kumin Associates in Anchorage;
8 Jay's group, DOWL HKM in Anchorage; and also Emma and
9 Denise's group in Nome, the Nome Eskimo Community.
10 Just a little pointer, Mahlum Architects also
11 was involved in the design. As far as DOWL goes, they
12 will be providing program management for the Norton
13 Sound Health Corporation; again, the resident engineer;
14 contract support; document control, probably in the form
15 of some type of FTP site might be implemented;
16 inspector -- inspection and clerical support. And those
17 are the folks that will be in the on-site trailer that's
18 provided by the contractor that's awarded.
19 Jay, I think at this point I wanted to ask if
20 you had any other input as far as DOWL's role.
21 And, Angie, I think in the next couple of
22 slides you'll give some input here.
23 MR. FARMWALD: Sure. Realizing -- what Paul
24 said, realizing that the government staff physically
25 resides in Seattle, one of our main roles, DOWL HKM's
1 roles in support of Norton Sound will be to staff the
2 on-site office with resident engineer quality assurance
3 inspectors. In Anchorage we'll have staff that can do
4 analysis of things like change proposals and make
5 recommendations to the government. But, again, the
6 government has final sign-off authority.
7 Special inspection. Special inspection
8 services provided by the owner per IBC will come from
9 Alaska Testlab through the Norton Sound to the project.
10 And I think that's all I really wanted to say
11 other than one thing that hasn't been mentioned here is
12 that Norton Sound does have some construction equipment
13 that they would hope to make available to respective
14 contractors. So we're encouraging some side discussions
15 between bidders and Norton Sound with respect to that
16 construction equipment.
17 MR. GEISERT: Thank you, Jay.
18 Again, Nome Eskimo Community will be providing
19 Indian Preference referral, training, and monitoring.
20 So Denise and Emma here, you'll be working with them.
21 MR. VINIKOOR: Do you want to give Angie a
22 shot?
23 MR. GEISERT: I was going to give you a shot
24 on the next couple of slides, if you don't mind. Go
25 ahead. If you want to speak now, Angie, go right ahead.
1 MS. BARR: It doesn't make any difference.
2 MR. GEISERT: Okay. Go ahead.
3 MS. BARR: Well, I was just going to briefly
4 outline the design team. I'm going to spotlight a few
5 of the major consultants. Of course Kumin Associates
6 Architects are the architects in Anchorage. We also
7 worked with Mahlum Architects, and they are located in
8 Seattle.
9 The civil engineering was provided by Bristol
10 Environmental. Geotechnical engineering by DOWL HKM.
11 Those are both located in Anchorage. Structural
12 engineering was by BBFM in Anchorage. Primary
13 mechanical engineering was by Notkin in Seattle.
14 Electrical, lighting technology, acoustics, those were
15 all provided by Sparling, also located in Seattle. AEI
16 was working on the commissioning plans. They're in
17 Seattle. Clevinger in Seattle was the kitchen
18 consultant. And Gordon Adams, also in Seattle, provided
19 hardware consulting.
20 A brief description of the project, which of
21 course you've all dug into the drawings and know all
22 this, I'm sure. But the project is an approximately
23 150,000-square-foot steel frame building located in the
24 arctic climate. I think we have a photograph back there
25 that illustrates that. It's three stories with an
1 additional mechanical penthouse on top of that and a
2 heated interstitial space below the first floor.
3 We've also noted on the document that there's
4 an existing gravel pad. And the steel piling foundation
5 and thermosiphons are due to the permafrost conditions
6 on the site. The pilings for the building are proper
7 and are in place.
8 The occupancy of this building. We are both
9 under the IBC and the NFPA codes for this project. And
10 it is primarily combined business and institutional
11 occupancy under the IBC. That's called business and
12 health care under NFPA. They're divided by a two-hour
13 wall.
14 The building is Type 2A or, in other words, 15 it's noncombustible one-hour construction. We do have
16 the State Fire Marshal permit, and I think that's an
17 attachment shown in the solicitation.
18 The steel, I'm sure you have noted. The steel
19 that's part of the owner-supplied materials is also
20 described in attachments to the solicitation. And
21 that's currently in the shop drawing and fabrication
22 process. And the RFIs that are being generated during
23 that review process will be made available by amendment
24 or addenda when we put an addenda out. So you will be
25 kept up to date on RFIs that are occurring in that
5 (Pages 14 to 17)
1 process. And the owner-supplied steel will be provided
2 to the contractor at the building site.
3 Medical equipment is another part of this
4 project. The medical equipment lists that are provided
5 as attachments to the solicitation describe medical
6 equipment that's going to be incorporated into the
7 project, as I'm sure you've seen. It's identified as
8 CC, contractor purchase, contractor installed; HC, 9 hospital purchase, contractor installed; HH, hospital
10 purchase, hospital installed; and HV, hospital purchase, 11 vendor installed.
12 So in addition to specific responsibilities
13 associated with the contractor purchase and contractor
14 installed as well as the hospital purchased contractor
15 installed equipment, in addition to those specific
16 responsibilities, you're going to have to coordinate as
17 required with some of the owner-related medical
18 equipment, furniture, et cetera. And those are
19 described in project management and coordination in the
20 Division 1.
21 IT. In general, the infrastructure related to
22 IT, such as cabling and conduit, is under this contract
23 with specific devices being provided by the owner.
24 There will be commissioning performed on this building
25 and so the general and subcontractors will have
1 responsibilities related to the commissioning plan.
2 And, again, those duties are outlined in the
3 specifications.
4 Just a heads up, some of the off-site
5 utilities, I'm sure you've noticed, are indicated on the
6 plans as not in contract. So this is just a reminder
7 that current utilities are not at the site at this time.
8 MR. GEISERT: Thank you, Angie.
9 MR. FARMWALD: There was mention earlier of
10 the submittal process. This will be a typical project
11 in the context that Angie's team will be doing the
12 formal submittal review process. So her whole team is
13 mobilized and will be on the project during the
14 construction phase for formal submittal review and
15 approval.
16 MR. GEISERT: Are you getting all this, 17 Valerie?
18 THE REPORTER: Yeah.
19 MR. GEISERT: Okay. So Angie Barr from Kumin
20 and Jay Farmwald from DOWL HKM.
21 The State Fire Marshal's office also plays a
22 role. They're the authority having jurisdiction for
23 fire code issues. Other code issues not in the
24 jurisdiction of the State Fire Mashal's office will be
25 resolved by the City of Nome and/or the Indian Health
1 Service, Division of Engineering Services in Seattle.
2 As Angie pointed out, there are some things
3 that are excluded from this direct federal contract that
4 will be contracted separately by DES. One will be a
5 commissioning agent. The other is with the Norton Sound
6 Joint Utility System for off-site utilities. And then
7 under the Public Law 93-638 contract with Norton Sound
8 between Norton Sound and the Indian Health Service, they
9 will be providing FF&E and artwork.
10 So in summary on the roles and responsibilities, 11 the Indian Health Service, Division of Engineering
12 Services, is the construction contract agency. The
13 contracting officer and the contracting officer's
14 technical representative, Abe Vinikoor and myself, 15 reside in Seattle and we will be supported by Norton
16 Sound Health Corporation staff in Nome, supported by the
17 Alaska Area Native Health Service staff in Anchorage, 18 and will be supported by the Norton Sound Health
19 Corporation architectural and engineering staff in
20 Anchorage.
21 We'll also be working closely with the Nome
22 Eskimo Community on IP referral, training, and
23 monitoring issues. And of course working with the State
24 Fire Marshal's office in the City of Nome on other code
25 issues.
1 Just what Jay had gone over was, you know, there
2 will be a Norton Sound Health Corporation project
3 manager, Cliff Gray, on site that will be providing a
4 resident engineer, quality assurance inspectors, and
5 special inspectors. The Area's role again is funding
6 and periodic on-site monitoring. And the A/E staff will
7 only be contract support/document management at DOWL, 8 and A/E submittal review, RFI, and periodic observation
9 services by Kumin on site.
10 A little bit about the project description and
11 history. I think Angie pretty much covered this. It's
12 on a new 38.9 acre site in the northeast corner of Nome
13 between -- on By-Pass Road between L and N Streets.
14 Like she said, it's about 150,000 square feet, three
15 stories. It has an 18-bed subacute inpatient/labor and
16 delivery unit.
17 It has an existing site. A gravel pad and the
18 steel pipe piling foundation is in -- the photos are
19 back there -- thermosiphons. And the government will
20 provide the structural steel. We expect it to be on
21 site no later than September of '09.
22 And this is where the contractor that is awarded
23 may want to speak with Cliff Gray about unloading the
24 steel because he will be delivering that to the site.
25 So if you are the lucky contractor, I would recommend
6 (Pages 18 to 21)
1 you talk to Cliff.
2 A little bit about project time lines. I won't
3 bore you with the beginning stuff, but we do anticipate
4 award/notice to proceed the summer of '09, late summer.
5 And in the fall of '09, again, we anticipate the
6 structural steel will be on site. In the spring of '10, 7 we anticipate the erection will start. And in the fall
8 of '12, we anticipate completion of occupancy, which is
9 1157 days from notice to proceed with a one-year
10 anticipated warrantee period.
11 And that's all I have as far as the project
12 status and overview.
13 MR. VINIKOOR: They were going to go after --
14 MR. GEISERT: Oh, that's right. You guys were
15 going to go after NSHC's presentation.
16 MR. FARMWALD: Paul, I've got one more.
17 MR. GEISERT: Go ahead.
18 MR. FARMWALD: This is Jay Farmwald again.
19 There was reference to the owner-supplied structural
20 steel. That's not 100 percent of the structural steel.
21 So please look at the drawings carefully and attachments
22 to the RFP to understand where the demarc line is
23 between owner-supplied steel and your supplied steel.
24 MR. VINIKOOR: Did everyone get a chance to
25 sign the sign-in sheet?
1 I'd like to give a brief overview of the
2 acquisition process and then highlight some specific
3 contract clauses that might be different than what you
4 would typically see in a direct federal contract.
5 There's my name and e-mail address. I give
6 you that address so you could just send me nice personal
7 messages. But your inquiries, you'll see that we have a
8 separate inquiry e-mail address that we like bid
9 inquiries to come into. If you send it to there, I
10 can't guarantee that I'll notice it as a bid inquiry and
11 get an answer to you.
12 So here's what I would like to discuss, a
13 tentative award schedule. And as part of that, I would
14 like to get some feedback from you as far as a bid
15 extension. I know we've gotten a number of requests to
16 extend the closing date for proposals, so I'd like to
17 hear your thoughts about what an appropriate new date
18 would be. And then talk just a little about where the
19 plans and specs and solicitation can be found, what you
20 need to submit with your proposals, how they'll be
21 evaluated, how we'll determine who will get the award, 22 and then highlight those contract requirements. And
23 then we'll take your general questions at the end.
24 So here's the tentative schedule. We issued
25 the RFP the 3rd of April. Today is the pre-proposal
1 conference. The current date for submission of
2 proposals is the 5th of May. Contract award, we need to
3 award that by the 15th of July. And 10 days after that, 4 no later than that, would be the notice to proceed. And
5 then final completion, what, 1,157 days, not later than
6 September.
7 So we've got a number of requests about
8 extending the proposal date. We know that you need more
9 time. I've gotten some requests for two or three weeks.
10 I mean, I'd like to hear some feedback. What do you
11 think you might need? We're open to suggestions. We
12 want to accommodate you as well as we can but still keep
13 to that award schedule, getting the award done by mid
14 July.
15 SPEAKER: Somewhere around maybe like May
16 27th, before the holiday weekend.
17 MR. VINIKOOR: That would be after the holiday
18 weekend --
19 SPEAKER: Oh.
20 MR. VINIKOOR: -- because I think Memorial Day
21 is that Monday.
22 MR. FARMWALD: It's early this year.
23 MR. VINIKOOR: Yeah.
24 SPEAKER: Oh, it is?
25 MR. VINIKOOR: Yeah. That would be right
1 after Memorial Day weekend.
2 SPEAKER: We can cancel Russ out.
3 MR. VINIKOOR: What did you say?
4 SPEAKER: We can cancel Russ out.
5 MR. VINIKOOR: Okay.
6 MR. JANDA: Substitutions. The process of
7 submitting substitutions for approval, et cetera. It
8 says substitutions will be allowed via amendment --
9 MR. VINIKOOR: Well, you know, the government
10 process is not to allow substitutions during the bidding
11 phase. You know, we do the substitutions if -- you
12 know, from an equal product after the award --
13 MR. JANDA: I thought I read that --
14 MR. VINIKOOR: -- because it's right under the
15 contract to provide materials that are equal to the
16 brand names that we might specify. You know, the
17 contract clause, that's the materials, and workmanship
18 clause states that, you know -- a specified material, 19 it's sort of a standard equality. But the contractor
20 has the right to submit an equal product as long as the
21 contracting officer determines that it is in fact equal.
22 So that process occurs after award, not during.
23 MR. JANDA: Because it says you have to go
24 through this, all substitutions are allowed as provided
25 or approved and the amendment will be issued to
7 (Pages 22 to 25)
1 include --
2 MR. VINIKOOR: Yeah, we need to correct that.
3 And we're going to correct the language and the
4 specifications that talk about approving substitutions
5 during the bidding phase. That's not how the government
6 operates, so we're going to correct that.
7 And, in fact, there's going to be a technical
8 amendment coming out fairly shortly, I think.
9 MR. GEISERT: Abe, could I just interrupt for
10 a minute?
11 For Valerie's sake, when you have a question, 12 could you please state your name and who you're with so
13 our stenographer can get that information?
14 MR. JANDA: My name is Noel Janda. I'm with
15 DSI. I was referring -- my part was to the
16 communication piece.
17 MR. VINIKOOR: So any other thoughts about a
18 revised closing date for the closing? The 27th is what
19 I heard.
20 MR. DOKOOZIAN: I was just looking at my
21 calendar and kind of looking at Memorial Day and trying
22 not to destroy everybody's family time or something like
23 that. The 29th is the following Friday.
24 SPEAKER: Yeah, that would be good.
25 MR. DOKOOZIAN: That gives us time for people
1 to maybe take some time at Memorial Day and then come
2 back and have a good full week there -- well, maybe not
3 quite a full week, but four days -- to put the proposal
4 together.
5 MR. VINIKOOR: You know, the proposals have to
6 physically come to our office, you know, in Seattle. So
7 you're going to have to account for, you know, the time
8 to physically get those proposals to us as well.
9 So May 29th would be that Friday.
10 MR. FARMWALD: And that comment came from
11 which distinguished gentleman, for the stenographer?
12 MR. DOKOOZIAN: The one behind me because I'm
13 not distinguished. Jim Dokoozian.
14 MR. VINIKOOR: Any other thoughts?
15 MR. BELOY: I have one comment. I'm Kiel
16 Beloy with Kiewit. So if we were to extend it to May or
17 whatever day you select or you selected, the contract
18 award will still be mid July?
19 MR. VINIKOOR: Yeah. I mean, we still need to
20 keep, you know, the July 15th award date. You know, we
21 think -- even with an extension, we don't think that
22 date is in jeopardy, especially if you give us these
23 great proposals that we can award immediately.
24 Do we want to try to make a decision now?
25 MR. FARMWALD: No. I think we should --
1 MR. VINIKOOR: We'll take it under advisement
2 and there will be an amendment forthcoming. It'll have
3 the technical amendment that's been prepared; if we have
4 it in time, it will have the information about this
5 meeting; and it will have a date for -- a new date for
6 the proposals. But we are going to extend it, so -- and
7 it will be in the two-to-three-week time frame. So I
8 hope that works out for everybody.
9 The solicitation, I just want to go briefly.
10 It's all on the FedBizOpps web site. It's the
11 solicitation, the plans, the specs, the other
12 information. You know, the solicitation is available to
13 anyone with web access. The plans and the specs -- if
14 you go to the next slide -- they're locked, secured
15 documents. So you have to be registered in FedBizOpps
16 and registered in CCR.
17 I haven't had any indications that people are
18 having difficulty, you know, downloading the plans and
19 specs or getting access to them. Is that the case? Has
20 anyone had trouble? No? That's great. This is our
21 first experience doing it strictly, you know, 22 electronic. It's saving us a lot of time and effort.
23 We appreciate you being able to do that for us.
24 So now I'd like to just briefly go through
25 some aspects of the acquisition process. This is a
1 disclaimer that -- you know, this is just like an
2 overview that you really need to read the solicitation
3 and comply with the requirements of solicitation.
4 So what do you need to submit? If you look in
5 the solicitation, there's a Section L-7 that details the
6 instructions for your proposal. And it's to be
7 submitted in two parts: The business proposal, Part 1;
8 and the technical proposal, Part 2.
9 The technical proposal will go to our
10 technical evaluation panel and they're going to evaluate
11 the strengths and weaknesses and risks of your proposals
12 and score the proposals. And the source election
13 official will use that to make a selection based on the
14 prices. The evaluation of the prices as well.
15 So the Part 1 is the business proposal and
16 that's the part that you fill out on the SF1442, which
17 is that front form, the solicitation offer and award
18 form. And there is a place in there to acknowledge
19 amendments. So please, when you submit your proposal
20 make sure you acknowledge all the amendments that might
21 be issued.
22 At this point, there was just that one
23 amendment that announced this meeting, but there are
24 going to be a number of amendments coming up. And I
25 don't know if you had trouble noticing that there was an
8 (Pages 26 to 29)
1 amendment posted. I think there's like a watch list
2 that you can sign up for so if there's any change on
3 that FedBizOpps web site you'll get an e-mail about it.
4 You might just want to check the web site periodically
5 and refresh it. Sometimes if you don't refresh it, you
6 know, the new information won't come up. So we're going
7 to post all the new amendments and any additional
8 information, like the information about this meeting, 9 strictly to that web site.
10 So then you'll need to submit your Section B, 11 which is the price schedule, fill in all the required
12 prices. You'll need to do the online representations
13 and certifications. That's called ORCA, which is
14 another online government site for your annual
15 representations and certifications. Everyone familiar
16 with ORCA? There should be people in your organizations
17 that have already completed that and are familiar with
18 it. If not, if you have any questions, you can give me
19 a call about it. But I think there's a link from CCR to
20 the online representations and certifications.
21 And then if you're a large business, you'll
22 need a subcontracting plan submitted with your proposal.
23 I'll talk a little more about that --
24 MR. GOLICK: John Golick, SKW, a question on
25 that. If it's required, can that get maybe three days
1 after the bid is turned in? We've kind of typically
2 been able to talk to government agencies to push that
3 three days past the closing date just because we don't
4 know subcontractors until the bid date.
5 MR. VINIKOOR: We'd like it submitted with
6 your proposal.
7 MR. GOLICK: Okay.
8 MR. VINIKOOR: We'll discuss it in a little
9 more detail, but yeah. I mean, one of the reasons is we
10 want to try to get this coordinated as soon as possible
11 and we want, you know, at one time all the information
12 that we need at hand to make an award. If things sort
13 of dribble in, it will make it a lot more difficult to
14 get a time in awarding.
15 MR. DOKOOZIAN: Jim Dokoozian from Arctic
16 Slope Construction Holding Company. I understand what
17 your concern there is, but the process of bidding and
18 trying to come up with a competitive price, that last
19 hour or half hour can change what happens on
20 subcontractors. We don't prefer it that way, but that's
21 what happens to us. So then for us to be able to turn
22 around and have given you in writing in Seattle our list
23 of subcontractors means that we have to make a decision
24 a day at least ahead of time before we have received
25 final pricing or even any pricing from subcontractors.
1 So it's virtually impossible for us to give you, what
2 I'll call, good data.
3 I mean, people will always comply, but we're
4 going to go through a process of sorting it out
5 afterward. If you made it a day later even or
6 something -- the numbers are all there that were chosen.
7 We could fax it down or something.
8 MR. JANDA: As one of the subcontractors, I
9 know I deal with -- in follow-up to this, I'm one of the
10 guys putting in the bidding at the last second. What I
11 suggest is maybe just doing a subcontractor's plan and
12 maybe doing an overview as part of the response. But if
13 you are looking for all the certifications and all that
14 other stuff, it's an enormous amount of work to
15 complete. I would suggest you do that as part of the
16 submittal process.
17 MR. VINIKOOR: Well, we'll talk about the
18 subcontract plan, but we need to negotiate an acceptable
19 plan before we make an award. So let me take it under
20 advisement what you said here and see, you know, what we
21 can do. I hear your concerns. Let me think about it, 22 take it under advisement. And if there's a change to
23 our requirement that you submit it with your proposal, 24 it will be an amendment. I hear your difficulty.
25 We'll need a bid bond. There's the SF24 form.
1 So the bid bond is 20 percent of your proposed price or
2 $3 million, whichever is greater.
3 And then if you're going to be proposing as a
4 joint venture or some sort of formal teaming
5 arrangement, we want to see that agreement that you have
6 with your joint venture partner.
7 And then because DOWL and Kumin are
8 participating in the evaluation as advisory non-voting
9 members of the evaluation panel, we have a section in
10 there about having an agreement signed with them with
11 regard to non-disclosure of proprietary information in
12 your proposals. So that's a federal acquisition FAR
13 requirement. There's a sample agreement that DOWL and
14 Kumin have prepared in the solicitation. So we want
15 that with your business proposal.
16 So the Part 2 is the technical proposal. And
17 that includes the list of subcontractors in excess of
18 $5 million. We're just looking for the list.
19 Then if you are proposing as a joint venture
20 as a teaming arrangement, we'd like you to tell us, you
21 know, what the roles of the two joint venture parties
22 are, what their level of participation is. This way, 23 we're going to be able to evaluate appropriately the
24 past performance of the two parties.
25 And then if you go to Section L-7, there's
9 (Pages 30 to 33)
1 detailed information about what we will -- with regard
2 to information on your corporate experience; the
3 technical and management approach, which is the work
4 plans, key personnel, scheduling and communication
5 plans. Then you're given the opportunity to tell us
6 about past performance issues that you've had and how
7 it's resolved, as well as an OSHA violation. You know, 8 to provide a list of any OSHA citations and how those
9 have been resolved.
10 We're going to be evaluating the past
11 performance of the offerors and the major subs. So we'd
12 like that information for the major subcontractors, 13 which we define as any subcontractor over $5 million.
14 And then we want the plans and the goals that
15 you have for giving Indian Preference. When Paul said
16 IP, that's what he meant. That's Indian Preference for
17 American Indian/Native Alaskans in terms of training, 18 employment, and then as well subcontracting with
19 Native-owned organizations. We'll talk in a little more
20 detail about that in a few minutes.
21 And then as the final part, we want
22 information with regard to your past success in
23 utilizing small disadvantaged businesses in prior jobs.
24 So all this information -- if you go to the
25 next slide -- relates to how you're going to be
1 evaluated, and that's stated in Section M of the RFP.
2 So you really need to understand Section M when you
3 prepare your proposal. If you understand how we're
4 going to evaluate you, then I think you'll be in a
5 better position to give us your best proposal.
6 Just some pointers. Remember to comply with
7 the technical submittal -- the L-7 proposal submittal
8 requirements. As it states, the technical factors when
9 combined are significantly more important than price.
10 So when we do our selection, we're going to be
11 considering the technical factors and evaluation of that
12 is more important than price. But we'll talk a little
13 more about how that gets accomplished in a minute.
14 Then just as warning, if you fail to give us a
15 complete proposal, you really risk being eliminated from
16 consideration. So just make sure you read it, comply
17 with it, and give us everything that we've asked for.
18 We'll go to the next one. So here is just a
19 summary of the technical non-price factors. So these
20 five factors are in descending order. Factors A, B, C, 21 and D are equal weight. And Factor E is a very minor
22 weighting.
23 So in corporate experience, we have three
24 sub-factors. We go into some more detail defining those
25 in the RFP. These are all equally weighted, these three
1 sub-factors; one, two, and three. Your experience with
2 similar hospital construction projects, your experience
3 with large construction projects in remote arctic
4 locations similar to Nome -- and we sort of have
5 definitions of what we think constitutes similar and
6 what we think constitutes large -- and then your
7 experience working with Alaska Native communities. So
8 those are all equally important to us.
9 Factor B is your technical/management
10 approach, which consists of work plans, your key
11 personnel, your scheduling plan, and then your
12 communication plan, which is how you propose to set up a
13 system so we're all effectively talking to each other
14 and getting submittals timely. We're looking for your
15 ideas about how to accomplish that.
16 And then past performance.
17 And then the other equally weighted factors, 18 your plans and goals for Indian Preference. There's two
19 sub-factors which are equally rated.
20 I should go back to Factor B. Those factors
21 are listed in descending order. But I think one, two, 22 and three are equally rated. Is that it? I think
23 that's it. And then four is minor. I think I got that
24 right.
25 And then Factor D, there's two aspects to the
1 Indian Preference. There's the employment of Natives
2 and the training, and then there's the subcontracting.
3 So those are both equally important to us.
4 And then the minor factors, your past
5 experience -- your past success in utilizing small
6 disadvantaged businesses.
7 SPEAKER: How much are the percentages?
8 MR. VINIKOOR: No, we don't publish the
9 percentages.
10 SPEAKER: Why not?
11 MR. VINIKOOR: Because we're not required. We
12 just don't do it as a standard practice. But I think
13 we've given you some pretty good ideas here. I mean, 14 the first four equally weighted and that last one is
15 pretty minor. So I think you should be pretty well
16 aware, you know, of how we are considering these factors
17 in terms of weighting.
18 So what we plan to do is award without
19 discussions. So that means we want to get with your
20 initial proposal your best possible price and your best
21 possible technical proposal. So we prefer not having to
22 go into discussions and get best and finals -- or is it
23 called final proposal? We want to be able to take your
24 initial proposal and go with the best value that's
25 submitted.
10 (Pages 34 to 37)
1 So you shouldn't assume that you're going to
2 be contacted or afforded an opportunity to qualify, 3 discuss, or revise your proposal. So don't go into it
4 thinking, oh, well, I'll give it a shot knowing we're
5 going to ask you about something, because we don't
6 intend to. But we do leave it open that if we need to
7 open discussions or have some clarifications, we'll do
8 that. So I would take this to heart in terms of urging
9 you to, you know, submit your best price and technical
10 proposal with your initial offer.
11 So who will get the award? Well, I can't tell
12 you, but it's going to be the offeror who submits the
13 proposal that the source selection officials determines
14 is the most advantageous, the best value for the
15 government. What's the best value? Well, it's getting
16 the best service at the best possible price that we can.
17 So who's the source selection official? It's
18 not me. Though typically it's the contracting officer
19 that's the source selection official, but this is a
20 highly visible project for IHS and it has Recovery Act
21 funds, which are getting a lot of attention. So the
22 acting head of contracting for all of IHS will be the
23 source selection official. And that's actually my boss
24 in Seattle, just by coincidence. Dale Burson in
25 Seattle. He's the head of contracting in Seattle for
1 the Division of Engineering Services and he's also
2 currently the acting head of contracts for all of IHS.
3 So he'll be the source selection official.
4 So he's going to look at your technical
5 non-price -- those factors that we listed in terms of
6 your strengths and weaknesses and risks. He's going to
7 look at the evaluation that the technical evaluation
8 panel provides and their rate, their scoring. And he's
9 going to compare it and look at the prices and determine
10 which one in his best judgment represents the best value
11 to the government.
12 So it could be -- as the last bullet says, it
13 could be the highest rated technical offeror. For
14 instance, if the highest technical proposal or the most
15 technically superior proposal is the lowest priced, then
16 the decision is going to be pretty clear who gets it.
17 If it's not the lowest price, then he has to make a
18 decision whether paying more money is worth the
19 additional technical capabilities the higher-rated
20 proposal provides.
21 So he has to make that decision, yes, we're
22 paying more money because we're getting more something, 23 consistent with the evaluation factors. If he doesn't
24 think it's worth that additional money, if the highest
25 rate of proposals are a higher price, then he might go
1 with a lower-priced proposal even though it's
2 technically rated lower. So it's a judgment call. It's
3 not arbitrary, it's rational. It's based on the
4 evaluation factors and it's consistent with what we say
5 in the proposal. But it is -- it's a business judgment
6 call.
7 So I'd like to just go through some highlights
8 of the contract requirements. The first is these unique
9 clauses that are in there because the funding will come
10 from the American Recovery and Reinvestment Act of 2009, 11 the Recovery Act. So on March 31st they were published, 12 clauses that implement certain unique Recovery Act
13 provisions. So we're very happy that we'll be able to
14 get this money. I guess it's money the
15 great-grandchildren are going to have to pay back, but
16 it will help build our hospital now so we're happy about
17 that.
18 So there's sections. What I have here is the
19 sections in the act and the new FAR provisions that
20 implement those sections. And I just want to bring your
21 attention to these. You really need to read them. The
22 first one is the reporting requirements. And that's
23 FAR 52.204-11. All these clauses are dated March 2009.
24 They came out on March 31st.
25 So at that one -- let's see where that is.
1 It's in I-3 of the RFP. And that discusses some unique
2 reporting that you're going to have to do as
3 contractors, because this is being funded by the
4 Recovery Act.
5 The Recovery Act, you know, requires that the
6 public knows what's happening with their money. And
7 there's transparency requirements in terms of how the
8 government is using this money and what benefit it's
9 giving the public in terms of job creation and
10 stimulating the economy. So there is some extensive
11 reporting requirements that the contractor and
12 subcontractors, certain subcontractors, will have to
13 have, so you need to be aware of that.
14 The next one is FAR 52.215-2. In the RFP it's
15 just incorporated by reference, but any of those clauses
16 that incorporated by reference we can give you the full
17 text. We can give you the site. There's a web site, 18 acquisition.gov, that you can go to to look at the full
19 text of those clauses. But that clause has been
20 revised. There's an alternate that provides for
21 additional rights of GAO and the Inspector General, the
22 Government Accountability Office, and the IG is the HHS
23 Inspector General's office. So they have additional
24 rights because of the Recovery Act in terms of coming in
25 and looking at records.
11 (Pages 38 to 41)
1 The next one is 52.203-15, whistleblower
2 protections. So the law says that contracts that are
3 funded by the Recovery Act, whistleblowers are given
4 certain protections against retaliation against them by
5 the contractor. So if a whistleblower calls the IG and
6 tells us something bad, this prevents contractors from
7 retaliating against them.
8 And then the Section 1605 is the section with
9 regard to use of American iron, steel, and other
10 manufactured goods. It's pretty complex. I suggest you
11 read it pretty carefully. I mean, it does change the
12 Buy America aspect to a certain degree. Buy America is
13 in there, but this puts a little twist in it. I would
14 look at it carefully and if you have questions, address
15 it.
16 That final clause is if you don't think you
17 can comply for certain materials, you don't think they
18 are a domestic supply, you would tell us. So take a
19 look at that. Have someone in your organization take a
20 look at that and make sure that you are going to be
21 complying with it.
22 So let's talk about Indian Preference. This
23 is unique to Indian Health Service projects. Our
24 projects are specifically for the benefit of Indians and
25 Alaska Natives. So by public law we're required to make
1 sure our contractors give preference to Indians and
2 Alaska Natives in hiring any subcontractors. This is
3 very important to us. And the Nome Eskimo Community is
4 going to be providing assistance to contractors with
5 regard to Indian Preference.
6 So there's two clauses. The first is HHSAR.
7 And HHSAR stands for Health & Human Services Acquisition
8 Regulation. And the first one is the Indian Preference
9 clause. You have to give preference in employment to
10 Indians, and that includes Alaska Natives, who can
11 perform the work regardless of their age, sex, religion, 12 or tribal affiliation. And then to the extent feasible
13 and consistent with the efficient performance of the
14 contract, you have to give preference in employment and
15 training to those who are not fully qualified to do the
16 work.
17 And then you need to give preference to Indian
18 organizations and Indian-owned economic enterprises --
19 and the clauses give definitions of what constitutes
20 Indian organizations and Indian-owned economic
21 enterprises -- in awarding of subcontracts consistent
22 with efficient performance under reasonable terms and
23 conditions, including price.
24 And you have to maintain statistical records and
25 you need to flow-down this clause and the other clause
1 to subcontractors. And then we conduct periodic reviews
2 to ensure compliance. And we're going to be assisted by
3 the Nome Eskimo Community in our monitoring efforts.
4 And then there's the Indian Preference Program
5 which goes beyond the Indian Preference clause
6 requirements in the sense it requires you to establish
7 and conduct an actual Indian Preference Program. So you
8 have to designate an individual liaison officer who will
9 administrate your program. You have to advise
10 recruitment sources and include a statement in all
11 advertisements that Indian applicants will be given
12 preference.
13 You need to post a notice of your employment
14 meetings with the designated Native Corporation
15 representative, which in this case would be the Nome
16 Eskimo Community. You need to establish a
17 subcontracting program to give preference to Indian
18 organizations.
19 And there's further record keeping and quarterly
20 reporting that's required. And we will work with Nome
21 Eskimo Community to monitor and review your quarterly
22 reports to make sure that you're doing what's necessary
23 and complying with your plan and achieving the goals
24 that you're going to give us in your proposal.
25 Now separately if you're a large business, you
1 need to give us a small business subcontracting plan.
2 And I heard what you said about needing some time to
3 prepare that plan beyond the date for submission of
4 proposals. We'll take that under consideration.
5 The plan is not part of the selection. We're
6 not evaluating your plan in terms of who gets the award.
7 But once we select the contractor, we need to make sure
8 that before award, we had negotiated an acceptable small
9 business subcontractor plan with you. And there's
10 specific goals that are in the RFP and there's a sample
11 plan, an model plan, that HHS has developed.
12 And before we accept a plan, we send it to the
13 Small Business Administration. They give us their input
14 on it. We also send it to the HHS small business
15 advocate, and they're going to give us their input on
16 it.
17 MR. FARMWALD: Before we move too far past
18 Indian Preference, were we going to give the Nome
19 Eskimo --
20 MR. VINIKOOR: Oh, yeah. I'm sorry. I did
21 forget. I moved on too quickly. I wanted to give the
22 representatives from the Nome Eskimo Community an
23 opportunity to say a few words about their participation
24 and their activities.
25 MS. GOODWIN: Good morning. I'm glad you're
12 (Pages 42 to 45)
1 all here. My name is Emma Goodwin, and I'm the deputy
2 director for Nome Eskimo Community, which is a federal
3 recognized and tribal government for Nome. And I'm also
4 the contact person named in the RFP.
5 NEC will be providing Indian Preference, 6 employment referral, training, and monitoring services
7 during the construction phases of this project
8 consistent with Indian Preference goals established by
9 the Norton Sound Health Corporation Board where they
10 delegated the responsibility for construction of this
11 project to IHS. Related goals outlined in the Recovery
12 Act implementing guidance gives specific requirements in
13 the Indian Preference clauses in the RFP.
14 NEC will have a formal role on the project to
15 assist the contractor in meeting these requirements and
16 goals. The specific services and activities to be
17…