Amendment No. 000002 dated April 24 2009. Extension of due date for receipt of offers to May 29 2009 plus technical and other changes.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OMB No. 0990-0115
(x)
09-102-SOL-00003
x x
6 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
Seattle WA 98121 2201 6th Avenue, RX-24 Division of Eng. Services-Seattle
Seattle WA 98121 2201 6th Avenue, RX-24 Division of Eng. Services-Seattle
NS0004/24/2009000002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
04/03/2009
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
New Norton Sound Regional Hospital, Nome Alaska
1. Reference SF 1442, block 13a:
The due date for receipt of offers is extended to May 29, 2009 by 1500 (hour) local time.
2. The contract technical specifications, contract drawings and other information in
Section J, List of Attachments, are amended as described in the attached
Amendment/Modification No. 2 dated 23 April, 2009, prepared by the Architect of Record, consisting of six pages plus 107 attachments.
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
ABRAM L. VINIKOOR
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
NSN 7540-01-152-8070
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
Electronically Signed 04/24/2009
Amendment #000002 Page 2 Solicitation No. 09-102-SOL-00003 Construction of the New Norton Sound Regional Hospital Nome, Alaska
3. Reference SF 1442, Block 11.
Change “(See Section E)” to read “(See Section F)”.
4. Reference Section F-3, 52.211-12, Liquidated Damages – Construction:
Replace “…in the amount of $6,083” with “… in the amount of $5,883”.
5. Delete Section H-9, Photographs on Sample Wall Panel.
6. Replace Section H-8 Progress and Final Photographs in its entirety with the attached Section H-8.
7. Replace Section H-16, Hours of Work, in its entirety with the following:
H-16 HOURS OF WORK
Work may be performed between the hours of 7:00 AM and 10:00 PM or as permitted by Ordinance.
8. Reference Section J-4, Department of Labor General Wage Determination:
Replace the wage determination with the attached General Decision Number, AK080001 dated 04/17/2009.
9. Section I-1, Clauses Incorporated by Reference:
In 52.219-9 Small Business Subcontracting Plan (APR 2008) – Alternate II (OCT 2001), delete the use of Alternate II.
By deleting Alternate II, offerors who are large businesses are no longer required to submit the Small Business Subcontracting Plan with their offers.
Rather, offerors who are large businesses must submit such plan within seven
(7) calendar days after the due date for receipt of offers.
10. Reference Section L-7, Proposal Submittal/Preparation Instructions:
In Part Two – Technical Proposal, Item b.ii, Key Personnel, add “Indian Preference Liaison Officer” to the list of required key personnel.
11. Reference Section M-2, Technical (Non-Price) Evaluation:
In Factor B, Technical/Management Approach, Subfactor 2, Key Personnel, add “Indian Preference Liaison Officer” to the list of proposed key personnel.
-END OF AMENDMENT-