NSRH Final Presentation-Geisert.ppt

PPT presentation 151 KB Posted

Attached to
Recovery - Construction of New Norton Sound Regional Hospital in Nome, Alaska
Solicitation number
09-102-SOL-00003
Issued by

About this file

PowerPoint Presentation by Paul Geisert

View the file

Other files

File Type Posted
Amendment_9_12-102-SOL-00003_nin-rml.pdf PDF
Amendment_9_Attachment_1Highway_mt120001_6.22.12.pdf PDF
Pano from SE Corner - 30 June 08.jpg JPG image
Amendment No. 000007.pdf PDF
South Edge Looking East - 30 June 08.jpg JPG image
Main Pad Looking West —
Main Pad Looking North - 30 June 08.jpg JPG image
South Edge Looking West - 30 June 08.jpg JPG image
NEC-NSHC IP Scope of Work —
05.29.2009_Compiled Answers.pdf PDF
Looking West Along ByPass Rd —
Amendment No. 000006 SF30.pdf PDF
Amendment No. 000005 SF30.pdf PDF
Amendment No. 000004 SF30.pdf PDF
SUPPLIES OR SERVICES AND PRICE REVISED 5-8-09.pdf PDF
Amendment No. 000003 SF30.pdf PDF
Pre-Proposal Final Agenda.pdf PDF
Pre-Proposal Conference 4-22-09 Transcript.pdf PDF
Sign-in Sheet Pre-Proposal Conference 4-22-09.pdf PDF
Nome Pre-Proposal Meeting-Vinikoor.ppt PPT presentation
H-8 Progress and Final Photographs.pdf PDF
AK1_dvb 04-17-2009.txt TXT text file
Amendment No. 000002 SF30.pdf PDF
Amendment No. 1.pdf PDF
AK1_dvb 04-03-2009.txt TXT text file
sf24_f.pdf PDF
sf25_f.pdf PDF
SampleSubcontractingPlan.doc DOC document
Sol 09-102-SOL-0003.pdf PDF
Sf25a.pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Norton Sound Regional Hospital Nome, Alaska Project Overview and Status Paul Geisert, P.E., Project Officer

Roles and Responsibilities Department of Health and Human Services, Indian Health Service, Division of Engineering Services - Seattle (DES)

Construction Contract Agency
Ken Harper, P.E., Director
Contracting Administration Branch
Project Management Branch
Technical Support Branch

Contracting Administration Branch

Contracting Officer (CO) is the Authority
Changes the work or contract
Approves payments
Settles requests for equitable adjustments
Makes final acceptance, etc.
Contracting Officer - Abram Vinikoor

Project Management Branch

Project Officer and Contracting Officer’s Technical Representative (COTR)
Works under the Authority of the CO
Technical approval of submittals
Directions to contractor that clarify contract requirements
Evaluation of performance and progress for payment and acceptance
Project Officer/Overall Project Manager for the IHS Paul Geisert, P.E.
Alternate PO/PM - Henry Hardnett, FAIA

Technical Support Branch

Licensed Architects and Professional Engineers
Advisors to CO and PO/COTR on technical issues
Provide technical support to PO/COTR
Submittal reviews
Code interpretation
Onsite monitoring, etc.

Project Officer, COTR and support staff precluded from taking action that:

Alters performance schedule
Increases contract price
Modifies contract language

Department of Health and Human Services, Indian Health Service, Alaska Area Native Health Service (AANHS)

Area Director
Christopher Mandregan, Jr., MPH, Director
Office of Financial Management
Office of Environmental Health and Engineering (OEH&E)
Tom Coolidge, P.E., Director
Dale Mossefin, P.E., Director, Health Facilities Engineering

Office of Environmental Health and Engineering (OEH&E)

Budgetary and Programmatic Role
Certification of funds
Advocates for the NSHC
Technical and Programmatic Advisors to DES
Member of Project Leadership Team (PLT)
Member RFP Technical Evaluation Review Panel
Onsite monitoring and support to CO & COTR/PO

Norton Sound Health Corporation (NSHC)

Carol Piscoya, Interim President and CEO
Cliff Gray, NSHC Project Manager
NSHC –
Land Owner
Facility Owner and Operator after transfer from DES at Project Completion
Advisors to IHS
ISDEA (P.L. 93-638) Title V Agreement with the IHS

ISDEA (P.L. 93-638) Title V Agreement

Furnish equipment & art work not in direct federal contract
Provide construction contract administration (CCA) services to IHS
Review contractor provided submittals, changes to work, time extension requests, and like matters
On-site inspection and surveillance
Recommendations to the Government’s CO, COTR/PO

NSHC CCA Team

In-house staff - Nome
Architect of Record
Kumin Associates, Inc. – Anchorage
Mahlum Architects - Seattle
Sub-consultants
DOWL HKM - Anchorage
Program management for NSHC, Resident Engineer, contract support to NSHC, document control, inspector and clerical support (on-site in contractor provided trailer)
Nome Eskimo Community
IP referral, training and monitoring

State Fire Marshall’s office

Official Authority Having Jurisdiction for Fire Code Issues
Code issues not in the jurisdiction of the State Fire Marshall’s Office resolved by City of Nome and/or IHS:DES-Seattle

Items Excluded from Contract (provided under separate contract with DES)

Commissioning Agent
Off-Site Utilities (NJUS)
FF&E and Art Work

Summary Roles and Responsibilities

IHS:DES - Construction Contract Agency
CO and COTR reside in Seattle
Supported by NSHC staff in Nome
NSHC Project Manager, Resident Engineer, QA inspectors, and Special Inspectors
Supported by AANHS staff in Anchorage
Funding and periodic onsite monitoring
Supported by NSHC A/E Staff in Anchorage
contract support / document management at DOWL HKM, and A/E submittal review, RFI, and periodic observation services at Kumin Associates
Nome Eskimo Community – IP Referral, Training and Monitoring
State Fire Marshal Office – AHJ Fire and Life Safety Code Issues
City of Nome – Other Code Issues

Project Description and History

Hospital located on a new, 38.9 acre site in NE Nome (By-Pass Road between L & N streets)
150,000 square foot, steel framed medical facility
Three stories with a ground level entry, heated crawl space and mechanical penthouse
18-bed sub-acute inpatient/labor and delivery unit

Previously constructed and Government furnished items

Building site gravel pad
18-inch steel pipe piling foundation
Thermo-siphons
Government provided materials
Structural steel
On-site NLT September 2009
Contractor can coordinate with NSHC for unloading onto site

Approximate Project Timelines

Spring 2008 - Pad Constructed
October 2008 - IHS funded pile/thermoprobe foundation
November of 2008 - Foundation started
January of 2009 - Foundation completed
February 2009 - Design complete
April 2009 - RFP issued
Summer 2009 - Anticipated Award/NTP
Fall 2009 - Anticipated Structural steel on-site
Spring 2010 - Anticipated erection start
Fall 2012 (1157 days from NT) Anticipated Completion/Occupancy
Fall 2013 - End anticipated warranty period