The file is a Schedule of Material Submittals for the Construct T-1A Static Display project at Laughlin Air Force Base, detailing 44 specific submittal requirements across three Notice to Proceed (NTP) phases. The schedule outlines detailed submission requirements for various documents including design packages, entry access lists, safety plans, quality control documentation, environmental compliance forms, waste disposal records, and project completion documentation.

Key submission timelines are structured around three primary phases: NTP 1 (Design), NTP 2 (Pre-Construction), and NTP 3 (Construction), with specific deadlines for each submittal. Critical submittals include design packages (65%, 95%, and 100%), entry access lists, safety compliance certificates, quality control plans, environmental notifications, and final project documentation like As-Built drawings and DD Form 1354. Submissions range from 2 weeks prior to base access to 2 weeks after final inspection, with most documents required within specific timeframes after each Notice to Proceed.

View the file

Other files for this federal contract opportunity

Other files attached to Construct T-1A Static Display, newest first.
File Type Posted
15 Financial Institution Reference Sheet.pdf PDF
Solicitation Amendment FA309925R00020003 SF 30.pdf PDF
01 MXDP 24-1015 Construct T-1A Static Display - Draft Statement of Work v2.pdf PDF
Solicitation Amendment FA309925R00020002 SF 30.pdf PDF
Solicitation Amendment_FA309925R00020001 SF 30.pdf PDF
11 Updated Past Performance Questionnaire.pdf PDF
14 Requests for Information.pdf PDF
Solicitation_FA309925R0002.pdf PDF
01 MXDP 24-1015 Construct T-1A Static Display - Draft Statement of Work.pdf PDF
04 C. Environmental Quality Construction Specifications Laughlin AFB May 2024.pdf PDF
05 D. Laughlin Legacy Sustainable Landscape Plan 2011.pdf PDF
10 Notification of Compliance with Contracting Insurance Requirements.pdf PDF
02 A. MXDP 24-1015 Construct T-1A Static Display Conceptual Layout.pdf PDF
03 B. Laughlin AFB Division 01 General Specifications.pdf PDF
06 E. Laughlin Installation Facility Standards.pdf PDF
09 Wage Determination_TX20250090_03Jan25.pdf PDF
08 G. Progress Schedule Form and Contract Progress Report.xlsx XLSX spreadsheet
11 Past Performance Questionnaire.pdf PDF
12 AF Form 3000.pdf PDF
13 AF Form 103 Work Clearance Request.pdf PDF
Show all 20

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Submittals Schedule SCHEDULE OF SUBMITTALS PROJECT # MXDP 24-1015 PROJECT TITLE Construct T-1A Static Display SOLICITATION / CONTRACT NO.

(To be completed by Project Engineer)(To be completed by Contract Administrator)
LINE NUMBERITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTALLAUGHLIN DIV 01 SPECIFICATIONSENVIRONMENTAL QUALITY CONSTRUCTION SPECIFICATIONS LAFBSTATEMENT OF OBJECTIVESNUMBER OF PAPER COPIES REQUIRED. DIGITAL COPIES ARE REQUIRED FOR ALL SUBMITTALSREQUIRED SUBMISSION DATEDATE RECEIVED IN CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATESUBMITTAL NUMBERSDATE CONTRACTOR NOTIFIEDCONTRACTOR RESUBMITTALFINAL APPROVALREMARKS

APPR

fergusog: Enter date the Contractor was notified of submittal approval

(MM/DD/YY)

DIS

fergusog: Enter date the Contractor was notified of submittal disapproval

(MM/DD/YY)

NTP 1 - Design
1Entry Access List (EAL)1.8.22 Weeks prior to base access
2Proof of OPSEC Training2.42 Weeks prior to base access
3Project and Progress Schedule3.2.1NLT 7 Days after NTP 1
465% Design Package3.2.22 (drawings only)NLT 60 Days after NTP 1
5Statement of Work3.3NLT 68 Days after NTP 1
695% Design Package3.2.3NLT 30 Days after Government Approved 65% Design
7100% Design Package3.2.42 (drawings only)NLT 30 Days after Government Approved 95% Design
8Progress Schedule Form and Contract Progress Report6.1.16.6Biweekly
9Meeting Minutes6.2.16.9NLT 3 Days after meeting
NTP 2 - Pre Construction
10Entry Access List (EAL)1.8.22 Weeks prior to base access
11AF Form 103, Work Clearance Request2.2NLT 1 week after NTP 2
12Proof of OPSEC Training2.42 weeks prior to base access
13Contractor Safety Plan3.2.2NLT 2 weeks after NTP 2
14Certificate of Contractor Safety Compliance3.2.3NLT 7 days after NTP 2
15QC Manager Qualifications4.2.3NLT 7 days after NTP 2
16QC Plan4.2.4NLT 3 weeks after NTP 2
17Meeting Minutes6.2.16.9NLT 3 Days after meeting
18Construction Site Plan12.1NLT 30 days after NTP 2
19Hazardous Material Approval (Safety Data Sheets)3.2.1NLT 30 days after NTP 2 (as required)
20Hazardous Waste Training Certificate3.2.2NLT 30 days after NTP 2 (as required)
21Laydown Area Request3.3.114 days prior to mobilization (as required)
22Public Water System Notification3.4.1NLT 30 days after NTP 2 (as required)
23Customer Service Inspection Certificate (TCEQ Form 20699)3.4.1NLT 3 weeks after NTP 2 (as required)
24TCEQ Public water system plan review submittal form (TCEQ Form 10233)3.4.1NLT 30 days after NTP 2 (as required)
25Clean Water Act TCEQ’s General Permit3.4.2NLT 30 days after NTP 2 (as required)
26Copy of notification to Department of State Health Services3.5.2.1NLT 10 days prior to construction start
27Worker/Area Protection Plan3.5.2.2NLT 3 weeks after NTP 2 (as required)
28Submittals per Contractor's Design / SOW10.4.4 through 10.4.113TBD
NTP 3 - Construction
29Non-Hazardous Waste Disposal Manifest and/or Waste Shipment Record5.1/6.2NLT 45 days from the date of signature of receiving facility
30Hazardous Waste Disposal Manifests5.2/6.2As required, prior to removal from Government property
31Hazmat Usage Log6.1End of each month during construction
32QC Daily Inspection Reports4.2.6Weekly
33Progress Schedule Form and Contract Progress Report6.1Biweekly
34Meeting Minutes6.2.1NLT 3 Days after meeting
35Records of Existing Conditions7.1.1NLT 14 days after NTP 2
36Materials Testing7.1.3As required, within 7 days of test
37Submittals per Contractor's Design SOW10.4.4 through 10.4.113TBD
38Operation and Maintenance Data10.4.12NLT 2 weeks after Final Inspection
39As Built Drawings/CAD Files10.4.133.42 (D size)NLT 2 weeks after Final Inspection
40Completion Inspection (QC Manager Punchlist)13.46.7, 6.8NLT 3 days after Pre-Final Inspection
41Draft DD Form 135413.36.7Prior to Pre-Final Inspection
42Final DD Form 135413.36.8At Final Inspection
44Construction Warranty Management Plan13.2NLT 2 weeks after Final Inspection

Task Order # FA3099-16-D-0002-0002 SOW Atch 2