This document contains a federal contract solicitation for repair work at Camp Rilea, Oregon. The solicitation seeks offers for repairs to the 116th Air Control Squadron Operations and Training Building located at Camp Rilea, with an estimated budget between $5 million and $10 million. The North American Industry Classification System code for this work is 236220. The solicitation sets aside this opportunity for small businesses only, with a small business size standard of $36.5 million. Offerors must submit relevant past performance examples using the template in Exhibit A. The point of contact for additional information is through the pre-proposal conference site visit. The agency issuing this solicitation is the Department of the Army Oregon Army National Guard. Funding availability is anticipated by September 30, 2020, with award being made based on best value as outlined in the solicitation.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W50S8Y-20-R-5000 Camp Rilea ANG Station Repair 116th ACS O&T B7116

EXHIBIT A – Performance Relevancy

PART 1: Provide the following information for each project submitted to support performance relevancy. The information MUST be provided in the format below. Prepare not more than three (3) of these documents.

Contractors should select their projects carefully. The quality of the contractor’s relevant performance is more important than the quantity of projects submitted. Projects must be complete prior to the solicitation date issue date.

Project completion date cannot be any older than 5 years prior to the solicitation issue date. Provide frank, concise comments regarding your performance on the contracts you identify. Use as much space as required.

1A. Offeror Name (You) and Company/Division:

1B. Project/Contract Title:

1C. Contract Specifics

1. Performance was as the Prime or Subcontractor:

2. Contract Number:

3. Original Contract $ Value:

4. Final Contract $ Value:

5. If amounts in 3 above are different, provide a brief description of the reason:

6. Completion Date

a. Original Date:

b. Actual Completion Date:

7. Number of and Causes for Contract Modifications:

1D. Provide a detailed description of the work performed under the contract including. Note that your description will be evaluated for similarity of the construction methods, project scope; cost magnitude, and complexity of work performed to those required for the proposed effort. The Government may also consider similarity of the client type (i.e. federal government). The location at which work was performed maybe considered against the location at which work will be performed.

1. Describe the specific elements of the work performed by your firm.

2. Indicate what elements of work were performed by your major subcontractors and if those same subcontractors will be used on this project. If you intend to use these subcontractors, please list name and principal areas of work they will perform. Indicate if you do not intend on utilizing any of these subcontractors.

3. Address any technical areas about this project you consider uniquely relevant to this project.

4. If you intend to use any of the same key personnel on this solicitation’s project, indicate by name and position those personnel proposed to be utilized on the referenced contract. (Project Manager, Site Superintendent, Quality Control Manager). Indicate what position they will have on this solicitation’s contract. Indicate if you do not intend on utilizing any of these same personnel.

5. Describe why you believe the work is very relevant, relevant or semi-relevant to this solicited project. (see section 00120 for information.) (Use as much space as necessary)

W50S8Y-20-R-5000 Camp Rilea ANG Station Repair 116th ACS O&T B7116

1E. List a point of contact for the owner, government agency Contracting Officer and/or inspector for the project;

include a current phone number and email address. (This information is required here even though you will be sending Exhibit C letters and questionnaires to these references. (Do NOT include a copy of the Exhibit Cs you sent to your references.)

End of Part 1 - Questionnaire Requirements – Prepare and send Exhibit C Package to the reference(s) for each of projects discussed in the Exhibit As.

PART 2: Additional offeror information. This information is required, but is not project specific. This information only needs to be provided once in your submission package.

2A. Applicable to all offerors - Describe your compliance with the requirements of FAR clause 52.219-8, Utilization of Small Business Concerns. This is required even if you are a Small or Small Disadvantaged Business.

It is the policy of the United States that small business concerns, veteran-owned small business concerns, service-disabled veteran-owned small business concerns, HUBZone small business concerns, small disadvantaged business concerns, and women-owned small business concerns shall have the maximum practicable opportunity to participate in performing contracts let by any Federal agency. It is also policy to establish procedures to ensure the timely payment of amounts due pursuant to the terms of their subcontracts. Describe below the methods you have used to comply with this policy on prior Federal contracts. Include any evidence, or a point of contact to verify this information, if available.

2B: Offerors are strongly encouraged to include with their proposals information on problems encountered on relevant projects and the specific corrective actions taken to remedy the problem(s).

2C: List any projects within the last five (5) years that have been assessed liquidated damages. If none have been assessed, make a positive statement to that effect.

2D: List any projects within the last five (5) years that have been terminated, for any reason. Provide an explanation. If none, make a positive statement to that effect.

2E. Compliance with Safety Standards. Provide proof of your Experience Modification Rate (EMR).

End of Questionnaire Requirements