About this file

This is an Invitation to Bid (ITB) solicitation document issued by the Connecticut Department of Transportation for the rehabilitation of Bridge No. 06770, an unnamed brook culvert crossing on State Route 796 (Milford Parkway Extension) in the City of Milford. The project scope involves installation of a 65-inch outside-diameter glass-fiber reinforced polymer pipe liner within an existing 72-inch corrugated metal pipe culvert, including cleaning and repair of the existing structure, construction of inlet and outlet cutoff walls and wingwalls, preformed scour hole installation, surface repair concrete for headwalls, temporary earth retaining systems, a 12-by-12-foot temporary access tunnel, and comprehensive water management systems. The bid solicitation opened August 5, 2026 at 7:00 a.m. EDT with bids due September 2, 2026 at 2:00 p.m. EDT. No pre-bid conference or mandatory site visit is required. Prospective bidders must be prequalified with the Connecticut Department of Transportation and maintain a current sworn Statement (CON 16) at least 30 calendar days before requesting the official Bid Proposal Form. Pre-bid questions close at 9:00 a.m. on the Monday before the Wednesday bid opening through the CTDOT Pre-Bid Q and A Website. Bids must be submitted electronically through Bid Express (bidx.com) only.

The estimated contract value falls between $1,000,000 and $2,499,999 under federal funding with Scope Code E classification. The project is designated as Work Classification 8B (Pipe Culverts/Culvert Linings) with a 0% Disadvantaged Business Enterprise (DBE) goal and no Small Business Enterprise (SBE) set-aside requirement. Bidders must submit a bid bond equal to at least 30% of the bid amount in PDF format via email to dotbid@ct.gov prior to bid opening, with the original signed bond from the low bidder required within 7 days of opening; the surety must be a corporate surety licensed by the Connecticut Insurance Commissioner. Prevailing wage rates established by the Connecticut State Labor Commissioner apply to all labor classifications. Environmental constraints include restriction of in-stream work to June 1–September 30, prohibition on tree removal three inches or greater in diameter from April 15 to October 31 for tri-colored bat protection, and adherence to Connecticut Department of Transportation Standard Specifications for Roads, Bridges, Facilities and Special Provisions (Form 819, dated 2024) and AASHTO LRFD Bridge Design Specifications (Ninth Edition, 2020). A critical utility consideration involves protection and coordination of a high-pressure 24-inch gas main located approximately 16 feet below existing grade with the Iroquois Pipeline utility representative during all construction activities. All bidding documents, plans, specifications, and addenda are available at no charge on the DAS State Contracting Portal (CTsource Bid Board).

View the file

Other files

File Type Posted
0083-0270_Bridge06770_06_FIO_Gas.pdf PDF
HW_CB_0083-0270_Alignment Ramp.dgn —
CTDOT_HIGHWAY_STD [02-10-25].pdf PDF
HW_CB_0083-0270_Alignment East Access Rd_ATW1.dxf DXF file
SV_D4_0170_3250_MILFORD_CONNECTOR_BR06770_GRN_Additional.dxf DXF file
TR_CP_0083_0270_MPT_MDL.dgn —
HW_CB_0083-0270_Alignment West Access Rd.dgn —
West Access Rd.xml XML file
HW_CB_0083-0270_Master_ATW1.dxf DXF file
0083-0270_Aug_5_26_solicitation_doc.pdf PDF
BR_CP_0083-0270_Bridge06770Model.dgn —
NTC - Bidx Enhanced Bidding Workflow-Rev April 2026.pdf PDF
HW_CB_0083-0270_Alignment West Access Rd.dxf DXF file
Electronic Bidding Instructions -Rev April 2026.pdf PDF
0083-0270_Bridge06770_04_Structures.pdf PDF
SV_D4_0170_3250_MILFORD_CONNECTOR_BR06770_GRN_Additional_Annotation.dxf DXF file
HW_CB_0083-0270_Alignment 72 Pipe.dxf DXF file
SV_D4_0170_3250_MILFORD_CONNECTOR_BR06770_GRN.dxf DXF file
NTC - New DBE Requirements - Regular Dealer Affirmation Form.pdf PDF
Online Q and A Instruction.pdf PDF
HW_CB_0083-0270_Layout_ATW1.dgn —
Bidders Checklist.pdf PDF
SV_D4_0170_3250_MILFORD_CONNECTOR_BR06770_GRN_Annotation.dxf DXF file
Milford Connector Ramp.xml XML file
SV_D4_0170_3250_MILFORD_CONNECTOR_BR06770_GRN_102(10.12)_Annotation.dxf DXF file
HW_CB_0083-0270_Alignment Ramp.dxf DXF file
HW_CB_0083-0270_Layout_ATW1_Default.dxf DXF file
EEDFileManifest.xlsx XLSX spreadsheet
HW_CB_0083-0270_Alignment 72 Pipe.dgn —
CL_72_PIPE.xml XML file
0083-0270_Bridge06770_02_Revisions.pdf PDF
HW_CB_0083-0270_Master_ATW1_ALI-GEOMETRY-CURVE.dxf DXF file
HW_CB_0083-0270_Alignment East Access Rd_ATW1.dgn —
PROSPECTIVE BIDDERS - 2.pdf PDF
HW_CB_0083-0270_Layout_ATW1.dxf DXF file
SV_D4_0170_3250_MILFORD_CONNECTOR_BR06770_GRN_Boundary.dxf DXF file
SV_D4_0170_3250_MILFORD_CONNECTOR_BR06770_GRN_102(10.12).dxf DXF file
HW_CB_0083-0270_Master_ATW1_highway plan Existing.dxf DXF file
HazMat Inspection Letter.pdf PDF
PROSPECTIVE BIDDERS - 1.pdf PDF
East Access Rd ATW1.xml XML file
0083-0270 Contract Special Provisions.pdf PDF
SV_D4_0170_3250_MILFORD_CONNECTOR_BR06770_GRN_102(10.12)_Boundary.dxf DXF file
SV_D4_0170_3250_MILFORD_CONNECTOR_BR06770_GRN_102(10.12).dgn —
SV_D4_0170_3250_MILFORD_CONNECTOR_BR06770_GRN_Additional_Boundary.dxf DXF file
0083-0270 Contract Special Provisions.pdf.crdownload CRDOWNLOAD file
BR_CP_0083-0270_Bridge06770Model.dxf DXF file
BR_CP_0083-0270_Bridge06770Details.dgn —
BR_CP_0083-0270_Bridge06770Details.dxf DXF file
0083-0270 Invitation to Bid.pdf PDF
Show 40 more

Latest 50 of 58 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation Number: 0083-0270

Rehabilitation of Bridge No. 06770 in the City of Milford

Invitation to Bid (ITB)

Transportation, Dept. of

August 05, 2026 - September 02, 2026

Page:2

General Header Information

This bid has no questions defined.

0083-0270

No. 0083-0270 Title: Rehabilitation of Bridge No. 06770 in the City of Milford Start Date: August 05, 2026 at 7:00:00 AM EDT End Date: September 02, 2026 at 2:00:00 PM EDT Vendor Q&A Start Date:

Vendor Q&A End Date:

Estimated Total Value:

Who can respond to this bid? : All Vendors Description:

Delivery Terms: N/A: Not Applicable Payment Terms: See Payment Notes Payment Notes: See Special Provisions Contact Information: Transportation, Dept. of

Nydia Cotto 2800 Berlin Turnpike Newington CT, 06111 United States Tel: 8605943123 Fax:

Nydia.cotto@ct.gov

Contact Details: If you have any questions, please contact:

Nydia Cotto 2800 Berlin Turnpike Newington CT, 06111 United States Tel: 8605943123 Fax:

Nydia.cotto@ct.gov

Selected Categories:

Page:3

Documents:

0083-0270 Contract Plans.zip

HazMat Inspection Letter.pdf

Bidders Checklist.pdf

Electronic Bidding Instructions -Rev April 2026.pdf

NTC - Bidx Enhanced Bidding Workflow-Rev April 2026.pdf

NTC - New DBE Requirements - Regular Dealer Affirmation Form.pdf

Online Q and A Instruction.pdf

EED_0083-0270.zip

0083-0270 Invitation to Bid.pdf

0083-0270 Contract Special Provisions.pdf

PROSPECTIVE BIDDERS - 1.pdf

PROSPECTIVE BIDDERS - 2.pdf

Page:4

Item Specifications Solicitation has been designated as having no line items.

Page:5

File details come from the government source that posted it. Updated .