0013Q Corridor-Ashaway_DOQ Index Page_5_Addendum-2.pdf

PDF 604 KB Posted

Attached to
Corridor - Ashaway
Solicitation number
TCB26006498
Issued by
Providence County, Rhode Island

About this file

This is an addendum index page for the Corridor-Ashaway project, a bridge replacement initiative managed by the Rhode Island Department of Transportation under Federal-Aid Highway program funding (FAP Number STP-3334(001)). The project involves replacement of three bridges spanning bodies of water in Providence County, with proposals due August 28, 2026 at 1:00 p.m. EDT. The scope of work encompasses guardrail connections and end treatments, concrete and asphalt sidewalks and driveways, curbing, mailbox post replacement, concrete bounds, riprap installation, and temporary traffic protection. Specific item quantities include eight guardrail connections to end posts, 225 square yards of Portland cement concrete sidewalks, 700 square yards of asphalt concrete sidewalks, 775 linear feet of precast concrete curb, 1,150 square yards of riprap (R-6, R-7, R-8), 24 rural mailbox posts, 16 test pits, and one lump sum mobilization and temporary traffic protection item. The Field Office component is estimated at 31 project manager-office (PMO) units. Phased completion deadlines are November 10, 2027 for the Ashaway River Bridge and August 14, 2028 for the Potter Hill Bridge, with substantial completion required by October 23, 2028.

The project is federally funded with 80 percent FHWA funding and 20 percent state funding. All work is subject to Davis-Bacon prevailing wage requirements effective May 18, 2026, and Buy America compliance mandates requiring 55 percent domestic content for manufactured products. Liquidated damages are assessed at $3,500 per day for phase completions and $1,950 per day for substantial completion milestones. Lump sum item breakdowns are due within 70 days of apparent low bidder notification. A 5 percent bid bond and 100 percent performance bond are required. Mandatory insurance includes $1,000,000 general liability and workers' compensation coverage. A 0.33 percent contract administrative fee applies to all proposals, which must be submitted electronically through Ocean State Procures, with vendor questions due August 19, 2026 at 12:00 p.m. EDT.

View the file

Other files

File Type Posted
TCB26006498_Sep_16_26_solicitation_doc.pdf PDF
0013Q_V2_015_52_BEAMDETL_REV1.pdf PDF
0013Q_V1_ 013-023_GENERAL PLAN NO. 1_REV1.pdf PDF
0013Q Corridor-Ashaway_DOQ Item 201.0432_Addendum-2.pdf PDF
0013Q Corridor-Ashaway_DOQ Item 203.0310_Addendum-2.pdf PDF
0013Q Corridor-Ashaway_DOQ Item 201.0321_Addendum-2.pdf PDF
TCB26006498_Oct_9_26_solicitation_doc.pdf PDF
0013Q Corridor-Ashaway_CS Pages CS-11_Addendum-2.pdf PDF
2026-CB-019_Plan_File_V1.pdf PDF
2026-CB-019_Plan_File_V2.pdf PDF
TCB26006498_Sep_11_26_solicitation_doc.pdf PDF
TCB26006498_Oct_2_26_solicitation_doc.pdf PDF
0013Q Corridor-Ashaway_DOQ Item 401.3000_Addendum-2.pdf PDF
0013Q Corridor-Ashaway_DOQ Index Page_2_Addendum-2.pdf PDF
0013Q Corridor-Ashaway_DOQ Index Page_1_Addendum-2.pdf PDF
TCB26006498_Oct_15_26_solicitation_doc.pdf PDF
2026_February_Standard_Specifications.zip.crdownload CRDOWNLOAD file
2026-CB-019-Corridor-Ashaway_CS_Pages.pdf PDF
TCB26006498_Aug_3_26_solicitation_doc.pdf PDF
TCB26006498_Aug_31_26_solicitation_doc.pdf PDF
0013Q Corridor-Ashaway_DOQ Item 920.0330_Addendum-2.pdf PDF
TCB26006498_Oct_6_26_solicitation_doc.pdf PDF
0013Q Corridor-Ashaway_DOQ Item 201.0403_Addendum-2.pdf PDF
0013Q Corridor-Ashaway_DOQ BR005151_Addendum-2.pdf PDF
2026-CB-019-Corridor-Ashaway_CS_Pages.pdf.crdownload CRDOWNLOAD file
Federal Wage Rates 5-18-2026.pdf PDF
2026-CB-019-Corridor-Ashaway_JS_Pages.pdf PDF
TCB26006498_Sep_10_26_solicitation_doc.pdf PDF
0013Q Corridor-Ashaway_DOQ Item 841.0100_Addendum-2.pdf PDF
0013Q Corridor-Ashaway_DOQ Item 201.0417_Addendum-2.pdf PDF
TCB26006498_Oct_8_26_solicitation_doc.pdf PDF
0013Q Corridor-Ashaway_DOQ Index Page_4_Addendum-2.pdf PDF
TCB26006498_Oct_16_26_solicitation_doc.pdf PDF
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Item Code Description Quantity UOM

Distribution of Quantities

0013Q Corridor - Ashaway

Estimate Name - PS&E Estimate

R.I. Contract No. - 2026-CB-019

FAP No. STP3334001

901.1050 GUARDRAIL CONNECTION TO END POST 8 EACH

901.1100 STEEL BEAM GUARDRAIL APPROACH END TREATMENT 7 EACH

901.1200 GUARDRAIL END TREATMENT PLATFORM 7 EACH

901.1300 STEEL BEAM GUARDRAIL AND ANCHORAGE TRAILING END SECTIONS 7 EACH

905.1000 PORTLAND CEMENT CONCRETE SIDEWALKS AND DRIVEWAYS 225 SY

905.2000 ASPHALT CONCRETE SIDEWALKS AND DRIVEWAYS 700 SY

906.0310 GRANITE CURB 120 LF

906.0320 PRECAST CONCRETE CURB 775 LF

906.0700 REMOVE, HANDLE, HAUL TRIM RESET CURB EDGING, STRAIGHT, CIRCULAR ALL TYPES 170 LF

915.0200 HIGHWAY BOUNDS REINFORCED CONCRETE STANDARD 14.1.0 2 EACH

917.0105 REMOVE & REPLACE RURAL MAILBOX POST WITH STD 15.1.0 24 EACH

917.0106 REMOVE AND REPLACE MULTIPLE MAILBOX MOUNTING WITH STANDARD 15.2.0 2 EACH

918.0200 RURAL MAILBOXES 2-DOOR 10 EACH

919.0101 TEST PITS 16 EACH

920.0320 RIPRAP R-3, R-4, R-5 STANDARD 8.3.0 65 SY

920.0330 RIPRAP R-6, R-7, R-8 STANDARD 8.3.0 1150 SY

929.0110 FIELD OFFICE 31 PMO

936.0110 MOBILIZATION 1 LS

937.0100 FURNISH, INSTALL, MAINTAIN, AND MOVE TEMPORARY TRAFFIC PROTECTION 1 LS

joseph.skymba Cloud joseph.skymba Stamp

File details come from the government source that posted it. Updated .