This is a bid tabulation document for Request for Bids (RFB) No. S-73000-00013702 issued by the State of Oregon for pavement work on OR99E at the Hubbard Weigh Station. The project involves cold planing pavement removal and overlay work on both the northbound (NB) and southbound (SB) lanes, including asphalt concrete pavement (ACP) placement and pavement markings. Five contractors submitted bids by the May 13, 2025, 2:00 PM deadline: Eagle-Elsner Inc, Knife River Corporation - Northwest, North Santiam Paving Co, Roy Houck Construction LLC, and Brix Paving Northwest Inc. The estimated quantities include 4,267 square yards of NB cold plane removal, 2,667 square yards of SB cold plane removal, 480 tons of NB ACP mixture, 300 tons of SB ACP mixture, and 2,600 linear feet of pavement markings across both directions.
The low bid of $113,423.00 was submitted by Eagle-Elsner Inc, with bids ranging up to $165,520.00 from Brix Paving Northwest Inc. Unit pricing varied significantly across bidders, particularly for cold plane pavement removal (ranging from $2.26 to $5.00 per square yard) and ACP mixture (ranging from $92.00 to $140.00 per ton). The bid tab reflects the standard unit pricing and total price columns for each line item across all five competing contractors, providing the basis for contract award determination based on low bid criteria.
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| RFB No.: | S-73000-00013702 | BIDDER | |||||
| NAME: | Eagle-Elsner Inc | Knife River Corporation - Northwest | North Santiam Paving Co | Roy Houck Construction LLC | Brix Paving Northwest Inc | ||
| Bids due: | 5/13/2025 2:00 pm | ||||||
| Description: | OR99E Hubbard NB and SB Weigh Station Paving |
| Bid Item # | Description | Est | |
| QTY | UNIT | UNIT | |
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL |
PRICE
| 1 | Mobilization | 1 | LS | $ 8,500.00 | $ 8,500.00 | $ 9,635.00 | $ 9,635.00 | $ 6,000.00 | $ 6,000.00 | $ 9,700.00 | $ 9,700.00 | $ 13,000.00 | $ 13,000.00 |
| 2 | Temporary Work Zone Traffic Control, Complete | 1 | LS | $ 5,987.40 | $ 5,987.40 | $ 9,380.00 | $ 9,380.00 | $ 3,600.00 | $ 3,600.00 | $ 7,950.00 | $ 7,950.00 | $ 4,000.00 | $ 4,000.00 |
| 3 | Pollution Control Plan | 1 | LS | $ 110.00 | $ 110.00 | $ 50.00 | $ 50.00 | $ 50.00 | $ 50.00 | $ 100.00 | $ 100.00 | $ 100.00 | $ 100.00 |
| 4 | NB - Cold Plane Pavement Removal, 2" Deep | 4,267 | SQ YD | $ 2.90 | $ 12,374.30 | $ 2.75 | $ 11,734.25 | $ 2.50 | $ 10,667.50 | $ 2.26 | $ 9,643.42 | $ 5.00 | $ 21,335.00 |
| 5 | Level 3, 1/2" Dense ACP Mixture (PG64-22) | 480 | TON | $ 92.00 | $ 44,160.00 | $ 94.00 | $ 45,120.00 | $ 110.00 | $ 52,800.00 | $ 107.25 | $ 51,480.00 | $ 140.00 | $ 67,200.00 |
| 6 | Longitudinal Pavement Markings - Paint, Extruded or Sprayed, Surface | 1,600 | FOOT | $ 1.65 | $ 2,640.00 | $ 1.05 | $ 1,680.00 | $ 1.50 | $ 2,400.00 | $ 1.50 | $ 2,400.00 | $ 1.75 | $ 2,800.00 |
| 7 | SB - Cold Plane Pavement Removal, 2" Deep | 2,667 | SQ YD | $ 3.90 | $ 10,401.30 | $ 2.75 | $ 7,334.25 | $ 2.50 | $ 6,667.50 | $ 2.26 | $ 6,027.42 | $ 5.00 | $ 13,335.00 |
| 8 | Level 3, 1/2" Dense ACP Mixture (PG64-22) | 300 | TON | $ 92.00 | $ 27,600.00 | $ 94.00 | $ 28,200.00 | $ 110.00 | $ 33,000.00 | $ 107.25 | $ 32,175.00 | $ 140.00 | $ 42,000.00 |
| 9 | Longitudinal Pavement Markings - Paint, Extruded or Sprayed, Surface | 1,000 | FOOT | $ 1.65 | $ 1,650.00 | $ 1.05 | $ 1,050.00 | $ 1.50 | $ 1,500.00 | $ 1.50 | $ 1,500.00 | $ 1.75 | $ 1,750.00 |
| $ 113,423.00 | $ 114,183.50 | $ 116,685.00 | $ 120,975.84 | $ 165,520.00 |